Ecoproduct Solutions, L.P. v. Englobal Engineering and Swenson Technology, Inc.

CourtCourt of Appeals of Texas
DecidedJune 30, 2011
Docket01-10-00366-CV
StatusPublished

This text of Ecoproduct Solutions, L.P. v. Englobal Engineering and Swenson Technology, Inc. (Ecoproduct Solutions, L.P. v. Englobal Engineering and Swenson Technology, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ecoproduct Solutions, L.P. v. Englobal Engineering and Swenson Technology, Inc., (Tex. Ct. App. 2011).

Opinion

Opinion issued June 30, 2011

In The

Court of Appeals

For The

First District of Texas

————————————

NO. 01-10-00366-CV

———————————

EcoProduct Solutions, L.P., Appellant

V.

ENGlobal Engineering, Inc. and Swenson Technology, Inc., Appellees

On Appeal from the 270th District Court

Harris County, Texas

Trial Court Case No. 2009-64881

MEMORANDUM OPINION

          EcoProduct Solutions, L.L.P. appeals from summary judgments granted in favor of ENGlobal Engineering, Inc. and Swenson Technology, Inc. on EcoProduct’s claims against them. We affirm.

Background

          This dispute arises out of the construction of a liquid calcium chloride manufacturing plant. EcoProduct created the process design for the plant, hired ENGlobal to provide engineering services, and acquired the evaporator system for the plant from Swenson. EcoProduct’s contracts with Swenson and ENGlobal each contain an arbitration provision requiring that any dispute arising out of or in connection with the contract be submitted to binding arbitration in Houston, Texas in accordance with the Commercial Arbitration Rules of the American Arbitration Association.

After problems arose with the plant, EcoProduct initiated an arbitration against Swenson. Two and a half months later, on October 31, 2008, EcoProduct sought to join ENGlobal into the Swenson arbitration. Swenson objected to joining ENGlobal in their ongoing arbitration; ENGlobal also did not consent to the joinder. In November 2008, the AAA declined to allow EcoProduct to join ENGlobal into the pending arbitration without ENGlobal’s and Swenson’s consent, noting that the parties had different arbitration contracts. The AAA advised EcoProduct that it could revisit the issue with the Swenson arbitration panel once the full panel was appointed. EcoProduct did not initiate a separate arbitration proceeding against ENGlobal or raise the issue again with the arbitration panel. Instead, EcoProduct sued ENGlobal and Swenson in state court in October 2009, approximately one year after the AAA declined to join ENGlobal into the Swenson arbitration.

EcoProduct’s petition contained an “arbitration caveat,” in which EcoProduct stated that it and Swenson were currently engaged in arbitration and requested that the trial court compel ENGlobal to join the pending arbitration and then abate the suit. EcoProduct’s petition did not merely seek arbitration; EcoProduct pled substantive causes of action against ENGlobal and Swenson for breach of contract, breach of warranty, negligence, fraudulent inducement, promissory estoppel, negligent misrepresentation and violations of the Texas Deceptive Trade Practices Act[1] and prayed for the award of actual damages of $45,000,000, exemplary damages, attorneys’ fees, and interest. The prayer of EcoProduct’s petition did not reference arbitration. EcoProduct’s petition also contained a request for disclosures, demand for jury trial, and statement that EcoProduct had paid the requisite jury fee.

In November 2009, ENGlobal answered EcoProduct’s petition and moved for traditional summary judgment on the basis of the applicable statutes of limitations. ENGlobal’s summary judgment evidence included an affidavit averring that ENGlobal’s work on the plant project was completed in August 2005, more than four years before EcoProduct filed suit. ENGlobal also moved to dismiss EcoProduct’s negligence claims for failure to file a certificate of merit in compliance with Chapter 150 of the Civil Practices and Remedies Code.

In December, Swenson answered and moved for traditional and no-evidence summary judgments, arguing that (1) EcoProduct’s claims under the DTPA were precluded by the DTPA’s statutory exclusions, (2) EcoProduct’s negligence claims were barred by the statute of limitations and were an improper recasting of its breach of contract claims, (3) the warranties pled were expressly disclaimed, (4) with respect to the breach of contract claim, there was no evidence that EcoProduct performed under the contract, (5) EcoProduct’s estoppel allegations were preempted by the parties’ contract, (6) the fraudulent inducement claim was defeated by the disclaimer of reliance in the parties’ contract, and (7) the contract barred recovery of consequential and exemplary damages.

On January 14, 2010, one week before the summary judgment hearings, EcoProduct moved to compel arbitration. The prayer of the motion to compel asked the trial court to “[o]rder all parties to Arbitration under [the pending arbitration against Swenson.]” In the text of the motion, EcoProduct asked, in the alternative, that the court “[c]ompel Arbitration against ENGlobal only and to consolidate” that arbitration with the pending arbitration against Swenson, either for discovery purposes or to have a single proceeding with two separate panels. The record on appeal does not reflect that EcoProduct ever set its motion to compel arbitration for hearing or submission.

EcoProduct also filed motions to “dismiss” the motions for summary judgment,[2] contending that the only issue the trial court could address in the suit was whether to compel arbitration. In its motions to dismiss, EcoProduct noted that it had filed a motion to compel arbitration, but it did not indicate that the motion had been set for hearing or submission or was otherwise before the court at that time. EcoProduct did not file a motion for continuance of the summary judgment hearing to allow it more time to obtain a hearing on or submission of its motion to compel arbitration. But its motions to dismiss each contained this sentence: “Should the Court determine jurisdiction is proper to determine the merits of [ENGlobal’s and Swenson’s motions for summary judgment], we ask [] the Court for an abatement of this motion until such time [as] proper relief is sought through AAA.” In the prayer of the motions to dismiss, EcoProduct asked the court to compel arbitration in the pending arbitration against Swenson.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dean Witter Reynolds Inc. v. Byrd
470 U.S. 213 (Supreme Court, 1985)
J.M. Davidson, Inc. v. Webster
128 S.W.3d 223 (Texas Supreme Court, 2003)
Valence Operating Co. v. Dorsett
164 S.W.3d 656 (Texas Supreme Court, 2005)
Peter C. Browning v. Jeff P. Prostok
165 S.W.3d 336 (Texas Supreme Court, 2005)
Diversicare General Partner, Inc. v. Rubio
185 S.W.3d 842 (Texas Supreme Court, 2005)
Ed Rachal Foundation v. D'UNGER
207 S.W.3d 330 (Texas Supreme Court, 2006)
In Re D. Wilson Const. Co.
196 S.W.3d 774 (Texas Supreme Court, 2006)
MacK Trucks, Inc. v. Tamez
206 S.W.3d 572 (Texas Supreme Court, 2006)
In Re Merrill Lynch Trust Co. FSB
235 S.W.3d 185 (Texas Supreme Court, 2007)
Perry Homes v. Cull
258 S.W.3d 580 (Texas Supreme Court, 2008)
In Re Fleetwood Homes of Texas, L.P.
257 S.W.3d 692 (Texas Supreme Court, 2008)
Mann Frankfort Stein & Lipp Advisors, Inc. v. Fielding
289 S.W.3d 844 (Texas Supreme Court, 2009)
Centeq Realty, Inc. v. Siegler
899 S.W.2d 195 (Texas Supreme Court, 1995)
San Saba Energy, L.P. v. Crawford
171 S.W.3d 323 (Court of Appeals of Texas, 2005)
Woods v. William M. Mercer, Inc.
769 S.W.2d 515 (Texas Supreme Court, 1988)
Malooly Brothers, Inc. v. Napier
461 S.W.2d 119 (Texas Supreme Court, 1970)
Vickery v. Vickery
999 S.W.2d 342 (Texas Supreme Court, 1999)
Stine v. Stewart
80 S.W.3d 586 (Texas Supreme Court, 2002)
Tenneco Inc. v. Enterprise Products Co.
925 S.W.2d 640 (Texas Supreme Court, 1996)
Williams Industries, Inc. v. Earth Development Systems Corp.
110 S.W.3d 131 (Court of Appeals of Texas, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
Ecoproduct Solutions, L.P. v. Englobal Engineering and Swenson Technology, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/ecoproduct-solutions-lp-v-englobal-engineering-and-texapp-2011.