Edward H. Schwartz Construction, Inc. v. Driessen

2006 ND 15, 709 N.W.2d 733, 2006 N.D. LEXIS 15, 2006 WL 231633
CourtNorth Dakota Supreme Court
DecidedJanuary 31, 2006
Docket20050150
StatusPublished
Cited by25 cases

This text of 2006 ND 15 (Edward H. Schwartz Construction, Inc. v. Driessen) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Edward H. Schwartz Construction, Inc. v. Driessen, 2006 ND 15, 709 N.W.2d 733, 2006 N.D. LEXIS 15, 2006 WL 231633 (N.D. 2006).

Opinion

CROTHERS, Justice.

[¶ 1] Garry Driessen, doing business as A & G Construction Company, appeals from a judgment awarding Edward H. Schwartz Construction, Inc., $20,615, plus interest, for breach of an oral contract to provide aggregate at $2 per cubic yard for a road construction project. We conclude the district court did not clearly err in finding Driessen orally contracted with Schwartz Construction to provide aggregate for the project at $2 per cubic yard, and we affirm.

*735 I

[¶ 2] In May 2002, the North Dakota Department of Transportation solicited bids on County Federal Aid Project No. SC-1927(056) for grading and aggregate surfacing of a county road south of Carson. Bids for the project were due on May 17, 2002, and on the evening of May 16, 2002, Randall Schwartz, the president of Schwartz Construction, secured bids from prospective subcontractors for the different parts of the project, including aggregate. According to Schwartz, Driessen orally offered to provide aggregate at $2 per cubic yard for the project. According to Driessen, his quote for the aggregate was $2 per ton. Schwartz testified he informed Driessen that Driessen had the low bid for the aggregate and that Schwartz Construction’s bid for the'project was based on Driessen’s bid for the aggregate. Schwartz Construction was awarded the contract for the project, and Driessen acknowledged that he learned Schwartz Construction had been awarded the contract shortly after the bids were opened on May 17, 2002.

[¶ 3] The parties did not have any further contact until June 2002, when Schwartz and Driessen had a telephone conversation and Schwartz Construction faxed several documents to Driessen. According to Driessen, he received a call from Schwartz on June 23, 2002, while Driessen was traveling to Aberdeen, South Dakota. Driessen testified he had taken other work in Aberdeen, because he did not know he had the job with Schwartz Construction. Driessen testified that during the phone conversation, Schwartz said “[h]e wanted [Driessen] to do the job,” and Driessen replied that “maybe we could do it on the way back.” According to Schwartz, he asked Driessen “point-blank if he was still going to do [the job]. And [Driessen] said, yeah, he’d do it after South Dakota.” On June 26, 2002, Schwartz Construction faxed several documents to Driessen, including a cover letter, a request to sublet form, and a standard subcontract agreement form for the project. Those documents stated the price for the aggregate was $2 per cubic yard. In the cover letter, Schwartz Construction asked Driessen to “sign & mail subcontracts & request to sublet back to me,” but Driessen did not return those documents to Schwartz Construction.

[¶ 4] Driessen did not provide Schwartz Construction with the aggregate for the project, and Schwartz Construction subsequently subcontracted with another firm to provide aggregate for the project at the price of $2.96 per cubic yard. Schwartz Construction sued Driessen for the difference in prices. Schwartz Construction claimed Driessen had contracted to provide aggregate for the project at the price of $2 per cubic yard. Driessen claimed there was no contract because his quote was conditioned .upon Schwartz Construction providing a gravel pit to supply the aggregate, his quote was not accepted by Schwartz Construction in a timely manner, and his quote was to provide the aggregate at $2 per ton and not $2 per cubic yard. After a bench trial, the district court found Driessen contracted with Schwartz Construction to provide aggregate for the project at $2 per cubic yard. The court awarded Schwartz Construction damages of $20,615, plus interest.

II

[¶ 5] During oral argument to this Court, Driessen abandoned his claim that this Court’s review of the district court’s findings is not - governed by the clearly erroneous rule because the court’s findings rest primarily upon documentary evidence. Compare Dolajak v. State Auto. & Cas. Underwriters, 252 N.W.2d 180, 181-82 (N.D.1977) (declining to apply clearly erroneous rule to findings based on documen *736 tary evidence), with Stracka v. Peterson, 377 N.W.2d 580, 582 (N.D.1985) (applying clearly erroneous rule to findings based on undisputed facts or documentary evidence). Driessen argues the district court clearly erred in finding he orally contracted with Schwartz Construction to provide aggregate for the project at $2 per cubic yard. Driessen argues there was no meeting of the minds between the parties, because his offer was conditioned upon Schwartz Construction securing a gravel pit to supply the aggregate, his offer was not accepted in a timely manner' and lapsed, and his offer was to supply aggregate at $2 per ton. Driessen argues the district court’s finding that there was an oral contract is not supported by substantial evidence and was induced by an erroneous view of the law. He also claims this Court should be left with a definite and firm conviction the district court made a mistake in finding he orally contracted with Schwartz Construction to provide aggregate at $2 per cubic yard.

[¶ 6] The existence of an oral contract and the extent of its terms are questions of fact, subject to the “clearly erroneous” standard of review under N.D.R.Civ.P. 52(a). Forster v. West Dakota Veterinary Clinic, Inc., 2004 ND 207, ¶ 57, 689 N.W.2d 366; Comstock Constr., Inc. v. Sheyenne Disposal, Inc., 2002 ND 141, ¶ 13, 651 N.W.2d 656. In Brandt v. Somerville, 2005 ND 35, ¶ 12, 692 N.W.2d 144 (citations omitted) we recently outlined our scope of review under the “clearly erroneous” rule:

A finding of fact is clearly erroneous if it is induced by an erroneous view of the law, if no evidence exists to support the finding, or if, on the entire record, we are left with a definite and firm conviction the trial court made a mistake. A trial court’s choice between two permissible views of the weight of the evidence is not clearly erroneous, and simply because we may have viewed the evidence differently does not entitle us to reverse the trial court. On appeal, we do not reweigh conflicts in the evidence, and we give due regard to the trial court’s opportunity to judge the credibility of the witnesses.

A

[¶ 7] Driessen argues the district court clearly erred in finding he did not condition his quote upon Schwartz Construction securing a gravel pit for the aggregate. Driessen argues the district court misapplied the law because the performance of the conditions of a proposal is necessary for the acceptance of a proposal under N.D.C.C. § 9-03-20 and the record clearly establishes he conditioned acceptance of his quote upon Schwartz Construction securing a gravel pit.

[¶ 8] Although Driessen testified his offer was conditioned upon Schwartz Construction procuring a gravel pit for the aggregate, Schwartz testified Driessen did not limit or condition his offer to Schwartz Construction. The district court found Driessen did not condition his quote upon Schwartz Construction securing a pit for the aggregate. On appeal, we do not reweigh conflicting evidence, and a choice between two permissible views of the evidence is not clearly erroneous. Brandt,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shift Services v. Ames Savage Water Solutions
2023 ND 237 (North Dakota Supreme Court, 2023)
PW Enterprises, Inc. v. Kaler
D. North Dakota, 2020
Tornabeni v. Cammie Wold, Roadrunner Hotshot & Servs., LLC
2018 ND 253 (North Dakota Supreme Court, 2018)
Tornabeni v. Wold
2018 ND 253 (North Dakota Supreme Court, 2018)
Titan Machinery, Inc. v. Patterson Enterprises, Inc.
2016 ND 19 (North Dakota Supreme Court, 2016)
Royal Jewelers, Inc. v. Light
2015 ND 44 (North Dakota Supreme Court, 2015)
Hoverson v. Hoverson
2015 ND 38 (North Dakota Supreme Court, 2015)
Lund v. Lund
2014 ND 133 (North Dakota Supreme Court, 2014)
Four Season's Healthcare Center, Inc. v. Linderkamp
2013 ND 159 (North Dakota Supreme Court, 2013)
Crandall v. Crandall
2011 ND 136 (North Dakota Supreme Court, 2011)
Willits v. Job Service of North Dakota
2011 ND 135 (North Dakota Supreme Court, 2011)
Community Homes of Bismarck, Inc. v. Main
2011 ND 27 (North Dakota Supreme Court, 2011)
State v. Wilson
2011 ND 18 (North Dakota Supreme Court, 2011)
RRMC Construction, Inc. v. Barth
2010 ND 60 (North Dakota Supreme Court, 2010)
Aasmundstad v. State
2008 ND 206 (North Dakota Supreme Court, 2009)
Doeden v. Stubstad
2008 ND 165 (North Dakota Supreme Court, 2008)
In Re Estate of Thompson
2008 ND 144 (North Dakota Supreme Court, 2008)
Overboe v. Brodshaug
2008 ND 112 (North Dakota Supreme Court, 2008)
In Re Estate of Elken
2007 ND 107 (North Dakota Supreme Court, 2007)
WFND, LLC v. Fargo Marc, LLC
2007 ND 67 (North Dakota Supreme Court, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
2006 ND 15, 709 N.W.2d 733, 2006 N.D. LEXIS 15, 2006 WL 231633, Counsel Stack Legal Research, https://law.counselstack.com/opinion/edward-h-schwartz-construction-inc-v-driessen-nd-2006.