Economy Forms Corporation v. Kandy, Inc.

391 F. Supp. 944, 17 U.C.C. Rep. Serv. (West) 93, 1974 U.S. Dist. LEXIS 9221
CourtDistrict Court, N.D. Georgia
DecidedMarch 29, 1974
DocketCiv. A. 2428
StatusPublished
Cited by6 cases

This text of 391 F. Supp. 944 (Economy Forms Corporation v. Kandy, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Economy Forms Corporation v. Kandy, Inc., 391 F. Supp. 944, 17 U.C.C. Rep. Serv. (West) 93, 1974 U.S. Dist. LEXIS 9221 (N.D. Ga. 1974).

Opinion

*946 ORDER

O’KELLEY, District Judge.

The foregoing matter was tried before the Court without a jury. Based upon the evidence and stipulation of the parties, the Court finds that it has jurisdiction of the case, and makes its findings of fact and conclusions of law as follows:

FINDINGS OF FACT

The Court finds that the plaintiff and defendant entered into a Purchase Order contract in the amount of $74,096.14 whereby the plaintiff was to manufacture and deliver to defendant some steel concrete forming equipment which included Cantilever forms for Monoliths D-l through D-ll, the Ogee forming equipment and certain equipment for the construction of piers, all of which equipment was to be used on the Carters Re-regulation Dam Project where the defendant was general contractor for the construction of said project. At the time of entry into the Purchase Order, defendant paid $17,985.00 leaving a balance of $56,111.14. The contract provided that interest was to be paid on the outstanding balance, thirty days after delivery, at 10 percent per annum. The parties in the pretrial order stipulated that the equipment was delivered starting January 8, 1970, through April 16, 1970. The Court finds that there is no dispute as to the contract terms nor as to the amount of the balance left owing on said contract, it being $56,111.14, and interest at 10 percent thirty days after delivery.

The Court further finds that the plaintiff, pursuant to the terms of Exhibit 2, shipped to defendant on open account certain accessory equipment in the amount of $829.87, however, the defendant alleges that this equipment should have been provided to the defendant as a part of the equipment delivered under the purchase order contract between the parties. Said equipment was furnished November 1, 1971.

Defendant, in its counterclaim, claims that it is entitled to an offset in the amount of $48,750.25, and alleges that certain oral representations were made to it by the plaintiff’s sales agent, wherein it was represented to defendant that the forms would accommodate the water-stop requirements on the job and that there would be no need for supplementary wood to be used on this job. The defendant claims that as a result of these representations, it purchased the equipment, that the equipment did not perform as warranted in that it was not designed to accommodate waterstop and that additional wood was needed in order to perform the job.

Plaintiff has raised certain defenses based upon the contract limiting warranties and excluding additional consequential damages. Plaintiff contends that the contract is clear and unambiguous on its face and does not set out any warranties in addition to those clearly stated on the face of the document itself, and that it was not accepted by the plaintiff until such time as the type of equipment was demonstrated and explained to the defendant’s agents and was accepted by the defendant through its agents. Plaintiff further raises the affirmative defenses to defendant’s counterclaims of waiver, estoppel and mitigation of damages.

The Court finds that the defendant was advised by plaintiff that equipment would accommodate waterstop prior to the time that said purchase order contract was executed by defendant. Sometime in October the plaintiff’s agent, Gary Pursley, was notified by plaintiff’s home office that the purchase order as submitted, could not be accepted by plaintiff unless defendant would agree to accept the equipment as shown on the erection drawings which called for a split waterstop. It further appears that in October, 1970, the defendant’s agents at the job in Carters, Georgia, received copies of the plaintiff's erection drawings and had an opportunity to review them.

*947 In November 1970, Mr. Don Bryan, district manager for the plaintiff, went to the job at Carters, Georgia, and discussed the job with the defendant’s superintendent on the job and Mr. John Cory. He received oral approval of the erection drawings and then advised the plaintiff’s home office that the defendant had approved the erection drawings and had accepted the purchase order, and the plaintiff was to commence the manufacturing of the equipment pursuant to the erection drawings. Based on this, plaintiff did accept the purchase order and manufactured the equipment. It further appears before this date that the defendant submitted a split waterstop to the Corps of Engineers, which submission was subsequently disapproved. Mr. Tom Jaudon, the field representative for the plaintiff, visited the job site upon three occasions in January. At the last meeting in January, there was enough equipment on the job site to begin setting it up in preparation for the job. At that time Mr. Jaudon went over the erection drawing^ and equipment on the job and the sequence of work to be done on the project with the defendant’s superintendent, Mr. Forrest Nowlin. At that time Mr. Jaudon discussed with Mr. Nowlin and Mr. Cory, the waterstop accommodation and went over various methods of water-stop accommodation with them. He was not advised that the waterstop accommodation set out in the erection drawings was not satisfactory to the defendant.

The first pour on the job, Monolith D-l, was commenced in April, 1971, at which time the pour was being made immediately above the rock and did not require the use of the plaintiff’s Cantilever forms. Defendant built some wooden forms to accommodate waterstop but did not advise Mr. Tom Jaudon, who was there assisting them, that they were unhappy with the manner of waterstop accommodation nor did they request any modification of the forms at that time. Mr. Jaudon, shortly thereafter on April 6, 1970, talked to. defendant’s president, Mr. Frank King, and advised him that the defendant would need additional equipment in order to complete the scheduling of the pours on the piers in an orderly manner. As a result of that conversation, the defendant executed a purchase order with the plaintiff for additional pier forms, which equipment was delivered to defendant and paid for by it. Subsequently, in May of 1971, the plaintiff’s agent, Mr. Tom Jaudon, met with the defendant’s agent, Mr. King, at the airport in Atlanta, Georgia, where Mr. Jaudon gave to him a section of split waterstop. Mr. Frank King advised Mr. Jaudon that he would submit this to the Corps of Engineers and that if he needed any help in submitting it, he would call upon Mr. Jaudon for his assistance. Mr. Jaudon’s assistance was never requested and he was not advised of the fact that the split waterstop accommodation had been denied. During the construction the defendant used the forms out of the sequence in which they were designed to be used as provided by the plaintiff and they were taken all over the construction location. Additional holes were drilled in most of the forms by defendant’s agents because of this improper use of the forms. ■

The only forms which would have had to have been redrilled would at the most have involved only six individual bulkheads of the eleven monoliths and would have involved no more than thirty-six panels, which at two holes per panel would have constituted no more than seventy-six holes.

The defendant failed to produce any evidence from its own records which would advise the court of the number of holes which were allegedly drilled as a result of the waterstop problem.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
391 F. Supp. 944, 17 U.C.C. Rep. Serv. (West) 93, 1974 U.S. Dist. LEXIS 9221, Counsel Stack Legal Research, https://law.counselstack.com/opinion/economy-forms-corporation-v-kandy-inc-gand-1974.