Edwards & Daniels Architects, Inc. v. Farmers' Properties, Inc.

865 P.2d 1382, 228 Utah Adv. Rep. 14, 1993 Utah App. LEXIS 206, 1993 WL 532422
CourtCourt of Appeals of Utah
DecidedDecember 17, 1993
DocketNo. 920723-CA
StatusPublished
Cited by3 cases

This text of 865 P.2d 1382 (Edwards & Daniels Architects, Inc. v. Farmers' Properties, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Edwards & Daniels Architects, Inc. v. Farmers' Properties, Inc., 865 P.2d 1382, 228 Utah Adv. Rep. 14, 1993 Utah App. LEXIS 206, 1993 WL 532422 (Utah Ct. App. 1993).

Opinion

OPINION

BENCH, Judge:

Edwards & Daniels Architects, Inc. (Edwards) appeals the trial court’s dismissal of its action against Farmers’ Properties, Inc. (Farmers), Herbert Bosch, Fran Archuleta, Veri Sortor, and Ron Jenkins.1 We affirm.

FACTS

In 1984, Farmers and Soter/Knudsen Construction Company, Inc. (Contractor) agreed to become jointly involved in the construction of a hotel and casino in Winnemueca, Nevada. Farmers did not have sufficient funds to build a casino and informed Contractor that if Contractor could finance and build a casino, Farmers would lease the casino from Contractor. Contractor and Farmers agreed to retain Edwards to prepare the designs and plans to be used in the construction of the project. On two occasions in the summer of 1984, Farmers met with Contractor and Edwards to discuss the project. On the second occasion, Farmers viewed preliminary drawings that Edwards had prepared and again approved the hiring of Edwards to prepare the architectural designs and plans. Contractor and Farmers also discussed Edwards’s fees and agreed it would be 4.5 percent of the cost of construction, which was estimated to be between $2.6 to $2.9 million.

Farmers sought to discover whether Contractor had the ability to obtain financing to build the casino. Accordingly, they had several discussions with Contractor concerning Contractor’s financial worth and its ability to obtain construction financing. Contractor told Fran Archuleta, one of Farmers’s principals, that Contractor had a net worth of eight million dollars.

As part of the negotiations, Contractor proposed that Farmers deposit $50,000 in an account, which would be used for preliminary expenses. After Farmers informed Contractor that Farmers would have difficulty raising more than $50,000, Contractor assured Farmers that Contractor would be able to obtain construction financing because of its net worth of eight million dollars. Some of the principals of Farmers had to borrow their share of the $50,000 deposit. Accordingly, Farmers insisted on a $50,000 limit, which was integrated into a lease agreement in September 1984 between Contractor as [1384]*1384lessor, and Farmers as lessee.2 The principals of Farmers guaranteed its performance under the lease agreement.

In December 1984, Contractor contacted Farmers and requested that Farmers pay $20,000 to Edwards. Farmers paid the $20,-000 by á check drawn on the account that initially contained the $50,000 deposit. Veri Sortor, a principal of Farmers, told Contractor that this payment completely depleted the $50,000 deposit. Accordingly, Contractor told Sortor not to worry about any further architectural fees because those fees would be paid out of the construction loan and they would not be the responsibility of Farmers. Contractor also told Sortor “not to have any contact with the architects whatsoever” because Contractor would take care of any changes or negotiations with Edwards. Contractor informed Edwards that the majority of Edwards’s fees would not be paid until construction actually commenced.

Eventually, Contractor failed to obtain construction financing and gave written notice to Farmers that it had not been able to obtain the financing. In December 1985, Contractor demanded that Farmers pay all preliminary expenses, including architectural fees. Farmers did not pay the remaining preliminary expenses.

Thereafter, Edwards brought an action against Contractor for its unpaid architectural fees and also against Farmers based upon a third-party beneficiary claim. Farmers cross-claimed against Contractor for deliberate misrepresentations concerning Contractor’s financial worth and the availability of construction financing.

Edwards obtained a judgment against Contractor.3 However, the trial court dismissed Edwards’s third-party claim against Farmers based on the lease agreement between Contractor and Farmers. The court determined that section 8 of the lease was a “condition precedent to further liability of [Farmers] and its personal guarantors beyond the initial deposit, and as such it requires that [Contractor] engage in ‘advance, meaningful consultations’ with [Farmers], before incurring preliminary expenses beyond the initial deposit of $50,000.” The trial court also determined that the condition precedent of “advance, meaningful consultations” was not satisfied, thereby breaching the lease agreement. Thus, the trial court determined that the principals of Farmers were not liable for payment of preliminary expenses beyond the initial $50,000 deposit. Further, the trial court rejected claims that the meetings between Edwards, Contractor, [1385]*1385and Farmers in the summer of 1984 satisfied the consultation requirement in section 8 of the September 1984 lease. Finally, the trial court rejected the cross-claim of Farmers against Contractor on the basis of insufficient evidence.

ISSUES

Edwards raises two issues on appeal related to the lease agreement: (1) whether the trial court erred in finding that Contractor failed to provide advance, meaningful consultations with Farmers regarding architectural fees as required by section 8; and (2) whether the trial court erred in determining that the consultation requirement in section 8 was a condition precedent to Farmers’s liability beyond $50,000.

STANDARD OF REVIEW

Edwards challenges the trial court’s factual findings. To successfully challenge a factual finding, Edwards must (1) marshal all of the evidence that supports the finding, and (2)demonstrate that, despite the evidence, the finding is so lacking in support as to be “against the clear weight of evidence” and thus, clearly erroneous. Doelle v. Bradley, 784 P.2d 1176, 1178 (Utah 1989).

Edwards also challenges the trial court’s determination that the failure to satisfy the condition precedent of advance, meaningful consultations constituted a breach of the lease agreement. If a contract is unambiguous, interpretation of the contract is a question of law, which we review for correctness. Craig Food Indus., Inc. v. Weihing, 746 P.2d 279, 283 (Utah App.1987) (citing Kimball v. Campbell, 699 P.2d 714, 716 (Utah 1985)). If, however, a contract is ambiguous and the trial court bases its construction on extrinsic evidence of intent, we review the trial court’s construction as a question of fact, using a clearly erroneous standard. Id.

ANALYSIS

Meaningful Consultations

At the outset, we note that the lease agreement provides that Nevada law governs its enforcement, validity, and performance. However, we see no significant difference between the law of Nevada and our own in regard to interpreting the lease agreement. Under these circumstances, this court may “properly apply Utah law in the absence of an affirmative showing that the law of [Nevada] is different.” Morris v. Sykes, 624 P.2d 681, 684 (Utah 1981).

Edwards challenges the trial court’s findings that advance, meaningful consultations did not take place as contemplated by the lease agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Heartwood Home v. Huber
2020 UT App 13 (Court of Appeals of Utah, 2020)
Acosta v. Paragon Contractors Corp.
884 F.3d 1225 (Tenth Circuit, 2018)
In Re Llennoc Real Estate, LLC
460 B.R. 801 (D. Utah, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
865 P.2d 1382, 228 Utah Adv. Rep. 14, 1993 Utah App. LEXIS 206, 1993 WL 532422, Counsel Stack Legal Research, https://law.counselstack.com/opinion/edwards-daniels-architects-inc-v-farmers-properties-inc-utahctapp-1993.