Ecodyne Cooling Division of Ecodyne Corporation, a Delaware Corporation, Plaintiff-Counterclaim v. City of Lakeland, Defendant-Counterclaim v. Ecodyne Cooling Division Fairfield Engineering Federal Insurance Company St. Paul Fire and Marine Insurance Company Charles T. Main, Inc. Blount International Ltd. United States Fidelity and Guaranty Company Aetna Casualty and Surety Company Fireman's Fund Insurance Company A.O. Smith-Inland, Inc. And Armco, Inc., Counterclaim Charles T. Main, Inc., Counterclaim Third-Party v. The Munters Corporation Julian Tobey & Associates John T. Boyd Company Ingersoll-Rand Company Atlanta Engineering Company Envirex, Inc. Babcock & Wilcox Company Milton Roy Company and Electric MacHinery Enterprises, Third-Party

893 F.2d 297, 1990 U.S. App. LEXIS 943
CourtCourt of Appeals for the Third Circuit
DecidedJanuary 29, 1990
Docket88-3761
StatusPublished

This text of 893 F.2d 297 (Ecodyne Cooling Division of Ecodyne Corporation, a Delaware Corporation, Plaintiff-Counterclaim v. City of Lakeland, Defendant-Counterclaim v. Ecodyne Cooling Division Fairfield Engineering Federal Insurance Company St. Paul Fire and Marine Insurance Company Charles T. Main, Inc. Blount International Ltd. United States Fidelity and Guaranty Company Aetna Casualty and Surety Company Fireman's Fund Insurance Company A.O. Smith-Inland, Inc. And Armco, Inc., Counterclaim Charles T. Main, Inc., Counterclaim Third-Party v. The Munters Corporation Julian Tobey & Associates John T. Boyd Company Ingersoll-Rand Company Atlanta Engineering Company Envirex, Inc. Babcock & Wilcox Company Milton Roy Company and Electric MacHinery Enterprises, Third-Party) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ecodyne Cooling Division of Ecodyne Corporation, a Delaware Corporation, Plaintiff-Counterclaim v. City of Lakeland, Defendant-Counterclaim v. Ecodyne Cooling Division Fairfield Engineering Federal Insurance Company St. Paul Fire and Marine Insurance Company Charles T. Main, Inc. Blount International Ltd. United States Fidelity and Guaranty Company Aetna Casualty and Surety Company Fireman's Fund Insurance Company A.O. Smith-Inland, Inc. And Armco, Inc., Counterclaim Charles T. Main, Inc., Counterclaim Third-Party v. The Munters Corporation Julian Tobey & Associates John T. Boyd Company Ingersoll-Rand Company Atlanta Engineering Company Envirex, Inc. Babcock & Wilcox Company Milton Roy Company and Electric MacHinery Enterprises, Third-Party, 893 F.2d 297, 1990 U.S. App. LEXIS 943 (3d Cir. 1990).

Opinion

893 F.2d 297

ECODYNE COOLING DIVISION OF ECODYNE CORPORATION, a Delaware
corporation, Plaintiff-Counterclaim Defendant-Appellee,
v.
CITY OF LAKELAND, Defendant-Counterclaim Plaintiff-Appellant,
v.
ECODYNE COOLING DIVISION; Fairfield Engineering; Federal
Insurance Company; St. Paul Fire and Marine Insurance
Company; Charles T. Main, Inc.; Blount International Ltd.;
United States Fidelity and Guaranty Company; Aetna
Casualty and Surety Company; Fireman's Fund Insurance
Company; A.O. Smith-Inland, Inc.; and Armco, Inc.,
Counterclaim Defendants-Appellees.
CHARLES T. MAIN, INC., Counterclaim Defendant, Third-Party
Plaintiff-Appellee,
v.
The MUNTERS CORPORATION; Julian Tobey & Associates; John
T. Boyd Company; Ingersoll-Rand Company; Atlanta
Engineering Company; Envirex, Inc.; Babcock & Wilcox
Company; Milton Roy Company; and Electric Machinery
Enterprises, Third-Party Defendants.

No. 88-3761.

United States Court of Appeals,
Eleventh Circuit.

Jan. 29, 1990.

Michael B. Colgan, Holland & Knight, Steven L. Brannock, Tampa, Fla., and Mark N. Miller, City Atty., Lakeland, Fla., for appellant.

Denise G. Morris, Fisher, Rushmer, Werrenrath, Keiner, Wack & Dickson, Orlando, Fla., for appellees.

William W. Shields, III, Lawson, McWhirter, Grandoff & Reeves, C. Thomas Davidson, J. Bert Grandoff, and John R. Lawson, Jr., Tampa, Fla., for Blount, Inc.

Jeffrey D. Keiner, Fisher, Rushmer, Werrenrath, Keiner, Wack & Dickson, Orlando, Fla., for Charles T. Main, Inc.

Douglas S. Gregory, Bush, Ross, Gardner, Warren & Rudy, P.A., Tampa, Fla., for Munters Corp.

James J. Evangelista, Fowler, White, Gillen, Boggs, Villareal & Banker, Tampa, Fla., for A.O. Smith-Inland.

Appeal from the United States District Court for the Middle District of Florida.

Before TJOFLAT, Chief Judge, and HATCHETT, Circuit Judge, and HILL, Senior Circuit Judge.

PER CURIAM:

CERTIFICATION FROM THE UNITED STATES COURT OF APPEALS FOR THE ELEVENTH CIRCUIT TO THE SUPREME COURT OF FLORIDA PURSUANT TO ARTICLE 5, SECTION 3(b)(6) OF THE FLORIDA CONSTITUTION

TO THE SUPREME COURT OF FLORIDA AND ITS HONORABLE JUSTICES:

This case, a contract action for consequential damages, arises from a dispute over the design and construction of a coal-fired power plant, known as McIntosh III, for appellant, the City of Lakeland, Florida (Lakeland). We have concluded that a question of law--namely, the proper interpretation of a Florida statute and of Florida public policy--is dispositive of the cause. Because the question is unanswered by controlling precedent of the Supreme Court of Florida, we certify the question for resolution by that court.

Under the Florida Electrical Power Plant Siting Act (Act), Fla.Stat. Secs. 403.501-.517 (1987), a power plant cannot be built unless a site certification is obtained from the Power Plant Siting Board (Board).1 Id. Secs. 403.506, .511. Such certification constitutes the sole license for a power plant's construction and operation. Id. Sec. 403.511. The Act charges the Department of Environmental Regulation (DER) with monitoring a power plant's continued compliance with the conditions of the site certification. Id. Sec. 403.504.

Lakeland's certification to build and operate McIntosh III specified that treated sewage effluent would be used for cooling; the certification permitted the pumping of ground water in limited amounts for emergency back-up cooling.2 When the effluent system developed serious problems,3 Lakeland began pumping ground water far in excess of the limitations imposed by the certification. The DER was aware of the excessive use of ground water and did nothing to stop it.

Meanwhile, there were other difficulties at McIntosh III, unrelated to the cooling system problems, that led to the current litigation. Alleging design and construction defects, Lakeland sued several parties, including the appellees: Chas. T. Main (Main), the engineer; Blount International, Ltd. (Blount), the general contractor; and A.O. Smith (Smith), the vendor of an above-ground fiberglass piping system. Because of these defects, according to Lakeland, the plant did not become commercially operable until eleven months after the projected date, and, thereafter, the plant was sporadically forced to shut down or to operate at less than full capacity. Lakeland sought consequential damages arising from both the eleven-month delay and the subsequent period of sporadic operation. Lakeland calculated its damages based on the difference in cost between coal-fired and oil-fired generation4 and on lost profits under a contract with Florida Power Corporation for the sale of excess power.

Appellees Blount and Main, later joined by Smith, moved for partial summary judgment. According to the appellees, the certification conditions, imposed to regulate environmental impacts, carry the force and effect of law, and the Board had the exclusive authority to modify them. In appellees' view, the DER had no discretion to permit any deviation, even temporary, from the certification conditions. Appellees raised an "illegality defense," arguing that Lakeland could not recover for its inability to operate at full load when such operation was or would have been in violation of Lakeland's certification and hence illegal, that is, when Lakeland was or would have been pumping unauthorized quantities of ground water. On appellees' theory, allowing Lakeland to recover consequential damages for operations violative of the certification conditions would reward Lakeland for ignoring the requirements of Florida law, in contravention of the law of damages and of Florida environmental protection policy as expressed in the Siting Act.

Lakeland conceded that it had pumped more ground water than its certification permitted. In responding to the illegality defense, however, it contended that operation of the plant during the period of excessive ground water use, although a violation of a condition of certification, was neither illegal nor in contravention of Florida public policy. Lakeland argued that the DER has discretion under the Act to permit temporary violations of a certification while a power plant is being brought "on line"--a difficult and complicated undertaking that would be virtually impossible without some temporary violations. Lakeland noted that DER officials expressed no objection to Lakeland's operation of the plant despite their knowledge of Lakeland's noncompliance with the certificate.

The Federal District Court for the Middle District of Florida granted appellees' motion for partial summary judgment based on the illegality defense, stating that the court was

duty-bound to enforce the clear language of Sec. 403.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
893 F.2d 297, 1990 U.S. App. LEXIS 943, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ecodyne-cooling-division-of-ecodyne-corporation-a-delaware-corporation-ca3-1990.