Edward F. Fonder Co. v. United States

48 Ct. Cl. 198, 1913 U.S. Ct. Cl. LEXIS 128, 1912 WL 1185
CourtUnited States Court of Claims
DecidedFebruary 17, 1913
DocketNo. 29989
StatusPublished
Cited by1 cases

This text of 48 Ct. Cl. 198 (Edward F. Fonder Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Edward F. Fonder Co. v. United States, 48 Ct. Cl. 198, 1913 U.S. Ct. Cl. LEXIS 128, 1912 WL 1185 (cc 1913).

Opinion

AteiNSON, J.,

delivered the opinion of the court:

Plaintiff sues to recover the sum of $18,138.11, based upon various allegations in the petition that the defendants caused delays, extra woi*k not embraced in the contract, and that the liquidated damages set out in the supplemental contract were accepted by the plaintiff because of threats and coercion on the part of the agents of the Government.

The findings show that, on the 12th day of April, 1905, plaintiff entered into a contract with the War Department, agreeing to construct at the United States powder depot, near Dover, N. J., the following buildings and within the following periods of time:

One wheel and dynamo house, to be completed within 90 working days from the 12th day of April, 1905, for the sum of $4,500.

One storehouse for nitrate of soda, for the sum of $9,000.

Five storehouses for reserve supply of war materials, for the sum of $59,550.

Three storehouses for reserve supply of war materials, for the sum of $36,000.

These several buildings were to be constructed in accordance with the plans and specifications which had been duly published. One of the buildings was to be completed within 90 working days, two of the five within 90 working days, three within 180 working days, and the remaining three within 180 working days after the date of the contract. Also one powder house was to be completed within 150 working days, for which $27,500 was to be paid, and one magazine for high explosives, for the sum of $17,500. to be completed within 90 working days.

The contract and supplemental contract are filed as exhibits to plaintiff’s petition.

The original contract was entered into between the plaintiff company and the United States on the 12th day of April, 1905, as before stated, which provided for the erection of these 12 buildings for governmental purposes on the Pic[210]*210catinny Reservation, 5 miles from Dover, N. J. These structures were to be one story in height with no cellars, and the only excavations necessary were for proper foundations, for preparing sites for the buildings, and for grading a given area around each building.

Five of the buildings were to be completed on July 28, 1905, one on October 9, 1905, and six on November 13, 1905.

The plans of the buildings did not show the exact amount of excavation necessary. The ground, however, was comparatively level, and the buildings were to be widely separated.

It appears that in the preparation of the specifications the subject of excavation was discussed by the commanding officer, Col. O. B. Mitcham, and George E. Jenkins, the Government engineer in charge, and it was agreed by them to require the respective bidders to estimate the cost of this work, and the following requirements were accordingly incorporated in the specifications:

“ 3. The location and grade of the building shall be indicated by the commanding officer; the site shall be cleared by the contractor for the reception of the structure and for that purpose should be examined by Mm before bidding. The contractor must lay out his own work correctly and will be responsible for all lines, levels, and measurements.”
“ 25. Grade line. — The finished grade shall be as shown on plan. The surface, for a distance of 15 feet from the building, shall be graded on a fall of not less than one-half inch to the foot.”
“ 26. Excavation. — Excavate, as required by the site and drawings, for all the footings, piers, platforms, steps, downspout drains, etc., to the depths figured or shown, or to such depth as will provide absolute security against danger from frost or insecure foundations. This must be done irrespective of depth shown by drawings or figures and without extra charge. In no case is the depth to be less than 4 feet below the finished grade. Make the excavations 8 inches wider all round than the outside foundation, leaving same open till walls are well set and dry. * * * For removing rock found in ledges or bowlders in the excavations an extra sum per cubic yard will be paid, but no extra payment will be made excepting for rock exceeding 1 cubic yard in volume.”

[211]*211Plaintiff visited the sites of the buildings and went over the ground with the Government engineer in charge. The approximate sites of each building were pointed out to plaintiff, who necessarily observed the rolling or undulating character of the land. It is, however, not claimed by plaintiff that the ground at the sites shown him was flat and required no other excavation than the digging of trenches for foundations. The findings show that the ground upon which the buildings were to be constructed was rolling or undulating in character, but it does not appear that plaintiff was led to believe, as he avers, that he understood the grading, other than for trenches, would be done by the Government. It appears that he went to a near-by railroad cut to observe the character of material likely to be encountered in cutting down the hillocks to a general level in arranging the sites for the locations of the buildings. It further appears that plaintiff asked no questions about grading. He necessarily knew from the plans that a slight slope of not less than one-half inch to the foot was required for the distance of 15 feet from the wall of each of the buildings to be constructed. It seems unreasonable, therefore, that a skilled and experienced contracting firm would not have inquired who was to remove and pay for any high ground inside this level space of 15 feet around the buildings, if there was at the time any doubt in plaintiff company’s mind as to the matter of the expense of the gradings for* the sites of the different buildings embraced in the contract. Plaintiff would, of necessity, by the specifications, be required to clear the sites for the location of these several buildings, and it therefore seems reasonable to contend that a site would “ be cleared by the contractor for the reception of the structures ” if after he had excavated for a. practically flat space of 15 feet in width all around a building there should remain a mound in the center of the building site higher even than the floor of the structure he was required to build. Clearly plaintiff was required by the contract to prepare the sites of the buildings for their reception, and for 15 feet on all sides of all of them. If plaintiff failed to provide for this outlay in its estimates, it alone must bear the burden [212]*212of such, negligence. It does not appear that deception was practiced by the Government, nor is fraud shown by the testimony; consequently it was the duty of the contractor under the provisions of its contract to make all excavations necessary for the reception of the buildings on the sites designated by the Government’s engineer, and also to make such excavations and fills as were necessary to secure a grade approximating, as nearly as possible, the determined slope of not less than one-half inch per foot for 15 feet on all sides of each of the buildings.

Plaintiff’s counsel raises the question of the Government’s right to assess liquidated damages against it, and also alleges duress by the Government to compel it to accept the terms of a supplemental contract which was entered into between it and the United States.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lovell v. United States
61 Ct. Cl. 756 (Court of Claims, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
48 Ct. Cl. 198, 1913 U.S. Ct. Cl. LEXIS 128, 1912 WL 1185, Counsel Stack Legal Research, https://law.counselstack.com/opinion/edward-f-fonder-co-v-united-states-cc-1913.