El Paso Natural Gas Company v. Federal Energy Regulatory Commission

50 F.3d 23, 311 U.S. App. D.C. 52, 1995 U.S. App. LEXIS 5550
CourtCourt of Appeals for the D.C. Circuit
DecidedMarch 21, 1995
Docket94-1059
StatusPublished

This text of 50 F.3d 23 (El Paso Natural Gas Company v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
El Paso Natural Gas Company v. Federal Energy Regulatory Commission, 50 F.3d 23, 311 U.S. App. D.C. 52, 1995 U.S. App. LEXIS 5550 (D.C. Cir. 1995).

Opinion

50 F.3d 23

311 U.S.App.D.C. 52, Util. L. Rep. P 14,035

EL PASO NATURAL GAS COMPANY, Petitioner,
v.
FEDERAL ENERGY REGULATORY COMMISSION, Respondent.
Public Utilities Commission of the State of California;
Arizona Public Service Company; Salt River Project
Agricultural Improvement and Power District; Meridian Oil
Inc.; San Diego Gas & Electric Company; Southern
California Gas Company; Southwest Gas Corporation;
Transwestern Pipeline Company, Intervenors.

No. 94-1059.

United States Court of Appeals,
District of Columbia Circuit.

Argued Feb. 28, 1995.
Decided March 21, 1995.

Petition for Review of an Order of the Federal Energy Regulatory Commission.

Richard C. Green, Washington, DC, argued the cause, for petitioner. With him on the briefs, were James R. McCotter, El Paso, TX, Mark F. Sundback, Peter J. Thompson, Washington, DC and Phillip D. Endom, El Paso, TX. Britton White, Jr., El Paso, TX, entered an appearance.

Eric L. Christensen, Atty., F.E.R.C., Washington, DC, argued the cause, for respondent. With him on the brief, were Jerome M. Feit, Sol., and Joseph S. Davies, Jr., Deputy Sol., F.E.R.C., Washington, DC.

Mark Fogelman, San Francisco, CA, argued the cause, for intervenors. With him on the joint brief, were Edward W. O'Neill, San Francisco, CA, for Public Utilities Commission of the State of California, Douglas M. Gleason, James P. Walsh and Nicholas W. Fels, Washington, DC, for San Diego Gas & Electric Co. and David J. Gilmore, Los Angeles, CA, for Southern California Gas Co. Barbara S. Jost and Joel L. Greene, Washington, DC, entered appearances, for Arizona Public Service Co. and Salt River Project Agricultural Improvement and Power Dist. Kim M. Clark, Washington, DC, entered an appearance, for Meridian Oil Inc. John C. Walley, Las Vegas, NV, entered an appearance, for Southwest Gas Corp. Sherrie N. Rutherford, Houston, TX, and Steve Stojic, Washington, DC, entered appearances, for Transwestern Pipeline Co.

Before EDWARDS, Chief Judge, WALD and RANDOLPH, Circuit Judges.

Opinion for the Court filed by Circuit Judge WALD.

WALD, Circuit Judge:

Petitioner El Paso Natural Gas Company ("El Paso") seeks review of two orders of the Federal Energy Regulatory Commission holding that a proposal by two local distribution companies ("LDCs") located in California to extend their pipeline network into Mexico would not bring the network within the Federal Energy Regulatory Commission's ("FERC" or "Commission") jurisdiction under Secs. 4 and 7 of the Natural Gas Act ("NGA" or "Act"). 15 U.S.C. Secs. 717c, 717f (1988). El Paso argues that FERC's determination contravened both the terms of the NGA and Commission precedent. We hold that El Paso lacks standing because it has failed to demonstrate aggrievement or a likelihood of imminent injury under the challenged rulings, and we therefore dismiss the petition without reaching the merits.

I. BACKGROUND

A. Regulatory Background

The NGA regulates the transportation and sale of natural gas in interstate commerce. Three sections of the Act are particularly relevant to this case. Section 7 provides that "[n]o natural-gas company1 or person which will be a natural-gas company upon completion of any proposed construction or extension shall engage in the transportation or sale of natural gas" without first obtaining a certificate of public convenience and necessity from the Commission. Id. at Sec. 717f(c)(1)(A). Section 4 requires that "natural-gas companies" must maintain their rates for transportation or sale of gas on file with the Commission. Id. at Sec. 717c(c).

Section 3 of the NGA is broader in scope than Secs. 4 and 7. It requires that the Commission must approve the exportation or importation of natural gas by any "person" unless it finds that the project "will not be consistent with the public interest." Id. at Sec. 717b. Because this section addresses "person[s]," rather than "natural-gas companies," the need for compliance with Sec. 3 extends to all importers or exporters of natural gas, regardless of whether they operate in interstate commerce.2

The "Hinshaw Amendment," contained in Sec. 1(c) of the NGA, exempts certain facilities that transport or sell "interstate" gas but that are located within a single state from many provisions of the NGA, including Secs. 4 and 7:

The provisions of this chapter shall not apply to any person engaged in ... the transportation in interstate commerce or the sale in interstate commerce for resale, of natural gas received by such person from another person within ... a State if all the natural gas so received is ultimately consumed within such State, or to any facilities used by such person for such transportation or sale, provided that the rates and service of such person and facilities be subject to regulation by a State commission. The matters exempted from the provisions of this chapter by this subsection are declared to be matters primarily of local concern and subject to regulation by the several states.

15 U.S.C. Sec. 717(c) (1988). Because the Hinshaw Amendment exempts "Hinshaw pipelines" only from aspects of the NGA "subject to regulation by a State Commission," and state commissions have no authority to approve exportation or importation of natural gas, the requirements of Sec. 3 apply even to Hinshaw pipelines. See, e.g., Empire State Pipeline, 64 F.E.R.C. p 61,035 at 61,335-36 (1993).

B. Factual Background

Petitioner El Paso transports natural gas in interstate commerce from various gas sources to distributors. It is a "natural-gas company," as defined by the NGA, 15 U.S.C. Sec. 717(a)(6), and is therefore subject to FERC's Secs. 4 and 7 jurisdiction.

Among El Paso's customers are two LDCs, San Diego Gas & Electric Company ("SDGE") and Southern California Gas Company ("SoCal"), whose pipeline network serves southern California. The LDCs are Hinshaw pipelines, and so exempt from FERC regulation under Secs. 4 and 7 of the NGA. Their rates, services, and facilities are regulated by the Public Utilities Commission of the State of California ("CPUC").

This case involves a proposal ("Project Vecinos") by the LDCs to extend their service into Baja California, in Mexico. The Project contemplates construction of 110 miles of new pipeline in California, primarily to transport gas to Mexico, but which would also convey gas for consumption in California. In addition, Project Vecinos would require the LDCs to construct and operate a border crossing facility at the Mexican frontier, including a 2.1 mile pipeline (the "Otay Mesa Extension") that would connect the LDCs network to a Petroleos Mexicanos facility.

C. Procedural Background

In December 1992, SDGE applied to the Commission for Sec. 3 authorization and a Presidential Permit to construct the Otay Mesa Extension.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
50 F.3d 23, 311 U.S. App. D.C. 52, 1995 U.S. App. LEXIS 5550, Counsel Stack Legal Research, https://law.counselstack.com/opinion/el-paso-natural-gas-company-v-federal-energy-regulatory-commission-cadc-1995.