Ecco-Phoenix Electric Corp. v. Howard J. White, Inc.

461 P.2d 33, 1 Cal. 3d 266, 81 Cal. Rptr. 849, 1969 Cal. LEXIS 207
CourtCalifornia Supreme Court
DecidedNovember 20, 1969
DocketDocket Nos. S.F. 22663, 22664
StatusPublished
Cited by42 cases

This text of 461 P.2d 33 (Ecco-Phoenix Electric Corp. v. Howard J. White, Inc.) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ecco-Phoenix Electric Corp. v. Howard J. White, Inc., 461 P.2d 33, 1 Cal. 3d 266, 81 Cal. Rptr. 849, 1969 Cal. LEXIS 207 (Cal. 1969).

Opinion

Opinion

MOSK, J.

Plaintiff, Ecco-Phoenix Electric Corporation, an electrical contractor, entered into a written subcontract agreement with defendant Howard J.' White, Inc., a general contractor, under which plaintiff agreed to install the electrical system in a building to be constructed by White on the Stanford University campus.

Following completion of the work, plaintiff demanded of defendant additional payment for “extras,” work assertedly performed outside the scope of the contract. Defendant denied liability for such payments, and there ensued this litigation, in which plaintiff sought an award of $14,-684.23, plus interest. Defendant conceded liability for only $3,084.76, and the jury found plaintiff was entitled to $11,464.97.

Under a clause of the subcontract providing that “Should litigation be necessary to enforce any term of provision of this agreement, then all litigation and. court costs and reasonable attorney’s fees shall be borne wholly by the Sub-Contractor,” the trial court awarded costs and attorney’s fees to defendant. Including costs and fees on appeal, which the trial court added in a later order, plaintiff was required to pay to defendant a total of $6,091.10, more than half of plaintiff’s award on the merits of its claim.

In S.F. 22663 defendant appeals from the judgment on the merits and plaintiff appeals from the award of costs and attorney’s fees at trial. In S.F. 22664 plaintiff appeals in a separate action from the award of costs and fees on appeal. We shall treat these as a single action for purposes of this opinion, and we conclude that the judgment for plaintiff on the merits must be affirmed, but the awards of costs and attorney’s fees to defendant must, at least in part, be reversed.

Defendant’s Appeal on the Merits

Defendant. cites as prejudicial misconduct requiring reversal a statement by plaintiff’s counsel during argument referring to a favorable verdict he had received in a previous case in the same court. Assuming that this isolated aside was misconduct, although it was neither emphasized nor *271 repeated and was terminated by defendant’s timely objection, it could not have been prejudicial. In addition to the seemingly innocuous nature of the remark, any possible prejudice was surely removed by the trial court’s immediate and proper admonition to the jury that they must “disregard any reference to any other case.” (See Sabella v. Southern Pac. Co. (1969) 70 Cal.2d 311, 318 [74 Cal.Rptr. 534, 449 P.2d 750], and cases cited therein.)

One Davey, an electrical contractor called as an expert witness by plaintiff, was asked several hypothetical questions framed in terms of “who should pay”—the general contractor or the subcontractor—for certain types of work. The trial court properly sustained defendant’s objections to this approach and limited the questions to the existence of a “custom and usage” in the electrical contracting business. Defendant asserts that custom or usage is inadmissible to vary the terms of a written contract (see C. J. Wood, Inc. v. Sequoia Union High School Dist. (1962) 199 Cal.App. 2d 433, 436 [18 Cal.Rptr. 647]); but it refers us to no specific provisions in the voluminous general contract—incorporated by reference in the subcontract—which are purportedly varied by the testimony of the witness. If there was a custom or usage which was admissible in evidence, Davey, as an unchallenged expert witness, could properly testify to its existence, even if his testimony thereby “embrace[d] the ultimate issue to be decided by the trier of fact.” (Evid. Code, § 805.)

Finally, defendant complains that the trial court erroneously instructed the jury that “Any loss arising from errors and ambiguity in the plans and specifications occasioned by the acts of the owner’s architect shall fall upon the general contractor and not upon the subcontractor, as between the general contractor and the subcontractor.” This is said to be too broad a generalization, as the general contractor would not be liable if, for example, the extra work was due to the subcontractor’s negligence in assessing the plans, and in any event it would not be liable unless it had “ordered, directed, or authorized” the subcontractor to do the extra work.

Although the instruction complained of, if isolated, might be erroneous, a reading of the entire charge to the jury reveals that this broad statement was qualified substantially. The jury was instructed, inter alia, that the subcontractor could not recover for work included under the contract; that it could not recover for extras occasioned by incomplete or confusing plans if reasonable care would have put it on notice of the error or confusion; and that recovery could be had only for extra work ordered by the general contractor in writing, unless this requirement had been waived. Viewing the questioned instruction in context, we perceive no error.

*272 Costs and Attorney’s Fees

We turn now to plaintiffs contention that the trial court erred in awarding costs and attorney’s fees to defendant, based on its interpretation of the subcontract. As indicated above, the pertinent clause of the contract provides that “Should litigation be necessary to enforce any term or provision of this agreement, then all litigation and court costs and reasonable attorney’s fees shall be borne wholly by the Sub-Contractor.” (Italics added.) This clause, and in particular the italicized portion, indicates that plaintiff is to bear all costs and reasonable attorney’s fees only in litigation necessary to enforce the contract.

We find the clause less than certain on its face, leaving unanswered such questions as “litigation” by whom, and made “necessary” by whom. As no extrinsic evidence was taken to aid the trial court’s interpretation of this clause, we are free to adopt our construction as a matter of law. (Parsons v. Bristol Development Co. (1965) 62 Cal.2d 861 [44 Cal.Rptr. 767, 402 P.2d 839].) As this printed form contract was prepared by defendant, and in light of the oppressive nature of a literal interpretation of the clause, we resolve any uncertainties in favor of a fair and reasonable interpretation and against the inflexible construction adopted by the trial court. (See Taylor v. J. B. Hill Co. (1948) 31 Cal.2d 373, 374 [189 P.2d 258]; cf. 3 Corbin on Contracts (1960) § 552, pp. 210-211.)

If the clause is read literally, plaintiff is to pay the costs and fees incurred whenever any litigation is necessary, regardless of who brings the action and who is responsible for making it necessary. This interpretation is patently inequitable and would be contrary to public policy as encouraging—and in fact indemnifying—vexatious or frivolous litigation, were it not for several qualifications which must be read into the text.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Amorastreya v. Torres CA1/2
California Court of Appeal, 2023
Hansen v. The Coca-Cola Co. CA4/1
California Court of Appeal, 2021
M'Guinness v. Johnson
243 Cal. App. 4th 602 (California Court of Appeal, 2015)
In re S.N. CA4/2
California Court of Appeal, 2014
Prahm v. Pickford Real Estate CA4/1
California Court of Appeal, 2014
Weinbach v. Windwings Productions CA2/3
California Court of Appeal, 2013
Howard Entertainment, Inc. v. Kudrow
208 Cal. App. 4th 1102 (California Court of Appeal, 2012)
Bohm v. Horsley Co. (In Re Groggel)
333 B.R. 261 (W.D. Pennsylvania, 2005)
First Nationwide Bank v. Mountain Cascade, Inc.
77 Cal. App. 4th 871 (California Court of Appeal, 2000)
Santisas v. Goodin
951 P.2d 399 (California Court of Appeal, 1998)
Sweat v. Hollister
37 Cal. App. 4th 603 (California Court of Appeal, 1995)
Chia-Lee Hsu v. Abbara
891 P.2d 804 (California Supreme Court, 1995)
Bussey v. Affleck
225 Cal. App. 3d 1162 (California Court of Appeal, 1990)
Paez v. Alcoholic Beverage Control Appeals Board
222 Cal. App. 3d 1025 (California Court of Appeal, 1990)
Kudon v. f.m.e. Corp.
547 A.2d 976 (District of Columbia Court of Appeals, 1988)
In Re Marriage of Segel
177 Cal. App. 3d 1030 (California Court of Appeal, 1986)
Sege v. Segel
177 Cal. App. 3d 1030 (California Court of Appeal, 1986)
Lanyi v. Goldblum
177 Cal. App. 3d 181 (California Court of Appeal, 1986)
Heston v. Farmers Insurance Group
160 Cal. App. 3d 402 (California Court of Appeal, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
461 P.2d 33, 1 Cal. 3d 266, 81 Cal. Rptr. 849, 1969 Cal. LEXIS 207, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ecco-phoenix-electric-corp-v-howard-j-white-inc-cal-1969.