Eddington-Griffitts Construction Co. v. Ireland

177 S.W. 259, 165 Ky. 518, 1915 Ky. LEXIS 551
CourtCourt of Appeals of Kentucky
DecidedJune 18, 1915
StatusPublished
Cited by2 cases

This text of 177 S.W. 259 (Eddington-Griffitts Construction Co. v. Ireland) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eddington-Griffitts Construction Co. v. Ireland, 177 S.W. 259, 165 Ky. 518, 1915 Ky. LEXIS 551 (Ky. Ct. App. 1915).

Opinion

Opinion of the Court by

Judge Settle

Affirming.

. This action was brought by the appellee, James Ireland, doing business as James Ireland & Company, against the Chesapeake & Ohio Kailway Company, the appellant Eddington-Griffitts Construction Company, . and others, its principal object being to recover of the Chesapeake & Ohio Kailway Company $13,000.00, with six per cent, interest from October 1, 1911, alleged to be a balance due appellee upon a contract whereby he undertook to construct and did construct for it certain work, consisting of excavation, grading and other like work, preparatory to the laying of double tracks along its line of railroad between Vanceburg and Carr’s- Station, in Lewis County,. Kentucky; it being alleged in the petition that the work was completed by appellee as required'by the terms of. the contract and duly accepted by the Chesapeake & Ohio Kailway Company, [520]*520which paid appellee at various times all that was due bim for the work performed by him under the contract, except the balance of $13,000.00 mentioned. The appellant, Edding'ton-G-riffitts Construction Company, and other persons made defendants to the action, were necessary parties because there were various sums due them for material furnished and labor ..done as subcontractors and otherwise for appellee under his contract with the Chesapeake & Ohio Railway Company, referred to, for which they were, respectively, asserting claim.

The Chesapeake & Ohio Railway Company answered, admitting that appellee and his sub-contractors and employes completed the construction work required by its contract with appellee and according to its terms, except a small part of same, from the doing and completion of which appellee was released by it; denied that ■there was due or owing to appellee in payment .of such work $13,000.00, but admitted an indebtedness to him therefor of $12,505.26, which, upon its motion, it was allowed to pay into court, to be distributed to whomsoever the court might direct.

The answer was made a cross-petition against the Eddington-Griffitts Construction Company and o.ther defendants in the petition, asking that they be required to set up and litigate with the appellee whatever claims they were respectively entitled to assert, under .lien or otherwise, against the fund which it paid into court.

By an amended petition appellee admitted that the indebtedness of the Chesapeake & Ohio Railway Company to bim was $12,505.26, as averred in its answer, instead of $13,000.00 as alleged in the petition. The ease was referred to the master Commissioner to hear proof upon and report the various claims for which liens were asserted against the fund in question.

The appellant, Eddington-Griffitts Construction Company, by its answer to the petition, which was made a counter-claim against appellee and a cross-petition against its co-defendants, Chesapeake & Ohio Railway Company and others, alleged that by contract with the appellee, James Ireland, it agreed and undertook to place upon the work of construction that the latter had contracted to do for the Chesapeake & Ohio Railway Company sufficient of its construction equipment for that purpose, and to do all the shovel work necessary to be done in such construction, for which it was to be paid [521]*521by appellee certain prices set forth in the contract and. in its answer; that it performed the work which it undertook to do for appellee according to the terms of the contract and was paid by the latter therefor various sums, leaving, as alleged, due it the amount and balance of $18,433.94, $4,684.71 of which was made up of charges at the rate of one cent for each 100 feet of “overhaul,” in excess of a distance of 1,000 feet, performed on certain parts of the work. For the $18,433.94 thus alleged to be due it, appellant asserted a lien, as allowed by statute in such cases, and asked judgment for its enforcement, as well as a personal judgment against appellee. ■

Appellee, both by amended petition and reply, controverted the claim of the appellant, Eddington-Griffitts Construction Company, to the extent of denying any liability on his part for the item of $4,684.71; but admitted his indebtedness to appellant for some part of the $13,759.25 remaining of the $18,433.94 of the latter’s claim, without being able to state definitely the amount of such indebtedness; alleged, however, that ;such indebtedness should be credited upon the amount of damages resulting to appellee from appellant’s failure to perform certain parts of the work required of it by its contract with appellee. That is, it was alleged that by reason of appellant’s failure to do the necessary .steam shovel work at Stamper’s fill, required by its contract with appellee, consisting of about 10,000 yards of earth excavation and overhaul, appellee was delayed in completing his contract with the Chesapeake & Ohio Railway Company and compelled to procure equipment at great cost, expend large sums of money in getting such equipment on the ground, and for labor, in doing the work which he was compelled by his contract with the Chesapeake & Ohio Railway Company to perform himself, after appellant’s failure to do so; by all of which he was damaged in the sum of $15,000.00.

It was further alleged that by reason of appellant’s .failure to comply with its contract in the particular mentioned, appellee was damaged $15,000.00 by reason of his being prevented from taking other contracts and ■doing other work for the Chesapeake & Ohio Railway ■Company after September 20, 1911, the date on which his contract with that company, in which appellant undertook to aid him, was to have been completed, from which ffie expected and would have received large profits;; [522]*522and that appellant, at the time of entering into the -eon-' tract it made with appellee referred to, knew that the latter had in contemplation the taking of other contracts and doing of other work for the Chesapeake Railway Company, following its completion, from which he would have received such profits.

All affirmative matter of appellee’s amended petition and reply was controverted by appellant’s answer and rejoinder, and in the latter pleading it was, in substance, alleged in explanation of its failure to do' the steam shovel work at the Stamper fill: (1) That it was not required of it by its contract with appellee; (2) That appellee contracted with one Simpson to do the work at Stamper’s fill; and (3) That it did not continue the work at Stamper’s fill because of appellee’s violation of his contract with it, in failing to pay it with -the promptness required by the contract, for the work it had previously done for the Chesapeake & Ohio Railway Company.

There was a trial by jury of the matters in issue between appellant and appellee, resulting- in the following verdict:

“We, the jury, find for the defendant $14,330.97, as instructed by the court. -

“We,, the jury find for the plaintiff $10,500 less $3,500.00. ■

“J. A. Cooper, Foreman.”

The $7,000.00 awarded appellee by the verdict was credited on the $14,330.97 it awarded appellant, and judgment entered against appellee in favor of appellant for the difference of $7,330.97. Appellant, complaining of that judgment and the refusal of the circuit court to grant it' a new trial, by this appeal seeks its reversal.

The facts, as we understand them from our examination of the evidence, are: That appellee, after entering into the contract with the Chesapeake &

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnson v. Tackitt
191 S.W. 117 (Court of Appeals of Kentucky, 1917)
Eddington-Griffitts Construction Co. v. Ireland
181 S.W. 975 (Court of Appeals of Kentucky, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
177 S.W. 259, 165 Ky. 518, 1915 Ky. LEXIS 551, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eddington-griffitts-construction-co-v-ireland-kyctapp-1915.