Eco Built, Inc. and Ed Travis v. Mark Lulfs D/B/A Paperhanger Plus Landmark Organization, L.P. And California Wholesale Material Supply, Inc. D/B/A Calply

CourtCourt of Appeals of Texas
DecidedAugust 13, 2010
Docket03-08-00427-CV
StatusPublished

This text of Eco Built, Inc. and Ed Travis v. Mark Lulfs D/B/A Paperhanger Plus Landmark Organization, L.P. And California Wholesale Material Supply, Inc. D/B/A Calply (Eco Built, Inc. and Ed Travis v. Mark Lulfs D/B/A Paperhanger Plus Landmark Organization, L.P. And California Wholesale Material Supply, Inc. D/B/A Calply) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eco Built, Inc. and Ed Travis v. Mark Lulfs D/B/A Paperhanger Plus Landmark Organization, L.P. And California Wholesale Material Supply, Inc. D/B/A Calply, (Tex. Ct. App. 2010).

Opinion

TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN

NO. 03-08-00427-CV

Eco Built, Inc. and Ed Travis, Appellants

v.

Mark Lulfs d/b/a Paperhanger Plus; Landmark Organization, L.P.; and California Wholesale Material Supply, Inc. d/b/a Calply, Appellees

FROM THE DISTRICT COURT OF TRAVIS COUNTY, 126TH JUDICIAL DISTRICT NO. D-1-GN-03-001970, HONORABLE LORA J. LIVINGSTON, JUDGE PRESIDING

MEMORANDUM OPINION

Eco Built, Inc. appeals a district court judgment awarding damages to appellee

Landmark Organization, L.P. for breach of a construction subcontract. In three issues, Eco Built

asserts that (1) the district court erred in disregarding jury findings that Landmark had breached

the contract and had thereby damaged Eco Built, (2) the evidence conclusively or by its great weight

and preponderance supported a larger amount of contract damages than the jury awarded to

Eco Built; and (3) no evidence supports the jury’s finding as to the amount of Landmark’s contract

damages or, in the alternative, the evidence conclusively establishes that Landmark waived breach

by Eco Built. Additionally, in a fourth issue, Eco Built and Yancey Ed Travis appeal a portion of

the judgment awarding Landmark damages from them, jointly and severally, based on a directed

verdict on claims that had been assigned to Landmark by one of Eco Built’s suppliers. We will

modify and affirm the judgment in part and reverse and remand it in part. BACKGROUND

This appeal stems from disputes among contractors and suppliers who were involved

in the construction of the Hilton Austin building, the “convention center hotel” that is located next

to the Austin Convention Center. The project owner, Austin Convention Enterprises (ACE), an

entity formed by the City of Austin, contracted with appellee Landmark to oversee and manage

construction on ACE’s behalf. Landmark’s duties included hiring and supervising all subcontractors,

architects, and engineers. Landmark executed a subcontract with Eco Built on September 27, 2002

(made effective retroactively on August 12, 2002) whereby Eco Built was to provide all labor

and material necessary to fabricate and install the building’s exterior wall system. In response to the

City of Austin’s expressed desire to feature “eco-friendly” materials in the building, the project’s

plans and specifications called for an exterior wall system that incorporated aerated autoclave

concrete (AAC), a material that weighs significantly less than ordinary concrete. The building’s

outside wall or “skin” was to consist of several hundred large panels comprised of AAC attached to

a steel frame and finished with a stucco-like appearance. Prior to the Hilton Austin project, AAC

had never been used as panels on a high-rise building like the hotel.

Simply described, Eco Built’s scope of work under the subcontract entailed it

purchasing two-inch thick, several square-foot sized pieces of AAC, steel, and other component

materials and fabricating panels by building a steel frame, attaching two layers of the AAC piece

to the frame with screws, and applying two coats of a finishing treatment. Eco Built was then

responsible for having the prefabricated panels transported to the project site and installed on

the building with a crane. Eco Built was also responsible for supplying the AAC component to

2 another contractor who would install it into steel frames constructed on the building itself to

create “field applied” panels, and for applying the finish to the field-applied panels. Eco Built

subcontracted with appellee Mark Lulfs d/b/a Paperhanger Plus to assist it with fabricating, finishing,

transporting and installing the prefabricated panels from materials Eco Built supplied and also in

finishing field-applied panels.

In consideration for the full performance of the work specified under Eco Built’s

subcontract with Landmark, Landmark agreed to pay Eco Built a total sum of $3,975,000. However,

it was explicitly “provided that no payments are to be made unless [Eco Built’s] rate of progress,

work done, and materials furnished are satisfactory to [Landmark] and has herein agreed upon.”

The subcontract provided for monthly progress payments to Eco Built—essentially

draws against the total contract amount—“covering the value of work completed to the satisfaction

of [ACE] during that month.” Eco Built was required to submit applications for such payments

on which it would list materials it had purchased and work that had been performed during that

period. The work and materials were required to be categorized among several line-items in a

“schedule of values.” To each line item was assigned a percentage of the total contract value, and

payment requests were to be charged against these values. The subcontract contemplated that

Landmark would incorporate information from Eco Built’s application into its own requests for

payment from ACE. ACE would then inspect the work and materials to verify the information

provided in the payment requests, and either pay the request or withhold payment pending cure of

any deficiencies. Assuming Landmark was paid for the materials or work, it would pay Eco Built,

and Eco Built would in turn pay its suppliers and subcontractors. The subcontract contained a pay-

3 when-paid clause—“PAYMENT TO [ECO BUILT] SHALL BE CONDITIONED ON PAYMENT

TO [LANDMARK] BY [ACE].”

Also of note, the subcontract required Eco Built to furnish Landmark a treasury-rated

payment and performance bond covering one-hundred percent of Eco Built’s contractual scope

of work. The bond was included in the total contract amount. Finally, the subcontract authorized

Landmark to terminate the contract at any time without cause upon written notice to Eco Built.

Essentially three sets of key disputes arose concerning Eco Built’s work on the

project. The first related to difficulty Eco Built encountered in obtaining the required bond. Despite

repeated assurances to Landmark that it would imminently obtain and furnish the bond, weeks

and then months elapsed without Eco Built satisfying the requirement. The second set of disputes

concerned the quality of Eco Built’s work. Although Landmark had paid an initial progress payment

application for Eco Built’s set-up costs (e.g., expenses for fabrication equipment, tools, and its

facility), complaints about cracked or misaligned panels prompted ACE to withhold payment to

Landmark for work and materials related to the panels, and Landmark in turn withheld payment from

Eco Built. The third set of disputes, related to the second, concerned Eco Built’s failure to pay its

suppliers and subcontractors and the prospect that Landmark could ultimately be required to satisfy

those obligations. These outstanding obligations included payments due to Paperhanger Plus and

to California Wholesale Materials Supply, Inc. d/b/a Calply, which had supplied steel to Eco Built.

On November 15, 2002, Landmark served notice to Eco Built that it was in default

under several provisions of the subcontract and demanded that the defaults be cured within 72 hours.

The claimed defaults included Eco Built’s failure to provide a payment and performance bond;

4 to promptly amend and make good any defective materials and/or workmanship to the approval of

Landmark, ACE, and the project’s architect; to pay its subcontractors and vendors; to provide a

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
Horrocks v. Texas Department of Transportation
852 S.W.2d 498 (Texas Supreme Court, 1993)
Szczepanik v. First Southern Trust Co.
883 S.W.2d 648 (Texas Supreme Court, 1994)
Dallas Railway & Terminal Company v. Gossett
294 S.W.2d 377 (Texas Supreme Court, 1956)
Ramos v. Frito-Lay, Inc.
784 S.W.2d 667 (Texas Supreme Court, 1990)
Billy Smith Enterprises, Inc. v. Hutchison Construction, Inc.
261 S.W.3d 370 (Court of Appeals of Texas, 2008)
Lairsen v. Slutzky
80 S.W.3d 121 (Court of Appeals of Texas, 2002)
White v. Southwestern Bell Tel. Co., Inc.
651 S.W.2d 260 (Texas Supreme Court, 1983)
Gupta v. Eastern Idaho Tumor Institute, Inc.
140 S.W.3d 747 (Court of Appeals of Texas, 2004)
Hernandez v. Gulf Group Lloyds
875 S.W.2d 691 (Texas Supreme Court, 1994)
T.O. Stanley Boot Co. v. Bank of El Paso
847 S.W.2d 218 (Texas Supreme Court, 1993)
Southeastern Pipe Line Co., Inc. v. Tichacek
997 S.W.2d 166 (Texas Supreme Court, 1999)
Spencer v. Eagle Star Insurance Co. of America
876 S.W.2d 154 (Texas Supreme Court, 1994)
Hanks v. GAB Business Services, Inc.
644 S.W.2d 707 (Texas Supreme Court, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
Eco Built, Inc. and Ed Travis v. Mark Lulfs D/B/A Paperhanger Plus Landmark Organization, L.P. And California Wholesale Material Supply, Inc. D/B/A Calply, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eco-built-inc-and-ed-travis-v-mark-lulfs-dba-paperhanger-plus-landmark-texapp-2010.