Eihausen v. Consumers, Inc.

209 N.W.2d 59, 1973 Iowa Sup. LEXIS 1072
CourtSupreme Court of Iowa
DecidedJuly 3, 1973
Docket55495
StatusPublished

This text of 209 N.W.2d 59 (Eihausen v. Consumers, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eihausen v. Consumers, Inc., 209 N.W.2d 59, 1973 Iowa Sup. LEXIS 1072 (iowa 1973).

Opinion

MASON, Justice.

Plaintiffs, Albert Eihausen and his wife Ethel, instituted a law action for damages from defendant, Consumers, Inc., for an alleged breach of contract growing out of the construction of plaintiffs’ house by defendant. They appeal from the trial court’s judgment determining the damages to be awarded them.

October 9, 1967, the Eihausens and Dewey Olson, defendant’s authorized representative and agent, executed a written contract for the construction of a house on plaintiffs’ farm by defendant for a total cost of $26,151.97. Although no plans were attached to the contract, it was agreed defendant would construct a home for plaintiffs copying the plan of a “Dingle home” with certain modifications involving a fall-out 'bomb shelter and breezeway, brick veneer walls, double-hung windows, hip roof style and rearranging of closets and baths. However, neither party strictly adhered to the agreement and several oral alterations and additions were requested by plaintiffs during the course of the building. Some of the changes made on the job were on direct orders from plaintiffs without clearing with Olson.

In its judgment the trial court noted, and there is substantial support for the view, that “little, if any, attention was given to the written agreement by either party after it was signed. Other than building the house on the right farm, there is little similarity between the terms of the ‘contract’ and what the parties did,”

Construction of the home commenced October 19. It was mutually agreed plaintiffs would perform certain portions of the inside work, including painting, plastering, electrical work and insulation. They were to be allowed a credit on the total contract price for these items of $3759.57.

November 15, as work proceeded on construction of the new home, plaintiffs paid defendant $10,000 at Olson’s request. At this time the basement was walled-up but the roof was not installed and there was snow on the sub-floor of the house.

January 3, 1968, Olson came to the Ei-hausen home requesting further payment on the contract. He had computed the costs of changes and extras and had prepared an itemized statement or recap of figures, identified as exhibit “M,” to advise plaintiffs of the total unpaid balance it would require to finish the house. Following an explanation and examination of exhibit “M,” plaintiffs paid the second $10,000. This left a balance of $4955.59 which represented a total increase of $2563.19 above the original total cost figure of $26,151.97.

Mr. Eihausen testified: “We agreed to pay Consumers $4955.59 in addition’to the $20,000 we had already paid them if Consumers finished the contract, paid off the sub-contractors, and finished the house.”

And Mrs. Eihausen stated: “I think my husband and Dewey [Olson] sat down, and after the payment of the $20,000, and agreed that the cost of finishing the house would be $4955.59.”

After Olson left Eihausen’s farm with the second $10,000 check, plaintiffs stopped payment on the check the following day, believing they had paid too much in view of the progress of the work. However, plaintiffs paid defendant $8000 on the contract January 16 and another $2000 on February 1, leaving the balance previously stated. For reasons not material to this appeal, defendant did not complete the construction of the home.

After the home was completed by third parties at an additional cost of $11,581.55, plaintiffs initiated this law action to recover their damages.

The court found plaintiffs were required to expend $11,581.55 to complete the house. Included in this amount was a $4450 claim *61 of Burdette Hansen, a bricklayer who had filed a mechanic’s lien against plaintiffs’ property.

The court also found that, “Olson had computed the cost of changes and extras and had prepared Exhibit ‘M’ to advise plaintiffs of the total unpaid balance it would require to finish the house. Following this explanation and examination of Exhibit ‘M’ plaintiffs, paid the second $10,000.00 and agreed that the balance due was $4,955.59.

» ⅜ ⅜ ⅜

“Defendant is entitled to off-set the account stated of $4955.59 but is liable for interest of the remaining damages.”

The court then set forth a recapitulation in the following manner showing how it arrived at the amount of the judgment awarded plaintiffs:

Total amount necessary to complete house $11,581.55
Less account stated -4,955.59
Damages $ 6,625.96
Interest for three years at 5 percent 993.90
Total including Interest $ 7,619.86

Defendant moved to reduce the judgment by the amount representing Hansen’s mechanic’s lien and interest. Following a hearing the court sustained the motion upon condition defendant comply with the provisions of section 572.15, The Code, 1971, by filing a bond as provided in this section to discharge the mechanic’s lien.

The judgment was thus reduced by $4450 plus interest for three years at five percent or $667.50 for a total of $5117.50.

I. Plaintiffs rely on only one assignment of error for reversal, asserting the court erred in its conclusion the balance due on the contract modified by oral agreement was an “account stated.” Plaintiffs, in effect, contend the judgment awarded them should be increased by the amount of the account stated, $4955.59 plus interest.

In a law action tried to the court as here, our review is not de novo but only on errors assigned. Under this limited extent of review the findings of fact by the trial court have the effect of a special verdict and are equivalent to a jury verdict. If supported by substantial evidence and justified as a matter of law, the judgment will not be disturbed on appeal. Rule 344(f)(1), Rules of Civil Procedure. Stated in other words, in a law action tried to the court its findings of fact having adequate evidentiary support shall not be set aside unless induced by an erroneous view of law. It follows, the rule does not preclude inquiry into the question whether, conceding the truth of a finding of fact, the trial court applied erroneous rules of law which materially affect the decision. We may also interfere when such findings are undisputed or no conflicting inferences may be drawn from them. Beneficial Finance Company of Waterloo v. Lamos, 179 N.W.2d 573, 578 (Iowa 1970).

In Conrad v. Dorweiler, 189 N.W.2d 537, 540-541 (Iowa 1971), this court had the occasion to discuss the measures of damage for breach of a construction contract. We quote from that opinion:

“ * * * The material portion of * * * [the] rule [set out in Restatement, Contracts, section 346(1), page 572] is as follows:
“ ‘(1) For a breach by one who has contracted to construct a specified product, the other party can get judgment for compensatory damages for all unavoidable harm that the builder had reason to foresee when the contract was made, less such part of the contract price as has not been paid and is not still payable, determined as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Conrad v. Dorweiler
189 N.W.2d 537 (Supreme Court of Iowa, 1971)
Beneficial Finance Company of Waterloo v. Lamos
179 N.W.2d 573 (Supreme Court of Iowa, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
209 N.W.2d 59, 1973 Iowa Sup. LEXIS 1072, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eihausen-v-consumers-inc-iowa-1973.