E.C. Ernst, Inc. v. Grumman Ecosystems Corp. (In Re E.C. Ernst, Inc.)

26 B.R. 576, 1983 Bankr. LEXIS 6975
CourtUnited States Bankruptcy Court, S.D. New York
DecidedJanuary 24, 1983
Docket18-37054
StatusPublished
Cited by4 cases

This text of 26 B.R. 576 (E.C. Ernst, Inc. v. Grumman Ecosystems Corp. (In Re E.C. Ernst, Inc.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
E.C. Ernst, Inc. v. Grumman Ecosystems Corp. (In Re E.C. Ernst, Inc.), 26 B.R. 576, 1983 Bankr. LEXIS 6975 (N.Y. 1983).

Opinion

DECISION AND ORDER ON MOTION TO IMPOSE DISCOVERY SANCTIONS

EDWARD J. RYAN, Bankruptcy Judge.

On December 1, 1978 E.C. Ernst, Inc. (“Ernst”) filed a Chapter XI petition in this court pursuant to the Bankruptcy Act of 1898. Ernst was thereafter continued in business.

On September 15, 1982, Ernst instituted the instant adversary proceeding against Grumman Ecosystems Corporation (“Grumman”) alleging the willful failure to comply with discovery requirements. The relief requested was the expungement of Grumman’s claim in the Ernst reorganization pursuant to Rule 37 of the Federal Rules of Civil Procedure (“FRCP”) made applicable to adversary proceedings in the bankruptcy court by Bankruptcy Rule 737.

The facts of the dispute are as follows: On or about December 1, 1977 Grumman and Ernst entered into a contract (“the Subcontract”) whereby Ernst agreed to perform the electrical construction work on the Hampton Roads, Virginia, Army Base Wastewater Treatment Plant, Phase II Improvements (“the Project”). Grumman was the general contractor on the Project.

In November, 1979 Grumman contracted with Perini Corporation (“Perini”) for Peri-ni to serve as Grumman’s construction manager for the Project. In December, 1979 Grumman terminated Ernst from the Project and engaged Manzi Electrical Company (“Manzi”) to complete the work left unperformed by Ernst.

On April 24, 1981 Grumman filed a proof of an administrative claim against Ernst in *577 its reorganization proceeding for $693,-720.41. That claim represented the damages suffered by Grumman as a result of Ernst’s alleged breach of the Subcontract.

On July 10, 1981 Ernst instituted an adversary proceeding in this court alleging that it was Grumman who had breached the Subcontract. Ernst requested this court to (a) expunge Grumman’s administrative claim, or in the alternative, permit rejection of the Subcontract and adjudicate that any claim proved by Grumman be allowed only as a general unsecured claim; and (b) enter a judgment against Grumman for $158,368 which represents unpaid sums due Ernst upon the Subcontract. On July 24, 1981 Grumman answered seeking dismissal of the complaint and counterclaiming for its administrative expense claim.

Discovery began shortly thereafter. In September, 1981 each party served the other with extensive document requests. Grumman delivered to Ernst voluminous documents pursuant to such request including copies of the invoices assembled by Manzi and Perini representing costs incurred by Grumman in securing completion of the unperformed portion of the Subcontract.

Ernst has also taken numerous depositions. Ernst has examined the following employees of Grumman: George Brown (on March 23, 1982); Dean Cassell (on March 24, 1982), Alex Wasyl (on June 23, 1982); and Jay Witte (on March 31, 1982, September 23, 1982 and October 18, 1982). Ernst has also deposed Warren Found of Manzi (on September 29, 1982) and Eugene Dragon of Perini (on March 31, 1982).

On June 20, 1982 Ernst served Grumman with written interrogatories seeking, inter alia, the component parts of Grumman’s claim in the Ernst reorganization proceeding; identification of the documents supporting the claim; identification of the persons who calculated the claim; when and where such claim was calculated; and information relating to the completion of the Project. During the third week of July, counsel to Grumman requested and received from counsel to Ernst an extension until August 20, 1982 of the time by which Grumman would be required to respond to the Ernst interrogatories. However, on that date the interrogatories were not delivered due to “mechanical difficulties and missed deliveries.”

On September 14, 1982 Ernst instituted the instant proceeding requesting discovery sanctions be imposed against Grumman for willful failure to comply with discovery. Although responses to the interrogatories were served on September 17, 1982 and Supplemental Responses served on October 18,1982 Ernst continues to seek the imposition of sanctions against Grumman. Ernst maintains that the responses to the interrogatories and the deposition testimony are so unresponsive, vague and incomplete that the Grumman claim remains totally unexplained.

The sanctions requested are: the dismissal of Grumman’s claim, the striking of Grumman’s answer to Ernst’s complaint and direction of judgment in favor of Ernst for $158,362.

Whether a court has the power to dismiss a claim for a failure of discovery depends exclusively upon FRCP 37 and not upon any inherent equity powers of a Federal court. Societe Internationale pour Participations Industrielles et Commerciales, SA v. Rogers, 357 U.S. 197, 207, 78 S.Ct. 1087, 1093, 2 L.Ed.2d 1255 (1958).

Dismissal for a failure to cooperate in pretrial discovery, pursuant to FRCP 37 is a draconian sanction which should be used only in extreme circumstances. See Israel Aircraft Ltd. v. Standard Precision, 559 F.2d 203, 208 (2d Cir.1977). Courts must exercise restraint because such a dismissal may operate to deprive a person of property without due process of law in contravention of the Fifth Amendment. See Societe Internationale, supra 357 U.S. at 209, 78 S.Ct. at 1094; Notes of Advisory Committee on Rules, Rule 37, 28 U.S.C.A. (1975 Supp.) page 53. Therefore, there is a strong policy favoring a trial on the merits and against depriving a party of his day in court because of misconduct during dis *578 covery. See Fox v. Studebaker-Worthington, Inc., 516 F.2d 989, 996 (8th Cir.1975); Pioche Mines Consolidated, Inc. v. Dolman, 333 F.2d 257, 270 (9th Cir.1964) cert. denied 380 U.S. 956, 85 S.Ct. 1082, 13 L.Ed.2d 972 (1965); Gill v. Stolow, 240 F.2d 669, 670 (2d Cir.1957).

FRCP 37(b)(2) and (d) authorizes a court to impose discovery sanctions. Rule 37(b)(2) is inapplicable in the instant case as dismissal pursuant to this subsection must be preceded by an order compelling discovery. Kropp v. Ziebarth, 557 F.2d 142, 146 n. 7 (8th Cir.1977); Israel Aircraft Ind., Ltd. v. Standard Precision, 559 F.2d 203, 208 (2d Cir.1977). No such order has been issued here.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
26 B.R. 576, 1983 Bankr. LEXIS 6975, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ec-ernst-inc-v-grumman-ecosystems-corp-in-re-ec-ernst-inc-nysb-1983.