Edward Peterson Co. v. O'Malley

113 F. Supp. 361, 44 A.F.T.R. (P-H) 200, 1953 U.S. Dist. LEXIS 2584
CourtDistrict Court, D. Nebraska
DecidedJuly 3, 1953
DocketCiv. No. 44-51
StatusPublished
Cited by1 cases

This text of 113 F. Supp. 361 (Edward Peterson Co. v. O'Malley) is published on Counsel Stack Legal Research, covering District Court, D. Nebraska primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Edward Peterson Co. v. O'Malley, 113 F. Supp. 361, 44 A.F.T.R. (P-H) 200, 1953 U.S. Dist. LEXIS 2584 (D. Neb. 1953).

Opinion

DONOHOE, 'Chief Judge.

The plaintiff, Edward Peterson Company, a Nebraska corporation, instituted this action to recover the sum of $62,702.27, with interest, the total amount of excess profits taxes which plaintiff asserts were wrongfully assessed and collected by the Director (formerly Collector) of Internal Revenue for the taxpayer’s fiscal year ending March 31, 1942. Jurisdiction of the action is vested in this court by virtue of Section 1340, Title 28 U.S.C.A. Venue is properly laid in the Omaha Division of the District of Nebraska, 28 U.S.C.A. § 1391 (b), and the conditions precedent to filing a suit for refund as specified in Section 3772 of Title 26 U.S.C.A. admittedly have been complied with. Since neither party made a demand for a jury trial, all issues were tried by the court, Rules 38(b, d), and 39(b), Federal Rules of Civil Procedure, 28 U.S.C.A.; and after careful considera[362]*362tion of the properly admissible evidence adduced during the proceedings the Court makes the following special Findings of Fact:

The Edward Peterson .Company, the taxpayer and plaintiff herein, was incorporated on April 20, 1931, in the state of Nebraska and maintains its principal place of business at Omaha, Nebraska. The taxpayer carries on the business of a general contractor, which includes the construction of highways, railroads, dams, levees, factory sites and the like. These construction projects are performed by the taxpayer pursuant to contracts entered into by the taxpayer as prime contractor, sometimes on its own account and sometimes in conjunction with other firms.

In April of 1937, plaintiff, A. Guthrie & Co., and John Marsch, Inc., executed a joint venture agreement providing that the joint venturers were to submit a bid to the Carnegie-Illinois Steel Corporation about April 23, 1937, for excavation and foundation work on the Irvin Mill Project in Camden, Pennsylvania. The agreement provided that if the joint venturers were successful in obtaining a contract for this work that a corporation, named GuthrieMarsch-Peterson 'Company, would be formed for the execution of the contract. The capital stock of the proposed corporation was to be $300,000, of which each of the joint venturers was to subscribe $100,-000, paying $50,000 cash, and the balance upon call of the corporate treasurer. The proposed corporation was to be managed, according to the joint venture agreement, by a board of directors under whose control there was to be a committee of three persons, one person representing each of the joint venturers. This committee of three was to be superior in authority to the general superintendent who in turn was to be in direct charge of operations. The joint venture agreement contains the following diagram of the proposed job organization under the committee:

The joint venture agreement provided that none of the officers, directors or members of the three-party committee of the proposed corporation were to receive salaries or expenses; however, the joint venturers were to receive payment for use of their grading equipment by the corporation. The joint venture agreement further provided that the funds of the proposed corporation were to be appropriated in the following order:

1. Payment of all costs of the work and claims against the corporation not including payments for use of the participants’ grading equipment.

2. Payment for use of participants’ grading equipment.

3. Return of capital investment.

4. Dividends.

Pursuant to the joint venture agreement just mentioned, plaintiff had Edward Peter[363]*363son, John Hershey and Robert Peterson go to the project location, gather information as to the labor and material costs of the required work and prepare individual estimates on the cost of the seventy or eighty items which the bid was to cover. Each of the other joint venturers made a similar determination of the costs of each bid item and representatives of the three joint venturers met in Pittsburgh, Pennsylvania, to discuss these individual estimates. Upon conclusion of their discussion they agreed upon the overall bid to be submitted to the Carnegie-Illinois Steel Corporation. The bid agreed upon was so submitted on April 26, 1937, in keeping with the original joint venture agreement.

The bid submitted was accepted by the Carnegie-Illinois Steel Corporation. Formal confirmation of the acceptance appears in a letter addressed to plaintiff, A. Guthrie & Co., and John Marsch, Inc., at .their respective business residences, dated May 15, 1937, and signed by Charles R. Miller, Jr., a purchasing agent of the Carnegie-Illinois Steel Corporation. This letter refers to certain essential specifications, advises the joint venturers that a contract would follow, and calls their attention to the fact that their bid included an offer to furnish a performance bond in the sum of $250,000, or in the alternative to deposit with the Carnegie-Illinois Steel Corporation certified checks amounting to $250,000, which the steel company would retain until satisfied that the work would be satisfactorily completed.

The same day that they were notified by the Carnegie-Illinois Steel Corporation that their bid had been accepted, the joint venturers, Taxpayer, A. Guthrie & Co., and John Marsch, Inc., executed two complementary agreements. The first, a joint venture agreement for the performance of the Irvin Mill project under the forthcoming Carnegie-Illinois Steel Corporation contract, was substantially a restatement, however with more formality and in greater detail, of the joint venture agreement entered into by the same parties the preceding April.

The Court feels constrained, even at the expense of being in some respects redundant, to call attention to the salient features of this second joint venture agreement. Paragraph 1 provides:

“It is the intention and purpose of the parties hereto that they shall act solely as joint adventurers and that there shall be no relation of, or liability among them as partners. No party hereto shall in any manner be liable or responsible for anything done or omitted by any other party hereto.”

Paragraph 2 provides that the joint venturers shall organize the Guthrie-MarschPeterson Corporation for execution of the Carnegie-Illinois Steel Corporation contract. This paragraph specifies the organization and capital structure of the proposed corporation; names Chicago, Illinois, as the location of the general office; sets out the six corporate directors: H. L. Mundy, R. M. Knox, John Marsch, Nicolas Marsch, Edward Peterson and John Hershey; and the members of the Executive Committee: Nicolas Marsch, Edward Peterson and R. M. Knox. In paragraph 3, the joint venturers each agree to subscribe for 1000 shares of stock in the corporation and pay therefor $100.00 a share. The next two paragraphs make the following provisions for the assignment by the joint venturers of the forthcoming Carnegie-Illinois Steel Corporation contract to the proposed corporation:

“4.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
113 F. Supp. 361, 44 A.F.T.R. (P-H) 200, 1953 U.S. Dist. LEXIS 2584, Counsel Stack Legal Research, https://law.counselstack.com/opinion/edward-peterson-co-v-omalley-ned-1953.