Edward Chassaniol, Jr., Roofing & Siding, Inc. v. Ramsey

144 So. 2d 618, 1962 La. App. LEXIS 2311
CourtLouisiana Court of Appeal
DecidedSeptember 4, 1962
DocketNo. 476
StatusPublished
Cited by3 cases

This text of 144 So. 2d 618 (Edward Chassaniol, Jr., Roofing & Siding, Inc. v. Ramsey) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Edward Chassaniol, Jr., Roofing & Siding, Inc. v. Ramsey, 144 So. 2d 618, 1962 La. App. LEXIS 2311 (La. Ct. App. 1962).

Opinion

CECIL C. CUTRER, Judge pro tem.

The plaintiff, Edward Chassaniol, Jr., Roofing & Siding, Inc., seeks judgment against defendant, William A. Ramsey, in the sum of $921.25 representing the contract price of $914.00 for the installation of a roof on defendant’s premises and $7.25 for the cost of filing a material and labor lien against the property.

The defendant resists liability on the ground that the work was not performed in compliance with the contract. The defendant, by reconvention seeks $1,150.00, which he alleges is the sum necessary to properly perform the roofing work in question.

The trial court rendered judgment for plaintiff in the sum of $921.25, with legal interest thereon from date of judicial demand until paid, less a credit of $75.00, the sum required to make adjustments necessary to properly complete the work. From this judgment, appellant (defendant) brings this appeal.

The contract entered into by the parties provides as follows:

“Mr. D. W. Ramsey
“1030 N. Rendon St.
“New Orleans, La.
August 18, 1959
“Re: 3128 Ursuline Ave.
“Dear Sir:
“We propose to furnish labor and material to remove all tiles from entire main roof at the above address, remove existing felt and galvanized iron valley. Then over sheathing, we will apply one layer of 30 lb. felt tacked down securely with nails and tin caps. After this is done, we will furnish and install one new 26 gauge galvanized iron valley, then over felt, we will relay all good tiles salvaged by us and furnish necessary tiles to complete job. All tiles to be nailed with galvanized [620]*620zinc coated rust proof nails. All for the sum of
“($914.00)
“Debris will be removed by us and premises left clean.
“Trusting you will favor us with your acceptance of the above contract, we remain,
“Yours very truly,
“Edw. Chassaniol, Jr.
“Accepted Roofing & Siding, Inc.
“s/W. A. Ramsey 1959
“By 3/28/59 s/Edw. Chassaniol, Jr. “Addendum: All tiles to be nailed with two nails and no exposed nails, all felt to be removed to wood sheathing. All ridge tiles to be set in cement and sand.
“s/Edw. Chassaniol, Jr.”

The defendant contends that the evidence, adduced below, conclusively preponderates a lack of substantial compliance with the contract by the plaintiff. The defendant contends that plaintiff failed to comply with its contract in the following respects: Failing to secure each tile with two galvanized nails and leaving nails exposed below sheathing; failing to remove old roofing felt; failing to replace broken or otherwise defective tiles; the method used to remove and install the tiles caused damage to the new felt; and tiles were not laid in accordance with the method customarily followed in the performance of this type of work.

After plaintiff finished the work, defendant complained to plaintiff about defective workmanship, and particularly about exposed nails and crooked tile. Plaintiff, along with an employee, went to defendant’s premises for the purpose of rectifying the complaints. Upon arrival, defendant refused permission for plaintiff or his employee to do any further work on the roof. Plaintiff testified that he proposed to cut the nails flush with the sheathing thereby alleviating any protruding portion thereof. This procedure was common practice or procedure in the roofing business according to a number of the witnesses. According to the testimony, the longer nails were used in this sheathing since its condition was such that shorter nails would not hold the tile as well as the longer.

The defendant also contends that two nails were not driven to hold each tile. The evidence preponderates that the employees placed two nails in each tile with the exception of those instances where metal or a crack in the sheathing existed below the hole in the tile. In those exceptional instances only one nail was used for obvious reasons.

We turn next to the consideration of whether the plaintiff failed to comply with the contract by not removing the old felt before laying the new felt. The written contract explicitly provides that the old felt was to be removed. The plaintiff admits that the old felt was not removed, but relies on the testimony of Claude Ratleff, plaintiff’s foreman of this job, who testified as follows:

“Q Did Mr. Ramsey tell you anything about removing the felt, Mr. Rat-leff?
“A The first day I worked on the job Mr. Ramsey spoke to me about it.
“Q What did he say to you ?
“A He told me according to the contract, that the felt should have been taken off. I told Mr. Ramsey that I didn’t know anthing about that, so he said he would have to see about it. He in turn brought me downstairs inside his apartment where he was living and showed me the contract stating that the old felt should have been taken off. I answered Mr. Ramsey that I would have to speak to Mr. Chassaniol about it. I left and went home that afternoon. The next morning when I reported on the job, Mr. Ramsey met me and told me that I wouldn’t have to take the old felt off.
“Q Mr. Ramsey told you that himself?
[621]*621“A Yes, sir, he did.”

Upon questioning by the Court, this witness further testified as follows:

“THE COURT:
“Q Let me be sure I understand this. You say that you put new felt over the old felt, is that right?
“A Yes, sir, I did.
“Q Were there any tiles over the new felt when Mr. Ramsey called that to your attention?
“A When he called what to my attention ?
“Q That you should not have applied the new felt over the old felt.
“A Yes, sir, there were a few tiles down when he called that to my attention.
“Q The whole roof wasn’t tiled over the new felt when he talked to you, was it?
“A No, sir.
“Q Then it wasn’t a fact accomplished. The whole job wasn’t completed ?
“A Oh, no, sir.
“Q And the tile that had been put down could have been taken off and the new felt taken off, and the old felt removed and new felt laid, is that right?
“A Yes, sir.
“Q Without going to too much trouble or doing too much damage to the work that you had done, couldn’t it?
“A Yes, sir, Your Honor.
“Q And you tell me that Mr. Ramsey told you the next day that it wouldn’t be necessary to take off the old felt?
“A Yes, Your Honor. I explained that.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jim Walter Corporation v. Laperouse
196 So. 2d 539 (Louisiana Court of Appeal, 1967)
U-Finish Homes, Inc. v. Michel
183 So. 2d 101 (Louisiana Court of Appeal, 1965)
WWom, Inc. v. Grapes
181 So. 2d 289 (Louisiana Court of Appeal, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
144 So. 2d 618, 1962 La. App. LEXIS 2311, Counsel Stack Legal Research, https://law.counselstack.com/opinion/edward-chassaniol-jr-roofing-siding-inc-v-ramsey-lactapp-1962.