Eiswirth v. Anthony L. Golemi, Contractor, Inc.

864 So. 2d 792, 3 La.App. 5 Cir. 1065, 2003 La. App. LEXIS 3657, 2003 WL 23025454
CourtLouisiana Court of Appeal
DecidedDecember 30, 2003
DocketNo. 03-CA-1065
StatusPublished
Cited by3 cases

This text of 864 So. 2d 792 (Eiswirth v. Anthony L. Golemi, Contractor, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eiswirth v. Anthony L. Golemi, Contractor, Inc., 864 So. 2d 792, 3 La.App. 5 Cir. 1065, 2003 La. App. LEXIS 3657, 2003 WL 23025454 (La. Ct. App. 2003).

Opinion

WALTER J. ROTHSCHILD, Judge.

Plaintiffs appeal from a judgment of the trial court granting defendant’s exception of prescription. For the reasons stated more fully herein, we reverse the trial court’s judgment and remand the case for further proceedings.

Facts and Procedural History

On December 28, 2000, Clement and Joan Eiswirth filed this petition for damages and breach of contract against Anthony L. Golemi Contractor, Inc. Plaintiffs alleged that they entered into a contract with Golemi for the construction of a residential building and that after moving into the home they noticed certain defects in the construction of the home that were brought to defendant’s attention. Plaintiffs allege that defendant failed to make the necessary repairs and replacements, and that defendant is therefore in violation of the contractual provision requiring the contractor to timely provide a completed product. Plaintiffs further allege that the defects in the home caused by defendant’s negligence constitute a breach of the warranty of good workmanship.

|3In response to this petition, Golemi filed exceptions of no cause and/or right of action, and an exception of prescription. Golemi also filed a reconventional demand against the Eiswirths for sums he alleged was owed under the contract and an answer and third party demand against various subcontractors who worked on the project.

A hearing was held in the trial court on defendant’s exceptions on March 1, 2002. Following the hearing, the trial court took the matter under advisement. By judgment rendered June 5, 2002, the trial court denied defendant’s exceptions of no cause and no right of action. However, the court granted defendant’s exception of prescription. Plaintiffs subsequently filed a devol-utive appeal, and a panel of this court dismissed that appeal because the judgment had not been certified as a final judgment pursuant to La. C.C.P. art. 1915 B. Eiswirth v. Anthony L. Golemi Contractor, Inc., 02-1060 (La.App. 5 Cir. 1/28/03), 839 So.2d 346.

Plaintiffs subsequently filed a motion to certify the judgment as final in the trial court, and on May 30, 2003, the trial court designated the judgment as final pursuant to the provisions of La. C.C.P. art. 1915 B(l). Plaintiffs now appeal from the final judgment granting defendant’s exception of prescription.

Breach of Warranty

By their exception of prescription, defendant argues that plaintiffs’ claims under the New Home Warranty Act have prescribed pursuant to the provisions of [794]*794La. R.S. 9:3144 and 9:3146. Defendant did not contend in the trial court that plaintiffs breach of contract claims have prescribed nor was this issue addressed during the exception hearing, and thus the trial court’s judgment granting the exception of prescription only relates to plaintiffs’ claims for breach of warranty. Plaintiffs’ claims of breach of contract, as [4well as defendant’s reconventional demand and third party demand, are still pending before the trial court.

The New Home Warranty Act (“NHWA”) governs the exclusive remedies, warranties and prescriptive periods as between a builder and owner relative to home construction. La. R.S. 9:3150. La. R.S. 9:3144 provides in part 1

A. Subject to the exclusions provided in Subsection B of this Section, every builder warrants the following to the owner:
(1) One year following the warranty commencement date, the home will be free from any defect due to noncompliance with the building standards or due to other defects in materials or workmanship not regulated by building standards.
(2) Two years following the warranty commencement date, the plumbing electrical, heating, cooling, and ventilating systems exclusive of any appliance, fixture, and equipment will be free from major structural defects due to noncompliance with the building standards or due to other defects in material or workmanship not regulated by building standards.
(3)Ten years following the warranty commencement date, the home will be free from major structural defects due to noncompliance with the building standards or due to other defects in materials or workmanship not regulated by building standards.

Pursuant to La. R.S. 9:3145, this section also requires the owner to give the builder written notice, by registered or certified mail, of the existence of the defect, giving him an opportunity to comply with the terms of this section, within one year from the owner’s discovery of the defect.

At the time the Eiswirths’ petition was filed, the applicable prescriptive period for suits brought pursuant to this section was contained in La. R.S. 9:3146, which provided:2

Is Any action to enforce any warranty provided in this Chapter shall prescribe thirty days after the expiration of the appropriate time period provided in R.S. 9:3144.

As defined by La. R.S. 9:3143, the warranty commencement date is the date legal title to the home is conveyed or the date the home is first occupied, whichever comes first. According to plaintiffs’ petition, the parties executed a “Notice of Termination/Substantial Completion of Work” on March 18, 1999, and a final punch list of remaining problems was forwarded to Golemi at this time. Plaintiffs subsequently moved into the home, and on [795]*795April 22, 1999, the parties executed a cancellation of the recorded building contract. Defendant admits in brief that the warranty commencement date occurred in April of 1999.

The petition for damages in this case alleges that plaintiffs notified the builder of defects in the home by correspondence dated August 15, 1999, February 13, 2000 and May 16, 2000. Defendant failed to address or repair the defects as listed by plaintiffs, and on March 18, 2000, plaintiffs forwarded an additional punch list to Gole-mi in an attempt to amicably resolve the matter. This petition for damages and breach of contract was subsequently filed on December 23, 2000.

Prescription

In the exception of prescription, defendant contends that the claims for breach of warranty are governed by the one year prescriptive period contained in La. R.S. 9:3144 A(l), and that plaintiffs’ claims filed more than one year and thirty days after the warranty commencement date have prescribed. Plaintiffs respond that their petition alleges major structural defects which are governed by R.S. 9:3144(A)(3), which allows a ten year prescriptive period. Plaintiffs also contend that the one year prescriptive | ^period for their remaining allegations was interrupted by defendant’s own acts.

Generally, the party raising the exception of prescription bears the burden of proof, unless prescription is evident from the face of the pleadings, in which case the plaintiff bears the burden of showing that the action has not prescribed. Spott v. Otis Elevator Co., 601 So.2d 1355 (La.1992). Prescriptive statutes are strictly construed against prescription and in favor of the obligation sought to be extinguished; thus, of two possible constructions, that which favors maintaining, as opposed to barring, an action should be adopted. Lima v. Schmidt, 595 So.2d 624, 629 (La.1992).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Joseph v. Kent
89 So. 3d 447 (Louisiana Court of Appeal, 2012)
Paragon Lofts Condominium Owners Ass'n v. Paragon Lofts, L.L.C.
55 So. 3d 970 (Louisiana Court of Appeal, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
864 So. 2d 792, 3 La.App. 5 Cir. 1065, 2003 La. App. LEXIS 3657, 2003 WL 23025454, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eiswirth-v-anthony-l-golemi-contractor-inc-lactapp-2003.