Ecosystem Investment Partners v. United States of

CourtCourt of Appeals for the Fifth Circuit
DecidedMarch 20, 2018
Docket17-30441
StatusUnpublished

This text of Ecosystem Investment Partners v. United States of (Ecosystem Investment Partners v. United States of) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ecosystem Investment Partners v. United States of, (5th Cir. 2018).

Opinion

Case: 17-30441 Document: 00514394390 Page: 1 Date Filed: 03/20/2018

IN THE UNITED STATES COURT OF APPEALS FOR THE FIFTH CIRCUIT United States Court of Appeals Fifth Circuit

No. 17-30441 FILED March 20, 2018 Lyle W. Cayce ECOSYSTEM INVESTMENT PARTNERS, Clerk

Plaintiff - Appellant

v.

CROSBY DREDGING, L.L.C.; UNITED STATES OF AMERICA,

Defendants - Appellees

Appeal from the United States District Court for the Eastern District of Louisiana USDC No. 2:16-CV-16504

Before KING, ELROD, and GRAVES, Circuit Judges. PER CURIAM:* Ecosystem Investment Partners (EIP) invests in projects which restore, build, improve, and protect natural resources. For its efforts, the Government compensates EIP with environmental-mitigation credits. EIP then sells those credits to entities seeking to offset their ecologically destructive actions. This lawsuit arose after the Army Corps of Engineers decided to build new wetlands to offset environmental damage from another one of its projects.

* Pursuant to 5TH CIR. R. 47.5, the court has determined that this opinion should not be published and is not precedent except under the limited circumstances set forth in 5TH CIR. R. 47.5.4. Case: 17-30441 Document: 00514394390 Page: 2 Date Filed: 03/20/2018

No. 17-30441 EIP sued the Corps and the Corps’ contractor, alleging that the Corps violated the National Environmental Policy Act (NEPA) by deciding to build its own wetlands without considering whether EIP’s credits were a reasonable alternative. EIP asked the district court to order the Corps not to build the new wetlands. EIP’s lawsuit was dismissed, and it took this appeal. We agree with the district court that EIP lacks statutory standing to sue. EIP has not alleged an environmental injury that would place it within NEPA’s zone of interests. Accordingly, EIP lacks a legislatively conferred cause of action, and thus we AFFIRM. I. After Hurricane Katrina devastated New Orleans in 2005, Congress authorized and funded the United States Army Corps of Engineers to develop a storm-and-flood-protection system in southeast Louisiana. This Hurricane and Storm Damage Risk Reduction System (HSDRRS) was to involve the construction of a series of canals, floodwalls, and levees. This sort of development obligated the Corps under the Water Resources Development Act of 1986 (WRDA) to produce a report with “a specific plan to mitigate for damages to ecological resources.” See 33 U.S.C. § 2283(d)(1). As the mitigation report pertained to a “major Federal action[] significantly affecting the quality of the human environment,” the Corps was required under NEPA to prepare an environmental-impact statement (EIS) detailing “the environmental impact of” and “alternatives to” its proposed action. See 42 U.S.C. § 4332(C)(i), (iii); 40 C.F.R. § 1508.11 (defining EIS). To expedite its NEPA analysis, the Corps and the Council on Environmental Quality (the body charged with overseeing the implementation of NEPA, see 42 U.S.C. §§ 4342–4344), agreed to an emergency arrangement. See 40 C.F.R. § 1506.11. Under the arrangement, the Corps would issue individual environmental reports (IERs). This would allow the Corps to 2 Case: 17-30441 Document: 00514394390 Page: 3 Date Filed: 03/20/2018

No. 17-30441 consider the impact of its actions piecemeal rather than omnibus in the hopes of accelerating the project. Of relevance to this appeal are a pair of IERs analyzing the Corps’ plans to offset the HSDRRS’s destruction of brackish marsh in and near Lake Pontchartrain (a lake directly to the north and east of New Orleans). For those unfamiliar with coastal-wetland ecology, brackish marshes are moderately salty marshes that form upstream of salt marshes and whose salinity is diluted by the influx of fresh water from coastal rivers. The Corps’ first IER contemplated that the HSDRRS’s brackish-marsh destruction could be offset with credits purchased from Corps-approved mitigation banks. Mitigation banks, per Corps regulation, are sites “where resources (e.g., wetlands, streams, riparian areas) are restored, established, enhanced, and/or preserved for the purpose of providing compensatory mitigation for impacts authorized by [Corps] permits.” See 33 C.F.R. § 332.2. The Corps releases credits to the mitigation bank’s sponsor, who will then usually sell its “credits to permittees whose obligation to provide compensatory mitigation is then transferred to the mitigation bank sponsor.” See id. But less than a year after this IER, which contemplated the use of mitigation banks, the Corps reversed course in a supplemental IER (SIER). Instead of buying credits to offset its destruction of brackish marsh, the Corps decided to build its own replacement marshes. To that effect, the Corps decided to build three mitigation projects. The New Zydeco Ridge project is the third of these projects and the subject of this lawsuit. The Corps awarded the contract for the New Zydeco Ridge project to Crosby Dredging, LLC. Three days later, EIP brought this lawsuit. EIP sued the Corps and Crosby Dredging and asked the district court to enjoin construction of the New Zydeco Ridge project. EIP’s complaint alleges that it owns the only Corps-approved brackish-marsh mitigation bank in the 3 Case: 17-30441 Document: 00514394390 Page: 4 Date Filed: 03/20/2018

No. 17-30441 Lake Pontchartrain region. To offset brackish-marsh destruction in the region, the Corps calculated that it needed a total of 118 mitigation units (known as Average Annual Habitat Units, or AAHUs). When the Corps first issued its SIER, EIP claims that it had credits worth 3.0 AAHUs available for sale or transfer to offset this brackish-marsh destruction. Nine months later—but a full year and a half before the Corps awarded the contract to Crosby Dredging—the Corps released more credits to EIP, bringing EIP’s credit total up to a value of 25 AAHUs. By contrast, the New Zydeco Ridge project would provide, EIP asserts, only 23.7 AAHUs in mitigation out of the 118 needed. Based on this, EIP claimed the Corps violated NEPA in two ways. The Corps violated NEPA, according to EIP, when it issued its SIER without considering the alternative of purchasing EIP’s credits. See 42 U.S.C. § 4332(C)(iii) (requiring a list of “alternatives to the proposed action”). And the Corps violated NEPA again, per EIP’s complaint, when it did not supplement its NEPA analysis after the value of EIP’s credits reached 25 AAHUs. See 40 C.F.R. § 1502.9(c)(1)(ii) (requiring a supplement when “significant new circumstances or information relevant to environmental concerns and bearing on the proposed action or its impacts” arise). As NEPA does not afford private litigants a cause of action to enforce its provisions, see Fla. Audubon Soc’y v. Bentsen, 94 F.3d 658, 665 (D.C. Cir. 1996) (en banc), EIP brought its claim through section 10(a) of the Administrative Procedure Act (APA), see 5 U.S.C. § 702. Both defendants moved to dismiss based on failure to state a claim under Rule 12(b)(6).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sierra Club v. Glickman
156 F.3d 606 (Fifth Circuit, 1998)
Collins v. Morgan Stanley Dean Witter
224 F.3d 496 (Fifth Circuit, 2000)
Texas Democratic Party v. Benkiser
459 F.3d 582 (Fifth Circuit, 2006)
Dorsey v. Portfolio Equities, Inc.
540 F.3d 333 (Fifth Circuit, 2008)
Gonzalez v. Kay
577 F.3d 600 (Fifth Circuit, 2009)
McGowan v. Maryland
366 U.S. 420 (Supreme Court, 1961)
Sierra Club v. Morton
405 U.S. 727 (Supreme Court, 1972)
Regents of the University of California v. Bakke
438 U.S. 265 (Supreme Court, 1978)
Allen v. Wright
468 U.S. 737 (Supreme Court, 1984)
Clarke v. Securities Industry Assn.
479 U.S. 388 (Supreme Court, 1987)
Robertson v. Methow Valley Citizens Council
490 U.S. 332 (Supreme Court, 1989)
Lujan v. National Wildlife Federation
497 U.S. 871 (Supreme Court, 1990)
Lujan v. Defenders of Wildlife
504 U.S. 555 (Supreme Court, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
Ecosystem Investment Partners v. United States of, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ecosystem-investment-partners-v-united-states-of-ca5-2018.