E&I Global Energy Services, Inc. v. Liberty Mutual Surety Co.

District Court, D. South Dakota·Decided June 13, 2023·No. 4:20-cv-04033·Unknown

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF SOUTH DAKOTA SOUTHERN DIVISION

E&I GLOBAL ENERGY SERVICES, INC. 4:20-CV-04033-KES and E&C GLOBAL, LLC,

Plaintiffs, FACTUAL FINDINGS AND ORDER vs. FINDING DEFENDANT NOT LIABLE ON ALL COUNTS LIBERTY MUTUAL INSURANCE CO., Defendant.

I. Procedural Background and Factual Findings Beginning on February 14, 2023, the court held a four-day bench trial. Before the court were E&I Global Energy Services, Inc.’s and E&C Global, LLC’s (collectively “Plaintiffs”) claims against Liberty Mutual Insurance Co. for 1) Breach of Contract; 2) Contractual Breach of the Implied Covenant of Good Faith and Fair Dealing; 3) Fraud and Deceit; and 4) Negligent Misrepresentation. See Docket 43 (amended complaint listing such claims plus an unjust enrichment claim); Docket 60 at 31-34 (granting summary judgment on plaintiffs’ unjust enrichment claim). After hearing all the testimony and reviewing all the exhibits, the court finds the following facts were proven by the greater weight of the evidence: This case revolves around the VT Hanlon Project (Project) that the Western Area Power Administration (WAPA) sought to complete. See generally Docket 108 at 134-152. Jeffrey Bruce formed E&I and E&C. See Docket 111 at 131-32. Although Bruce did not explicitly testify that he owned E&C, the court credits his testimony that he and another one of his employees had “partnered up and built” E&C. See id. at 132. Similarly, Bruce repeatedly referred to his and his partner’s actions with respect to E&C as “we,” further indicating that

Bruce was one of the owners of E&C. See id. at 131-32. Thus, the court finds that Bruce was an owner of E&C. Although E&I and E&C are similarly named and did similar work, Bruce testified that the two entities “didn’t gel well together” due to having “different philosophies.” See id. at 132. Bruce also repeatedly distinguished the two entities throughout his testimony. See, e.g., id. at 131-33; Docket 112 at 82-83. Thus, the court finds that E&I and E&C are separate legal entities. E&I’s involvement on the project started as a subcontractor to Isolux, the

principal contractor with WAPA. See Docket 111 at 134, 137-38; Docket 110 at 12. Representatives of Isolux, Waylon Ferreira and Mike Tiffin, approached Bruce and told Bruce that Isolux needed help. See Docket 111 at 137-39; see also Docket 108 at 118 (showing Waylon Fereira was a construction manager with Isolux). Bruce went down to the VT Hanlon construction site “right away” with “trucks, tools, and manpower” to “help [] get Isolux out of the ditch.” See Docket 111 at 138-39; Docket 112 at 33. Bruce arrived on site sometime in the summer of 2016 without having signed a subcontract with Isolux. See Docket

111 at 138-39, 142, 150. Despite not signing a contract, Bruce supplied a trailer with tools and rental equipment such as forklift machines and manlifts. See id. at 145-48. Bruce testified that when he arrived on site, the project was “in tough shape” and “a total mess,” observing “right off the bat” problems with grading, no fence around the project, and incomplete buildings. See id. at 150-52, 155.

Based on this testimony, the court finds Bruce knew that the project was risky from the beginning. Bruce arrived on site without any plans, disks, drawings, or specifications. See id. at 140-41. Bruce also testified that he did not have access to all of the project drawings for the site, and instead only received the relevant drawings that pertained to specific tasks E&I performed. See id. at 141. Bruce asked Isolux for all of the drawings, but Isolux indicated it could not print all of them. Id. at 141-42. Eventually, after WAPA inquired about E&I’s identity given that E&I was

not an official subcontractor for Isolux, E&I signed two subcontracts with Isolux. See id. at 142, 144-45; see Docket 108 at 17-63; 68-114. One subcontract required E&I to complete various steel and aluminum work, electrical installation, and other related items. See Docket 108 at 20. This subcontract gave E&I access to a Dropbox link that contained “VT Hanlon Drawings and Specifications[.]” Id. at 55. The second subcontract required E&I to construct a service building for the substation. See id. at 71. Liberty and The Insurance Company of the State of Pennsylvania

(collectively the “sureties”) issued a payment bond and performance bond on behalf of Isolux and in favor of WAPA for the prime contract between Isolux and WAPA. See id. at 1-4. Liberty served as the lead surety. See Docket 110 at 152. The performance bond guaranteed to the federal government that Isolux would complete the contract according to its terms, and if Isolux failed to perform, the sureties would step in and perform according to the terms of the bond. See id. at 153. The payment bond protected the subcontractors and suppliers who

provided work for Isolux and for whom Isolux failed to pay. See id. at 153-54. Carolyn Banks served as Liberty’s claim specialist and handled the claims related to the project. See id. at 12. On November 17, 2016, Jonathan Dittmer, a WAPA representative, issued a Stop Work Order to Isolux, effective November 18, 2016. See Docket 108 at 5. On December 2, 2016, Dittmer notified Liberty that WAPA had terminated the main contract between itself and Isolux, and requested Liberty to submit a proposal detailing how Liberty intended to complete the project.

See id. at 6. Liberty responded on December 7, 2016, requesting additional time for its consulting team to visit the site and obtain documentation surrounding the project. See id. at 11-12. At the time WAPA terminated Isolux, Liberty had little information about the project. See Docket 110 at 156-57; 163 (Banks stated that prior to sending out requests for documents to WAPA and Isolux that Liberty did not have any of the requested documentation); 164 (Banks testified that at the time, she “did not even know that E&I was a subcontractor on [the] job[.]”). David Mattingly,

vice president of Professional Construction Consulting (PC2), testified that Liberty hired PC2 to support Liberty in its investigation. See Docket 111 at 28. Mattingly testified he was “heavily involved early on in PC2’s involvement” with the VT Hanlon project. See id. at 29. Marvin House, PC2’s owner, also testified that Liberty was one of PC2’s clients. See Docket 112 at 151. As part of the investigation, Mattingly visited the site in December 2016.

See Docket 111 at 35. Bruce gave Mattingly a couple-hour tour of the site, where Bruce “point[ed] out some of the issues that he was running into during the construction.” Id. at 69. Mattingly also took pictures of the site. See id. at 35-36. Mattingly testified that prior to the tour, he “didn’t know anything about the job.” Id. at 69. During this December 2016 visit, Mattingly also spoke with WAPA representatives, including Dittmer, in the WAPA office. See id. at 36. Dittmer gave Mattingly four CDs, which Mattingly never gave to Bruce. Id. at 36, 45-46. Mattingly also summarized his trip in Exhibit 518. See Docket 108

at 119. There is no evidence in the record suggesting Mattingly gave Bruce this summary. After this December 2016 visit, Mattingly and House (both with PC2 and on behalf of Liberty), and Bruce negotiated a Completion Agreement. See id. at 121-22; Docket 111 at 29. E&C—rather than E&I—submitted its first written bid to be the completion contractor of the Project on January 6, 2017. See Docket 108 at 121-22. The purpose of a Completion Agreement was for the sureties to negotiate a contract with a completion contractor and then “turn

[the completion contractor] over to the government and allow [the completion contractor and government] to work together directly without the involvement of the sureties.” See Docket 110 at 158. E&C submitted other proposals in the next month and a half.

Free access — add to your briefcase to read the full text and ask questions with AI

E&I Global Energy Services, Inc. v. Liberty Mutual Surety Co., (D.S.D. 2023).

E&I Global Energy Services, Inc. v. Liberty Mutual Surety Co. (E&I Global Energy Services, Inc. v. Liberty Mutual Surety Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

McKie v. Huntley
2000 SD 160 (South Dakota Supreme Court, 2000)
Action Mechanical, Inc. v. Deadwood Historic Preservation Commission
2002 SD 121 (South Dakota Supreme Court, 2002)
Fisher v. Kahler
2002 SD 30 (South Dakota Supreme Court, 2002)
A.P. & Sons Construction v. Johnson
2003 SD 13 (South Dakota Supreme Court, 2003)
Farm Credit Services of America v. Dougan
2005 SD 94 (South Dakota Supreme Court, 2005)
Ehresmann v. Muth
2008 SD 103 (South Dakota Supreme Court, 2008)
Schwartz v. Morgan
2009 SD 110 (South Dakota Supreme Court, 2009)
Bowes Construction, Inc. v. South Dakota Department of Transportation
2010 S.D. 99 (South Dakota Supreme Court, 2010)
American Family Insurance Group v. Robnik
2010 SD 69 (South Dakota Supreme Court, 2010)
Regan v. Moyle Petroleum Co.
344 N.W.2d 695 (South Dakota Supreme Court, 1984)
Mahan v. Avera St. Luke's
2001 SD 9 (South Dakota Supreme Court, 2001)
Garrett v. BankWest, Inc.
459 N.W.2d 833 (South Dakota Supreme Court, 1990)
Mash v. Cutler
488 N.W.2d 642 (South Dakota Supreme Court, 1992)
Ducheneaux v. Miller
488 N.W.2d 902 (South Dakota Supreme Court, 1992)
Kasselder v. Kapperman
316 N.W.2d 628 (South Dakota Supreme Court, 1982)
Pieper v. Pieper
2013 SD 98 (South Dakota Supreme Court, 2013)
Stabler v. First State Bank of Roscoe
2015 SD 44 (South Dakota Supreme Court, 2015)
Stern Oil Co. v. Brown
2018 SD 15 (South Dakota Supreme Court, 2018)
L.S. v. C.T.
2009 SD 2 (South Dakota Supreme Court, 2009)