Edison Electric Illuminating Co. of New York v. Guastavino Fireproof Constr. Co.

44 N.Y.S. 1022, 16 A.D. 358
Appellate Division of the Supreme Court of the State of New York·Decided April 15, 1897·No. No. 1,089·Published·Cited by 1 cases

Opinion

INGRAHAM, J.

Upon this appeal, which is by the plaintiff from, the judgment entered upon the decision of the court at special term, the one question raised is as to the correctness of the finding by the trial court that there is due and owing from the plaintiff to the defendant the construction company the sum of $6,646.06; being the amount which the plaintiff agreed to pay for work to be performed and materials to be supplied by the said Guastavino Fireproof Construction Company in the construction of the plaintiff’s building mentioned and described in the complaint, after crediting the plaintiff with all payments made on account, and the necessary and reasonable cost of completing the said work subsequent to the abandonment thereof. The action was in the nature of an interpleader action, in which the plaintiff alleged in the complaint that the defendant the construction company furnished certain materials and performed certain labor for the plaintiff in and about certain premises of the plain[1023] tiff in the city of New York, and that the same were reasonably worth, and of the value of, $3,000, which sum is now due and owing by the plaintiff; that various claims had been made upon the plaintiff for the said sum of money by the defendants,—and demands judgment of interpleader, and that the plaintiff be directed to pay the sum due into court. Upon the trial the plaintiff asked leave to amend the complaint by alleging that the amount due was $2,750 instead of $3,000. The plaintiff proved upon the trial a contract between the plaintiff and the defendant the construction company by which the construction company agreed to do certain work upon a building to be erected by the plaintiff agreeably to the drawings made by the architects, and for which the plaintiff was to pay—

“The sum of thirty-five cents for each and every square foot of plain tile arches erected three courses in thickness; for all fire-clay flange finishing tile that may be required, an additional sum of sixteen cents for each and every square foot; and for all the tile arches over three courses in thickness, the sum of nine cents for each and every square foot of each additional course.”

The said contract provided that:

“Should, at any time during the progress of said works, the said party of the second part refuse or neglect to supply a sufficiency of materials or workmen, or suspend work on said building (except through stress of weather), said party of the first part shall have the power, and is hereby authorized, on giving two days’ written notice, to provide, at the expense of the party of the second part, materials and workmen to proceed with and finish the said works, and such expense shall be deducted from the amount required to be paid by this agreement; and, if such amount be insufficient to pay such expense, said party of the second part shall remain liable for any deficiency.”

The plaintiff then offered evidence tending to show that the total amount of the work done by the said company, which apparently included certain work done by the plaintiff after the construction company had abandoned the work, aggregated $43,998.71; that the plaintiff had paid to the construction company on account thereof the sum of $41,256.14, leaving a balance due from the plaintiff to the construction company of $2,612.57. The plaintiff further offered in evidence two letters written by the architects to the construction company, the first of which was dated February 7, 1894, whereby notice was given on behalf of the plaintiff to the construction company that, “if you do not proceed with the work under your contract on said building within three days from the date hereof, that others will be employed to complete your work at your expense,” which notice was substantially repeated in the second letter, of February 12, 1894. Thus, under this third clause of the contract, and the notice given on behalf of the plaintiff to the construction company, upon the failure of the construction company to continue the work the plaintiff was authorized to proceed and complete it; deducting the cost of such completion from the amount allowed as the contract price to be paid by the plaintiff. The question upon this appeal is therefore narrowed down to the question of fact as to the amount due by plaintiff to the construction company. This is to be determined by taking the amount due at the time the construction company abandoned the contract, adding the contract price for the work subsequently completed, and deducting the amount that the plaintiff was compelled to

Free access — add to your briefcase to read the full text and ask questions with AI

Edison Electric Illuminating Co. of New York v. Guastavino Fireproof Constr. Co., 44 N.Y.S. 1022, 16 A.D. 358 (N.Y. Ct. App. 1897).

44 N.Y.S. 1022 (Edison Electric Illuminating Co. of New York v. Guastavino Fireproof Constr. Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Murphy v. Williams
124 S.W. 900 (Texas Supreme Court, 1910)