E.F. Coe T/a Cabana Motel v. Thermasol, Ltd.

785 F.2d 511, 1986 U.S. App. LEXIS 22775
CourtCourt of Appeals for the Fourth Circuit
DecidedMarch 6, 1986
Docket85-1916
StatusPublished
Cited by7 cases

This text of 785 F.2d 511 (E.F. Coe T/a Cabana Motel v. Thermasol, Ltd.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
E.F. Coe T/a Cabana Motel v. Thermasol, Ltd., 785 F.2d 511, 1986 U.S. App. LEXIS 22775 (4th Cir. 1986).

Opinion

MURNAGHAN, Circuit Judge:

I

The appeal involves a contract dispute between E.F. Coe (“Coe”), who owns a motel in Boone, North Carolina, and Thermasol, Ltd. (“Thermasol”), a manufacturer of steam bath units installed in motels. Coe brought suit against Thermasol in the Superior Court of Watauga County, North Carolina and Thermasol, on diversity grounds, removed to the United States District Court for the Western District of North Carolina.

Pursuant to an agreement entered into by Coe and Thermasol in 1978, Thermasol agreed to install forty-two steam bath units in Coe’s motel. A disagreement soon arose between the parties because Coe expected that the steam units Thermasol was installing in his motel would include special liners which would cover the previously existing walls of the bath and shower units in Coe’s motel. Coe had first seen the Thermasol units in a trade publication and they were depicted therein with the wall liners in place. When the units were installed without such liners in his motel, Coe complained to the Thermasol representatives in New Jersey.

*513 However, under the terms of Coe’s 1978 lease agreement, which he signed with Thermasol, no such liners were included as part of the items to be installed. Coe elected to pay according to the Daily Rental plan which established a rate based on the occupancy of those suites in his motel which had Thermasol units installed. 1

The 1978 lease agreement contained a choice of law clause stating that the lease was to be interpreted in accordance with New Jersey law. It also contained a liquidated damages clause, setting forth numerous events of default 2 and specifying that on occurrence of any of those events

then Lessee, in addition to paying any arrears in rent and additional rent, late payment charges, the expenses of retaking possession and removal of the System, reasonable attorney’s fees of 207< of the amount of any claim, court costs and expenses of disposing of the System, will pay Lessor the unpaid rent that would become due during the balance of the Lease term had Lessee elected the Daily Rental Plan, as set forth in paragraph 4A, after giving effect to rent rate changes as a consequence of the operation of paragraph 10, less all amounts realized by Lessor, if any, in Lessor’s disposition of the System, after first deducting all expenses of such disposition. Lessor may, after Lessee’s default, and prior to Lessee’s payment of all sums payable under this paragraph, enter Lessee’s premises and render the System, or parts thereof, unusable, or may remove the System in whole or in part, the Lessor shall not be liable for any damage or injury caused or resulting therefrom, including without limitation, the rendering of the premises or rooms therein as uninhabitable or unrentable. Lessor may, if in Lessor’s opinion the cost of removal and disposition would exceed the proceeds of disposition, elect not to remove and dispose of the System, and such election by Lessor shall not be a failure to mitigate damages, nor in any way entitle Lessee to a reduction in the amount due.

Coe admitted he did not, prior to signing, thoroughly read the contract. Coe, nevertheless, persisted in his complaints to Thermasol, which responded by promising action. An executive vice-president of the company stated that “if Wall Liners are needed, we will take care of this.” Despite representations to that effect, problems persisted. Coe refused at one point to pay for the units and the company again promised action on the wall liners and made other promises to Coe.

Eventually, in late 1981, a representative of Thermasol came to Boone to arrange *514 installation of the liners. In order to get the liners installed, Coe agreed, in a separate lease agreement, to pay an additional $0.35 for each occupied suite for 102 months inclusive. 3 Subsequently, wall liners were installed in some, but not all, of Coe’s Thermasol units.

In February or March 1982, Coe refused to pay Thermasol anything on either agreement and he defaulted on both leases. Coe instituted suit against Thermasol on May 28, 1982. Thermasol removed to federal court on June 22, 1982 and on June 29, 1982 counterclaimed against Coe for what was due it under the liquidated damages clause of its 1978 lease and what was due under the separate 1981 agreement for installing the wall liners. Thermasol also set forth various defenses, including the applicable statutes of limitations.

On February 14, 1983, Thermasol moved (1) to strike Coe’s request for jury trial 4 (2) to strike Coe’s prayer for damages; (3) for partial summary judgment on its counterclaim for damages against Coe; and (4) for summary judgment against Coe on his breach of contract claim.

On June 20, 1983, Thermasol moved to dismiss Coe’s complaint on the grounds that Coe’s breach of contract claim was barred by the applicable statute of limitations. The court ruled that under N.C.Gen. Stat. § 1-52(1), which specifies a three year limitations period for a cause of action based on a contract 5 or under N.C.Gen. Stat. § 25-2-725, which specifies a four year period for actions brought under the Uniform Commercial Code, Coe’s breach of contract action was time-barred. The court ruled that the applicable periods began to run when Coe accepted the equipment from Thermasol on April 22, 1978. The court did not grant Thermasol’s motion for summary judgment on its counterclaim because Coe had raised a question of whether there was fraud in the execution of his two leases with Thermasol.

Coe amended his complaint to allege fraud and execution of the contract under material mistake of fact and the case proceeded to trial. By stipulation, the parties dismissed Thermasol’s second counterclaim based on the 1981 lease agreement. A bench trial occurred on June 10, 1985. On August 1, 1985, the court issued its findings of fact and conclusions of law, ruling in favor of Thermasol and awarding it $242,009.60 damages, $48,401.92 in attorney fees 6 and court costs, 615 F.Supp. 316.

II

On appeal Coe argues a) that the liquidated damages clause in his 1978 lease agreement with Thermasol is an unenforceable penalty under New Jersey law and b) that, because of its actions, Thermasol was equitably estopped from asserting the statute of limitations against Coe’s breach of contract claim.

A. Liquidated Damages

Under New Jersey law, in order for a liquidated damages clause to be a penalty, the covenants in an agreement which trigger application of the liquidated damages provision must be both of varying degrees of importance and disconnected. Borden Co. v. Manley, 127 N.J.L. 461, 23 A.2d 281, 283 (1942), citing Summit v. Morris County Traction Co., 85 N.J.L. 193, 88 A. 1048, 1049 (1913). In Suburban Gas Co. v. Mollica, 21 N.J.Misc.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
785 F.2d 511, 1986 U.S. App. LEXIS 22775, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ef-coe-ta-cabana-motel-v-thermasol-ltd-ca4-1986.