Effort Alexander v. Charlys Espinoza

Court of Appeals of Mississippi·Decided August 13, 2024·No. 2023-CP-01139-COA·Published

Opinion

IN THE COURT OF APPEALS OF THE STATE OF MISSISSIPPI NO. 2023-CP-01139-COA

EFFORT ALEXANDER APPELLANT v. CHARLYS ESPINOZA APPELLEE

DATE OF JUDGMENT: 10/05/2023 TRIAL JUDGE: HON. VICKI B. DANIELS COURT FROM WHICH APPEALED: DESOTO COUNTY CHANCERY COURT ATTORNEY FOR APPELLANT: EFFORT ALEXANDER (PRO SE) ATTORNEY FOR APPELLEE: JOSEPH M. SPARKMAN JR. NATURE OF THE CASE: CIVIL - REAL PROPERTY DISPOSITION: APPEAL DISMISSED - 08/13/2024 MOTION FOR REHEARING FILED:

BEFORE CARLTON, P.J., McDONALD AND McCARTY, JJ.

McDONALD, J., FOR THE COURT:

¶1. Effort Alexander contracted with Charlys Espinoza and his Tennessee company C&A Construction LLC (collectively, “Espinoza”) to frame a home Alexander was building in DeSoto County, Mississippi. When a dispute arose, Alexander terminated the contract, and Espinoza filed a mechanic’s lien on the property for $6,200, the amount he claimed Alexander owed him.

¶2. Alexander sued Espinoza in the DeSoto County Chancery Court, and Espinoza filed a counter-claim. In a second suit, Alexander filed a motion for declaratory judgment, claiming that Espinoza’s lien was invalid because Espinoza was not licensed in Mississippi. The chancery court ultimately denied the motion, assessed attorney’s fees against Alexander, and transferred the case to the chancellor handling Alexander’s first lawsuit. Alexander

appeals from the order denying declaratory relief. Having reviewed the record and considered the arguments of the parties, we find that the chancery court’s order was not a final judgment; therefore, we dismiss Alexander’s appeal for lack of jurisdiction.

Facts

¶3. Alexander, a resident of Memphis, Tennessee, decided to build a home on property he owned in Southaven, Mississippi. On November 12, 2021, he contracted with Espinoza, who owned C&A Construction LLC (a sole proprietorship located in Tennessee), to do the framing work.1 The parties agreed on a contract price of $37,120, which would be paid upon completion of the work.

¶4. On November 28, 2022, after allegedly paying Espinoza $33,020, Alexander terminated the contract. In a letter he sent to Espinoza that day, Alexander said that Espinoza had allowed or was responsible for the theft of building materials that had been delivered to the gated job site during working hours. Because of this alleged theft, Alexander said he had to replace the stolen material with lesser quality material.2

¶5. About a month later, on December 20, 2022, Espinoza filed a mechanic’s lien on the property, claiming Alexander owed him $6,200.

¶6. On December 29, 2022, Espinoza sent a copy of the mechanic’s lien to Alexander’s

1 This project included work on the lower level, main floor, carport, screened porch, rear balcony and deck, front porch, and an addition to the house.

2 As added grounds for the termination, Alexander said that there was so much unfinished framing work that the balance of the contract price was not sufficient to cover the cost of another company finishing the work. Alexander said he based his allegations on the advice of Matthew Thompson, a licensed construction contractor and architect.

bank in Southaven (Guaranty Bank). Espinoza told the bank that he had completed the framing of the home and that he had to file the lien on the property because Alexander refused to pay him according to their agreement.3

¶7. According to Alexander, Guaranty Bank cut off Alexander’s funding for the project when the bank received Espinoza’s letter and the mechanic’s lien.

First Lawsuit

¶8. On January 27, 2023, Alexander sued Espinoza in the DeSoto County Chancery Court. The pro se complaint, entitled “Complaint to Remove Lien and Award Damages Penalty,” was assigned cause number 23-cv-167. The docket for that cause number is not included in our record; however, several of the pleadings are in the record.4 In the complaint, Alexander alleged that he had terminated his contract with Espinoza and that he had paid Espinoza in full. Alexander further alleged that Espinoza had filed a mechanic’s lien, which Alexander characterized as “fraudulent” because he did not owe Espinoza anything. Alexander further alleged that Espinoza sent a copy of the mechanic’s lien to Guaranty Bank along with other alleged “misinformation.” Alexander claimed that he was entitled to damages because the bank cut off his funding due to Espinoza’s letter and lien.

¶9. Espinoza filed a motion for a more definite statement and then filed a “Counter-

3 Espinoza told the bank that the framing of the structure was complete and ready for code inspection, and all that remained to be done was to install three windows. The window installation was not completed, Espinoza said, because Alexander had ordered the wrong size windows and had added an additional room beyond the contract’s terms.

4 When Alexander designated the record for appeal purposes, he included selected pleadings from the first and the second cases he filed.

Complaint” on April 18, 2023. In it, Espinoza alleged that during the construction process, Espinoza purchased materials and performed additional work on changes/additions to the contract that Alexander requested. When Alexander terminated the contract and refused to pay for these materials, Espinoza filed a mechanic’s lien. Because of Alexander’s alleged breach of the agreement, Espinoza sought a judgment of $6,200, judicial foreclosure to satisfy the lien, and attorney’s fees. On May 5, 2023, Alexander denied Espinoza’s allegations in response to the counter-complaint.

¶10. On May 31, 2023, Espinoza filed a motion to dismiss Alexander’s complaint, alleging insufficient service of process. On June 16, 2023, the chancery court held a hearing on the motion and dismissed Alexander’s claim without prejudice. The court made no ruling on Espinoza’s counter-claim, and on July 12, 2023, Espinoza moved to schedule a trial on that claim.

Second Lawsuit

¶11. On June 27, 2023, Alexander filed a second complaint against Espinoza in the DeSoto County Chancery Court, entitled “Complaint to Remove Lien and Award Damages Penalty,” which was docketed as cause number 23-cv-1120. In the pro se complaint, Alexander claimed Espinoza failed to complete the framing work,5 and Alexander alleged Espinoza had filed an “illegal, invalid, fraudulent and grievously false lien” on Alexander’s property.

5 Alexander stated that the soffits and facia were not completed, nor was the home’s interior stairway finished. He alleged that all the windows were not installed, nor was the “Hardie Panel” siding on the home completed. Alexander pleaded that a June 26, 2023 inspection by the “City of Southhaven Building Department” had determined the work was incomplete and inadequate.

Alexander claimed that Mississippi allows only licensed residential contractors to file mechanic’s liens, and Espinoza was not licensed.6 Alexander also alleged that Espinoza had mailed his invalid lien to Alexander’s bank in an attempt to extort $6,200 from Alexander. In his request for relief, Alexander contended that Espinoza’s filing an invalid mechanic’s lien was a felonious act, that Espinoza illegally interrupted Alexander’s possession and peaceful use of his property by filing the lien, and that Espinoza “denied Plaintiff his right to an unclouded property title.” Alexander asked that the court strike Espinoza’s invalid lien and award Alexander $18,600, the statutory penalty for filing a false lien authorized under Mississippi Code Annotated section 85-7-429 (Rev. 2021),7 and damages for his loss of peaceful use and the cloud on his title.

¶12. According to the docket for cause 23-cv-1120, which is included in our record, Espinoza filed an answer to this complaint on August 1, 2023. However, a copy of the pleading was not included in the record.

¶13. On August 11, 2023, Alexander filed a “Motion to Pass Declaratory Judgement” pursuant to Rule 57(b)(1) of the Mississippi Code of Civil Procedure, asking the court to “conclude that Defendant’s lien is invalid under the law of the State of Mississippi.”

Free access — add to your briefcase to read the full text and ask questions with AI

Effort Alexander v. Charlys Espinoza, (Mich. Ct. App. 2024).

Effort Alexander v. Charlys Espinoza (Effort Alexander v. Charlys Espinoza) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Miller v. RB Wall Oil Co., Inc.
850 So. 2d 101 (Court of Appeals of Mississippi, 2002)
Meekins v. Kennon
141 So. 3d 51 (Court of Appeals of Mississippi, 2014)
LaFontaine v. Holliday
110 So. 3d 785 (Mississippi Supreme Court, 2013)
M.W.F. v. D.D.F.
926 So. 2d 897 (Mississippi Supreme Court, 2006)