El Escorial Owners' Ass'n v. DLC Plastering, Inc.

65 Cal. Rptr. 3d 524, 154 Cal. App. 4th 1337
CourtCalifornia Court of Appeal
DecidedSeptember 6, 2007
DocketB173829
StatusPublished
Cited by66 cases

This text of 65 Cal. Rptr. 3d 524 (El Escorial Owners' Ass'n v. DLC Plastering, Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
El Escorial Owners' Ass'n v. DLC Plastering, Inc., 65 Cal. Rptr. 3d 524, 154 Cal. App. 4th 1337 (Cal. Ct. App. 2007).

Opinion

Opinion

GILBERT, P. J.

Defendants are found liable for negligence in a multiparty construction defect case. The trial court gives them partial credits for damages paid in good faith settlements before trial by jointly liable defendants. This assures a fair and appropriate distribution of damages. Plaintiff does not receive a double recovery. Nor do the nonsettling defendants bear a disproportionate share of damages. The trial court has acted within its discretion.

Plaintiff El Escorial Owners’ Association (Escorial), a condominium association, appeals a judgment, partially in its favor, in its construction defect action against defendants DEC Plastering, Inc. (DEC), Alderman Construction, Inc. (Alderman), Coastline Painting & Drywall, Inc. (Coastline), Mid-Cal Painting & Drywall, Inc. (Mid-Cal), and Pyramid Tile Company (Pyramid). DEC and Alderman appeal the damage judgments entered against them. Coastline, Mid-Cal, and Pyramid prevailed at trial, but appeal the orders that reduce their attorney fees. Defendant and cross-complainant Investec Construction, Inc. (Investec), which settled and assigned its causes of action to Escorial, appeals and joins on the side of Escorial.

The trial court found that DEC’S and Alderman’s latent construction defects caused $8.6 million in damages to Escorial. It gave them credits, however, for a prior good faith settlement between Escorial and other contractors. This reduced DLC’s and Alderman’s combined obligation to *1344 $2,461,495. The court also ruled that Escorial could not maintain a nuisance cause of action for construction defects.

Among other things, we conclude that Escorial did not state a valid nuisance cause of action; the good faith settlement proceedings were adversarial and fair; and the court gave proper settlement credits to DEC and Alderman. The statutes of limitations were tolled pursuant to the Calderon Act (Civ. Code, § 1375). Escorial’s action was timely because the construction defects fell within the statute of limitations and there is substantial evidence that Alderman caused damage to Escorial. The trial court properly rejected Alderman’s claim that it was exempt from liability because it complied with the project’s building plans. We also conclude that the collateral source rule applied, DEC agreed to indemnify the builder, the court properly awarded Escorial its expert fees as damages and did not abuse its discretion by reducing Coastline’s, Mid-Cal’s and Pyramid’s request for attorney fees. We affirm.

FACTS

Escorial is the condominium association for four, 3-story buildings housing 261 condominiums. These units were originally apartments in a complex owned and operated by another company. Between 1990 and 1996, the apartments were converted to condominiums in a four-phase construction project.

Viola, the initial construction contractor for the condominium conversion, required its subcontractors to sign indemnity agreements to hold Viola harmless for construction defects. Viola’s services were terminated before the completion of the project. Investec, the new builder, agreed to complete the construction and required Viola’s subcontractors, which included DEC, to sign an assumption agreement. The subcontractors agreed to indemnify the new builder, Investec.

As Investec completed construction, it formed a homeowners association and managed the condominium project. The Investec Management Corporation controlled the daily operations of the association. The Escorial homeowners assumed the management of the condominium association in July of 1995 and on June 15, 1996, “assumed voting control” of the board. Escorial discovered a series of construction defects.

On June 28, 1996, Escorial gave notice that it was proceeding under the Calderon Act (Civ. Code, former § 1375, as added by Stats. 1995, ch. 864, § 1, p. 6579) and demanded that Investec correct numerous construction defects. Escorial and Investec met over the next two years in an attempt to resolve the dispute.

*1345 In December of 1998, as negotiations continued, Escorial and Investec signed an agreement to toll the statute of limitations retroactive to December 1, 1996, and prospectively until the end of the negotiations. Ultimately, they were unable to resolve their differences about the repairs.

On March 31, 2000, Escorial filed a construction defect lawsuit against 35 contractors and subcontractors, alleging causes of action for negligence, nuisance, and breach of implied warranties. Defendant Investec cross-complained against its subcontractors for indemnity. Prior to trial, most of the defendants settled. The court approved good faith settlements totaling $10,629,759. Investec and its related entities contributed $5,649,999, and several subcontractors contributed $4,979,760. Escorial proceeded to trial against the subcontractors that did not settle. Investec had assigned its indemnity claims against these subcontractors to Escorial.

The defendants were Pyramid, an installer of bathtubs and windows; Mid-Cal and Coastline, painters; Alderman, a framing contractor; and DEC, a plastering contractor. DEC performed work in the 1991 and 1994 construction phases. Alderman began work in the 1994 and 1996 phases. The parties agreed to a court trial.

For a period covering a year and a half before trial, the trial court approved numerous good faith settlements involving other defendants. These settlements did not specify particular construction defects attributable to any of these settling defendants. During a hearing involving the final settlement, the nonsettling defendants asked the trial court to apportion the amounts of settlement among the various settling contractors and relate those amounts to specific construction defects. In this way, the trial court could decide the extent to which each nonsettling defendant might be entitled to credits should it be found liable at trial.

Instead of continuing the trial date, or reopening the previously approved settlements, the trial court devised a plan. As the evidence unfolded at trial, the court would hold hearings on apportionment during which it would “make the decision on the allocations with the assistance of [Escorial and the nonsettling defendants.]” The parties did not object to this procedure.

As the trial progressed, the court held periodic hearings on apportionment in which the parties presented evidence and registered objections. The court made findings on the apportionment of liability and damages and approved a spreadsheet that listed categories of defects and damages and the amount attributable to each settling party within each category.

*1346 Liability of DLC and Alderman

Various experts testified at trial. Michael Shotwell, a construction expert, testified that Alderman’s framing work was deficient. He said it should have used “metal clips” to “structurally tie” the “upper plates into the walls.” Instead, it used nails to create a “nailing ledger,” an inadequate structure for the purpose of making that area watertight. As a result, moisture seeped into the walls causing water damage.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McFadyen v. County of Tehama CA3
California Court of Appeal, 2025
Torres v. Saied CA2/5
California Court of Appeal, 2025
West Sacramento Hospitality v. S.A.V. Texas CA3
California Court of Appeal, 2025
Chavez v. Cal. Collision
California Court of Appeal, 2024
Lynch v. Peter & Associates etc.
California Court of Appeal, 2024
Lynch v. Peter & Associates etc. CA4/3
California Court of Appeal, 2024
Wu v. ABC Lucky Transportation CA2/1
California Court of Appeal, 2024
Riley v. Quantumscape Corp.
N.D. California, 2023
Plyley v. Renovating Specialist, Inc. CA2/6
California Court of Appeal, 2022
Pacific West Group v. Interlandi CA2/8
California Court of Appeal, 2022
Currency Corp. v. Wertheim CA2/1
California Court of Appeal, 2021
Rickley v. Gulf Oil Corp. CA2/2
California Court of Appeal, 2021
Doe v. Westmont College
California Court of Appeal, 2021
Mass, Inc. v. Hughes
Ninth Circuit, 2021

Cite This Page — Counsel Stack

Bluebook (online)
65 Cal. Rptr. 3d 524, 154 Cal. App. 4th 1337, Counsel Stack Legal Research, https://law.counselstack.com/opinion/el-escorial-owners-assn-v-dlc-plastering-inc-calctapp-2007.