Edelblut Construction Co. v. Free

149 So. 2d 360
CourtDistrict Court of Appeal of Florida
DecidedJanuary 11, 1963
DocketNos. 2984, 3090
StatusPublished
Cited by4 cases

This text of 149 So. 2d 360 (Edelblut Construction Co. v. Free) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Edelblut Construction Co. v. Free, 149 So. 2d 360 (Fla. Ct. App. 1963).

Opinion

SHANNON, Chief Judge.

The defendants below have filed two appeals from the final decree rendered below. By previous order of this court these appeals were consolidated for all purposes and all pending ■ motions were carried over to the consideration of the case on its merits. At the outset, therefore, we shall dispose of the pending motions.

Final decree herein was rendered on November 16, 1961. On November 24, 1961, Appellee Hardrives filed petition for rehearing. On December 21, 1961, while Hardrives’ petition for rehearing was pending, defendants filed notice of appeal. Then, on January 12, 1962, the chancellor entered an order denying Appellee Har-drives’ petition for rehearing and setting supersedeas bond in the amount of $80,-000.00. Being in doubt as to the validity of the appeal, defendants filed a second notice of appeal on February 16, 1962. Now pending is a suggestion by appellants that this court lacks jurisdiction over the first appeal, No. 2984, on the ground that it was taken prematurely, since there was pending below an undisposed post-decretal motion. Coupled with the suggestion is a motion that this court set over to appeal in No. 3090, the supersedeas bond filed below, in the event the appeal in No. 2984 is dismissed. Additionally, Appellee Hardrives has filed a motion to dismiss the second appeal, No. 3090, on the ground that because one appeal was pending, the second is unauthorized.

Appellants’ suggestion is well taken and the appeal in Case No. 2984, commenced by filing notice of appeal on De[361]*361cember 21, 1961, is hereby dismissed on the authority of Seiferth v. Seiferth, Fla.App.1960, 121 So.2d 689, since an appellant cannot be said to have waived an unadjudicated motion filed in the lower court by the ap-pellee, because to do so would allow an appellant to deprive an appellee of a ruling and the incidental right to cross-assign error. Cf. Bannister v. Hart, Fla.App.1962, 144 So.2d 853; Guarria v. State Road Department, Fla.App.1960, 117 So.2d 5; and Frank v. Pioneer Metals, Inc., Fla.App. 1959, 114 So.2d 329.

Appellants’ motion to set over to the appeal in Case No. 3090, the supersedeas bond filed and approved below on February 8, 1962, is hereby granted. The motion of Appellee Hardrives to dismiss the appeal in Case No. 3090 is denied in view of our ruling as to Case No. 2984.

We proceed now to the merits of this litigation. Edelblut Construction Company, Inc., and United States Fidelity and Guaranty Company appeal from a final decree in the amount of $65,074.02 in favor of Free & Son, and in the sum of $58,345.37 in favor of Hardrives of Indian River, Inc., appellees.

The parties and the history of this litigation, as taken from the final decree entered below are as follows: The parties involved in the three suits originally filed are Gilman C. Free and Jack W. Free, doing business as Free & Son; Edelblut Construction Company, Inc.; Hardrives of Indian River, Inc.; the City of Vero Beach; Metropolitan Casualty Insurance Company of New York, surety for Gilman C. Free and Jack W. Free, doing business as Free & Son; and United States Fidelity and Guaranty Company, surety for Edel-blut Construction Company, Inc.

In March of 1958, the City entered into a prime contract with Edelblut which provided for sewer system improvements and a sewage collection system. After the contract was entered into with the City, Edelblut entered into a subcontract with Free. Later Free entered into a subcontract with Hardrives. Edelblut, Free and Hardrives all entered upon the performance of their contracts. A dispute arose between Edelblut and Free concerning the measurements to be used for payment by Edelblut to Free. Hardrives and Free ceased work under their respective contracts and in due time the above referred to suits followed. 1

In the first suit, filed September 18, 1958, Hardrives sued Free to recover damages for breach of contract. In the second suit, filed January 13, 1959, Free sued Edelblut to recover damages for breach of contract. The third suit, filed April 21, 1959, was brought by Free against Edelblut and Har-drives, seeking a declaratory decree and an order staying the above mentioned law actions. Upon hearing, an order was entered staying further proceedings in said law actions until further order of Court The City, Metropolitan and USF&G were added as parties to the suit. Later, an order was entered transferring the law actions to the chancery side of the Court, consolidating the three suits for trial and merging them into a single suit, and allowing the parties in the law actions time within which to appropriately amend their pleadings or to file additional pleadings, if desired, in the chancery suit, to fully comprehend their respective claims contained in their pleadings in the law actions.

Free, in its second amended complaint, alleged in detail the work performed and materials furnished by it pursuant to the contract and sought a money decree against Edelblut and USF&G therefor, together with interest and costs.

Hardrives, in its second answer, counterclaim and cross-claim, alleged in detail the work performed and materials furnished by it pursuant to the contract and sought a money decree against Free, Edelblut, Metropolitan and USF&G therefor, plus interest, cost and statutory attorney fees.

Edelblut, in its counterclaim against Free and Metropolitan alleged that because of the nonperformance of Free and because of [362]*362Free’s refusal to perform its contract, Edelblut sustained certan damages and sought a money decree against Free and Metropolitan therefor, together with interest and costs.

Edelblut, in its counterclaim against the City, sought a money decree against the City for the balance alleged to be due on the contract price in the sum of $38,120.26.

The City, in its amended answer to the counterclaim of Edelblut against the City, alleged that after the commencement of this action, and the filing of its original answer herein, it was indebted to Edelblut in the sum of $36,844.06; that after the filing of said answer and the taking of testimony in this cause, because of the refusal of Edelblut and its surety to comply with the provisions of the prime contract, it was necessary for the City to enter into a contract with Swords Brothers-McDougal, Inc., to complete the work and that the City became obligated to Swords Brothers-Mc-Dougal, Inc., in the sum of $19,560.05 therefor; that the City claims a set-off in the sum of $19,560.05 against the amount of $36,844.06 the City owed Edelblut, leaving a balance due Edelblut in the sum of $17,284.01.

The final decree, which grants judgments against the appellants is challenged for the following reasons: 1) The wording of the subcontract documents shows, as a matter of law, that Edelblut’s payment to Free and Free’s payment to Hardrives were to be limited to payment for pavement replaced up to a three-foot width. 2) Even if the prime contract’s width limitation on payment was properly not considered a part of the subcontract, the chancellor erred in awarding payment to Free and Hardrives in excess of the total yardage measured by the resident engineer. 3) The chancellor erred in awarding to Hardrives damages in excess of those allowed by Section 255.05, Florida Statutes, F.S.A. 4) The chancellor erred in not reducing the liability of appellants to Free by the amount appellants were held to be liable to Hardrives.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Quix Snaxx, Inc. v. Sorensen
710 So. 2d 152 (District Court of Appeal of Florida, 1998)
J & J Engineering, Inc. v. SAC Construction Co.
562 So. 2d 450 (District Court of Appeal of Florida, 1990)
United States v. Carl Geupal Construction Co.
423 F.2d 818 (Seventh Circuit, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
149 So. 2d 360, Counsel Stack Legal Research, https://law.counselstack.com/opinion/edelblut-construction-co-v-free-fladistctapp-1963.