EKE Builders, Inc. v. Quail Bluff Associates

1985 OK CIV APP 46, 714 P.2d 604, 1985 Okla. Civ. App. LEXIS 84
CourtCourt of Civil Appeals of Oklahoma
DecidedDecember 24, 1985
Docket61411, 61710
StatusPublished
Cited by6 cases

This text of 1985 OK CIV APP 46 (EKE Builders, Inc. v. Quail Bluff Associates) is published on Counsel Stack Legal Research, covering Court of Civil Appeals of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
EKE Builders, Inc. v. Quail Bluff Associates, 1985 OK CIV APP 46, 714 P.2d 604, 1985 Okla. Civ. App. LEXIS 84 (Okla. Ct. App. 1985).

Opinion

BRIGHTMIRE, Presiding Judge.

Do material issues of fact exist which prevent a summary adjudication of this action? The trial judge concluded there were none and granted defendants a summary judgment. We hold, however, material issues exist and reverse.

I

On December 14, 1982, K & E Builders, later incorporated as EKE Builders, Inc., entered into a contract with Quail Bluff Associates, a partnership, for the construction of an apartment complex in Oklahoma County. 1 The contract required Quail *606 Bluff to pay plaintiff $7,165,923 for the building project and was contingent on Quail Bluffs obtaining a loan of not less than $6,500,000. The contract further provided that “[i]f such construction funds are not, for any reason, obtained and recorded for this project from time to time as required by the Owner [Quail Bluff], Owner may terminate this Agreement .... ”

On January 6, 1983, defendant Douglas Corvin allegedly notified EKE that the lender, RepublicBank Dallas, would not approve EKE as contractor under any circumstances. On that same date, defendants employed Western Construction Company, a competitive bidder, to handle the Quail Bluff project for $7,053,000. A construction loan commitment was issued by the bank on January 10, 1983, which, among other things, provided that Quail Bluff could not enter into any contract for construction on the property “except upon such terms and with such parties as shall be approved in writing by Lender.”

But to back up a bit. The facts are that, contrary to the Quail Bluff representation, RepublicBank mailed a letter to Quail Bluff dated January 6. It was received by Quail Bluff in an envelope bearing a postmark date of January 11, 1983, and said that “K & E Construction does not meet minimum underwriting standards. Consequently, they are not acceptable as general contractor for the Quail Bluff project without a $7,165,923.00 Payment and Performance Bond from a bonding company approved by RepublicBank Dallas.” (Emphasis added.) Without informing EKE of this or giving it the chance to comply with the bond requirement, Quail Bluff immediately entered into a contract with Western, finalized it on February 3, 1983, and obtained lender approval that same day.

Eventually, EKE Builders learned of Quail Bluffs deception and on January 19, 1983, notified defendants in writing that it regarded their actions as a total breach of its contract. Not realizing that Quail Bluff had already contracted with Western, Plaintiff advised defendants it was willing and able to post the required bond, demanded that defendants express a willingness to honor its contract, and asked to be granted 15 days to post the requisite performance bond. The letter further notified defendants that if such action was not taken litigation would be filed on January 25, 1983..

Defendants did not, of course, respond with the requested expression but instead procured a letter from the lending bank dated January 25 reciting that EKE had been unconditionally disapproved as contractor.

The next day, plaintiff EKE brought an action against Quail Bluff Associates, Douglas Corvin and J.R.W. Properties, seeking damages for the detriment it had sustained. Two causes of action were pleaded in an amended petition. One, sounding in tort, alleged that Quail Bluff made false representations concerning the bank’s requirements and generally failed to deal with plaintiff in good faith causing detriment to plaintiff in excess of $1,000,-000. The other cause was for breach of the contract. Among the allegations was one to the effect that EKE was at all times ready, willing, and able to produce such a bond. And it pleaded that its detriment was lost profits in the amount of $1,200,-000. A conspiracy between Quail Bluff and the bank to tortiously deprive plaintiff of its contractual benefits was not alleged.

Defendants moved for summary judgments on the ground that the lender’s disapproval of EKE as a contractor constituted a failure of a condition precedent to acceptance of the agreement, and therefore, there could have been no breach. Ignoring the tort issue, the trial court agreed with defendants and entered judgments in favor of all three of them based upon the legal conclusion that there was no breach *607 of the contract as pleaded by EKE Builders, hut rather a “failure of a condition precedent to acceptance of the agreement.” Implicit in this language is a further ultimate conclusion that no enforceable agreement ever existed under the undisputed facts and that defendants never acted in bad faith.

II

The primary question, of course, is whether, with regard to the two causes of action pleaded, there is an absence of any material issue of fact requiring entrance of judgment for one or the other of the parties.

As we said, plaintiff has stated two causes of action and that, if its allegations are found to be true, it is entitled to recover for tort as well as contractual detriment. And a number of issues, we think, emerge from the pleadings relating to specific rights and obligations of the parties.

The undisputed fact is that on December 14, 1982, a valid construction contract between plaintiff and Quail Bluff was executed calling for the construction of a 360-unit apartment complex. Quail Bluff, through its general partner, swore in an interrogatory that it terminated the contract because the “project lender ... advised Defendant that K & E Construction was not acceptable as General Contractor for the project,” and that it did so under the provisions of paragraph 6 of the contract which makes the agreement “contingent upon the Owner obtaining a loan from the Lender in a sum of not less than ... $6,500,000.” And finally, in answers to interrogatories, Quail Bluff admitted an inability to recall advising plaintiff about the lender’s bond requirement or requesting it to obtain the required bond prior to the termination. Instead, it said, it asked a competing bidder, Western Construction Company, to submit a new bid which turned out to be about $113,000 less than plaintiffs.

It was on January 6 that three significant events took place.

First. David Ardire, assistant vice president of lender bank dictated a letter addressed to defendant Corvin, the general partner of Quail Bluff, advising that K & E was “not acceptable as general contractor for the Quail Bluff project without a $7,165,923.00 Payment and Performance Bond from a bonding company approved by RepublicBank Dallas.”

Second. A Quail Bluff official called EKE and represented that RepublicBank would not approve EKE under any circumstances and Quail Bluff was therefore terminating the contract.

Third. Quail Bluff entered into a general contract with Western.

If these facts are true, and they certainly appear to be, then the legal effect is that Quail Bluff not only breached the EKE agreement but committed the tort of deceit to accomplish it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

OAK TREE PARTNERS, LLC v. WILLIAMS
2020 OK CIV APP 5 (Court of Civil Appeals of Oklahoma, 2018)
Peters v. American Income Life Insurance Co.
2003 OK CIV APP 62 (Court of Civil Appeals of Oklahoma, 2002)
Lewis v. Aetna U.S. Healthcare, Inc.
78 F. Supp. 2d 1202 (N.D. Oklahoma, 1999)
Boyd v. K Mart Corporation
Tenth Circuit, 1997

Cite This Page — Counsel Stack

Bluebook (online)
1985 OK CIV APP 46, 714 P.2d 604, 1985 Okla. Civ. App. LEXIS 84, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eke-builders-inc-v-quail-bluff-associates-oklacivapp-1985.