EDF-RE US Development, LLC v. RES America Construction, Inc.

CourtCourt of Appeals of Minnesota
DecidedApril 29, 2024
Docketa231264
StatusPublished

This text of EDF-RE US Development, LLC v. RES America Construction, Inc. (EDF-RE US Development, LLC v. RES America Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
EDF-RE US Development, LLC v. RES America Construction, Inc., (Mich. Ct. App. 2024).

Opinion

This opinion is nonprecedential except as provided by Minn. R. Civ. App. P. 136.01, subd. 1(c).

STATE OF MINNESOTA IN COURT OF APPEALS A23-1264

EDF-RE US Development, LLC, Appellant,

vs.

RES America Construction, Inc., Respondent.

Filed April 29, 2024 Affirmed Slieter, Judge

Murray County District Court File No. 51-CV-23-23

Dean B. Thomson, Hugh D. Brown, Alexander B. Athmann, Fabyanske, Westra, Hart & Thomson, P.A., Minneapolis, Minnesota (for appellant)

James J. Hartnett, Joshua T. Peterson, Faegre Drinker Biddle & Reath LLP, Minneapolis, Minnesota (for respondent)

Considered and decided by Wheelock, Presiding Judge; Slieter, Judge; and Schmidt,

Judge.

NONPRECEDENTIAL OPINION

SLIETER, Judge

In this appeal from the rule 12.02 dismissal of its complaint, appellant argues that

the district court erred in determining that appellant’s breach-of-contract claim seeking

liquidated damages is barred by res judicata. Because the earlier claim involved the same set of factual circumstances and was adjudicated on the merits following a trial, appellant’s

claim is barred by res judicata. We therefore affirm.

FACTS

This is the second case in prolonged litigation between appellant EDF-RE US

Development LLC and respondent RES America Construction Inc. based on the

construction of a wind farm. The wind farm is located in Murray and Pipestone counties

and was developed by EDF-RE. EDF-RE contracted with RES for RES to construct the

wind farm. The contract included firm project-milestone deadlines and provided for the

payment of liquidated damages by RES for each deadline RES missed. It provided, “Any

Delay Liquidated Damages [RES] is obligated to pay to [EDF-RE] will be due and payable

within seven (7) Days after [EDF-RE] has invoiced [RES] for such amounts.”

We derive the following facts from our previous opinion, EDF-RE US Dev., LLC v.

RES Am. Constr., Inc., No. A21-1669, 2022 WL 17574687 (Minn. App. Dec. 12, 2022)

(EDF-RE I). Construction began in May 2018, and RES missed the deadlines for several

milestones. EDF-RE sent two liquidated damages invoices for the delays: one in the

amount of $10,000 and one in the amount of $45,000.

In March 2019, EDF-RE filed suit against RES which sought, among other remedies

for breach of contract, liquidated damages for all missed milestones in the total amount of

$5,766,500. Following a court trial after which the district court concluded that RES had

breached the contract due to the missed milestone, it determined that EDF-RE had “only

invoiced RES for $55,000.” The district court stated in its conclusions of law:

2 [I]t is clear and unambiguous the [liquidated damages] did not become due and payable until seven days after [EDF-RE] invoiced RES for such amounts. Consequently, only $55,000.00 of [EDF-RE’s] liquidated damages claim has become due and payable. It is this amount, plus interest at the contract rate, which is owed by RES to EDF-RE.

And in its order, the district court stated:

[RES] owes to [EDF-RE] $55,000.00 in invoiced liquidated damages, plus interest at the contract rate. [EDF-RE’s] remaining demand for liquidated damages in the amount of $5,711,500.00 ($5,766,500 - $55,000) is denied for failure to follow the requirements in the EPC Agreement to invoice RES for liquidated damages due and owing.

EDF-RE appealed to this court, claiming that it was entitled to the full amount of

liquidated damages. It made three arguments: (1) the agreement did not require EDF-RE

to invoice for the liquidated damages, (2) it was futile for EDF-RE to invoice for the

liquidated damages even if the agreement required one, and (3) its repeated demands for

the liquidated damages nevertheless fulfilled the requirement of an invoice. In a footnote

in its principal brief in that appeal, EDF-RE asked this court to “clarify” whether RES

would be liable for liquidated damages if EDF-RE were to later send an invoice.

This court affirmed. EDF-RE I, 2022 WL 17574687, at *1. We concluded that the

plain language of the agreement required EDF-RE to timely send an invoice for liquidated

damages, that futility did not excuse the performance of the invoice requirement, and that

the demand letter did not satisfy the requirement of an invoice. Id. at *4-6. We declined

to address EDF-RE’s request for clarification as to whether RES would be liable for

liquidated damages if EDF-RE sent a subsequent invoice. Id. at *7.

3 On January 18, 2023, EDF-RE sent an invoice dated January 13, 2023 to RES for

$5,711,000 in liquidated damages. RES declined to pay the invoice, citing res judicata.

In February, EDF-RE filed suit, alleging breach of contract and seeking the remaining

$5,711,000 of liquidated damages. RES moved to dismiss pursuant to Minn. R. Civ. P.

12.02(e) for failure to state a claim, arguing that EDF-RE’s claim was barred by res

judicata and collateral estoppel.

The district court granted RES’ motion. It determined that both res judicata and

collateral estoppel applied to prevent further litigation and, therefore, EDF-RE had failed

to state a claim upon which relief could be granted.

EDF-RE appeals.

DECISION

EDF-RE argues that the district court erred in its application of res judicata to its

new complaint, contending that the district court incorrectly analyzed two prongs of the

res judicata test. We are not persuaded.

Appellate courts review an order dismissing a case pursuant to Minn. R. Civ. P.

12.02(e) de novo. Hebert v. City of Fifty Lakes, 744 N.W.2d 226, 229 (Minn. 2008). A

district court’s application of res judicata likewise requires our de novo review. Rucker v.

Schmidt, 794 N.W.2d 114, 117 (Minn. 2011).

Res judicata is based on the principle that a claim adjudicated by a court cannot be

disputed in a later lawsuit between the same parties. Hauschildt v. Beckingham, 686

4 N.W.2d 829, 837 (Minn. 2004). 1 Res judicata, also called claim preclusion, applies

generally to a set of circumstances that gave rise to an entire lawsuit. Id. It applies

“regardless of whether a particular issue or legal theory was actually litigated.” Id. at 840.

There is a four-prong test for res judicata, and each prong must be met for the bar to apply.

Id.

Res judicata applies as an absolute bar to a subsequent claim when (1) the earlier claim involved the same set of factual circumstances; (2) the earlier claim involved the same parties or their privies; (3) there was a final judgment on the merits; (4) the estopped party had a full and fair opportunity to litigate the matter.

The district court determined that all four prongs were met. EDF-RE challenges

only the district court’s determination on the first and third prongs.

The Earlier Claim Involved the Same Set of Factual Circumstances.

EDF-RE suggests that because it sent an invoice after litigation ended in the

previous litigation, and RES declined to pay that invoice, its claim in this litigation is based

on two new facts: the new invoice and RES’ refusal to pay. RES counters that, because in

the previous lawsuit EDF-RE argued that it had satisfied the invoice requirement, the facts

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mahowald v. Minnesota Gas Co.
344 N.W.2d 856 (Supreme Court of Minnesota, 1984)
Krogness v. Best Buy Co., Inc.
524 N.W.2d 282 (Court of Appeals of Minnesota, 1994)
Paulos v. Johnson
597 N.W.2d 316 (Court of Appeals of Minnesota, 1999)
Hebert v. City of Fifty Lakes
744 N.W.2d 226 (Supreme Court of Minnesota, 2008)
Brown-Wilbert, Inc. v. Copeland Buhl & Co.
732 N.W.2d 209 (Supreme Court of Minnesota, 2007)
Garbush v. Order of United Commercial Travelers of America
228 N.W. 148 (Supreme Court of Minnesota, 1929)
Wisconsin v. Torinus
9 N.W. 725 (Supreme Court of Minnesota, 1881)
State ex rel. Nebraska State Bar Ass'n v. Rein
4 N.W.2d 829 (Nebraska Supreme Court, 1942)
Rucker v. Schmidt
794 N.W.2d 114 (Supreme Court of Minnesota, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
EDF-RE US Development, LLC v. RES America Construction, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/edf-re-us-development-llc-v-res-america-construction-inc-minnctapp-2024.