Eaton v. Ann-L Corp., 06 Co 53 (6-1-2007)

2007 Ohio 2759
CourtOhio Court of Appeals
DecidedJune 1, 2007
DocketNo. 06 CO 53.
StatusPublished
Cited by2 cases

This text of 2007 Ohio 2759 (Eaton v. Ann-L Corp., 06 Co 53 (6-1-2007)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eaton v. Ann-L Corp., 06 Co 53 (6-1-2007), 2007 Ohio 2759 (Ohio Ct. App. 2007).

Opinion

OPINION
{¶ 1} This timely appeal comes for consideration upon the record in the trial court, Appellant's brief, and its oral argument to this court. Appellant, Ann-L Corporation, appeals the decision of the Columbiana County Municipal Court granting judgment in favor of Appellee, Eaton, in the amount of $850. Because the trial court's decision was based upon competent, credible evidence, the decision of the trial court is affirmed.

{¶ 2} According to the findings of fact made by the trial court, Eaton purchased a manufactured home that required a foundation and finished brickwork. Ann-L presented a quote to Eaton that she accepted on July 28, 2005. The total cost was $7,800.00. The work was to be performed in two phases. Phase I, to be completed before the home was delivered to the site, consisted of bringing the sewer and water line to grade, supplying and installing limestone, and pouring a concrete slab on grade. Phase II, to be completed after the home was delivered, consisting of laying a 4" skirt wall out of brick. Eaton was required to pay $4,000 upon signing of the agreement, $1,000 upon completion of the slab, and $2,880 upon completion of the work. However, Eaton elected to pay $6,000 upon the signing of the agreement with the balance of $1,880 to be paid upon the completion of work.

{¶ 3} Although the written agreement did not require that Ann-L clean up the site prior to beginning the project, there was debris on the site from a former mobile home that needed to be removed. When Eaton discovered that her family member was not available to clean up the debris, she called Ann-L and requested that they clean up the site. The value of this additional work was $150.

{¶ 4} After Ann-L completed Phase I and the manufactured home was on the site, Eaton requested that Ann-L perform Phase II of the written agreement. Ann-L refused to perform Phase II claiming that Eaton had failed to pay the $150 for the additional site cleanup. Ann-L then demanded payment of the $150 and the written contract balance of $1,880 before Phase II would be completed. Eaton, having already paid more than what was required by the written contract, refused to pay anything further until Ann-L performed under the written contract.

{¶ 5} When Ann-L did not perform Phase II of the agreement, Eaton retained *Page 2 Better Basements to complete the work. Better Basements used the same grade brick as specified by Ann-L. However, in addition to laying a 4" skirt wall out of brick, Better Basements also installed vents and a service door that had not been included in the contract to be performed by Ann-L. Better Basements completed the work in January of 2006 at a total cost to Eaton of $3,350.

{¶ 6} Eaton then filed suit attempting to recover damages resulting from Ann-L's alleged breach of the written contract. A bench trial was conducted in small claims court. At the conclusion of the trial, the trial court concluded that Eaton was entitled to damages against Ann-L in the amount of $1000, which represents the deposit paid by Plaintiff to Defendant for performance of Phase II of the contract. The trial court also found that, pursuant to the doctrine of quantum meruit, Ann-L should be reasonably compensated for the removal of debris in the amount of $150 for a total judgment for Plaintiff in the amount of $850.00.

{¶ 7} As their first assignment of error, Ann-L. claims:

{¶ 8} "The Trial Court erred as a matter of law when it found that Defendant/Appellant Ann-L breached the contract with Plaintiff/Appellee Eaton."

{¶ 9} The standard of review governing this appeal is whether the decision of the trial court is contrary to law. We will not disturb the trial court's judgment if it is "supported by some competent, credible evidence going to all the essential elements of the case." CE. MorrisCo. v. Foley Construction Co. (1978), 54 Ohio St.2d 279, syllabus. " `If the evidence is susceptible of more than one construction, the reviewing court is bound to give it that interpretation which is consistent with the verdict and judgment.' " Estate of Barbieri v. Evans (1998),127 Ohio App.3d 207, 211.

{¶ 10} Here, Ann-L claims that the trial court erred in finding that Ann-L breached the contract, because, in actuality, they claim it was Eaton who breached the contract by failing to pay the $150. Ann-L bases this claim on the alleged "verbal addendum" to the contract. More specifically, Ann-L claims that the negotiations over who was going to remove the debris from the site resulted in a verbal addition to the terms of the contract.

{¶ 11} A contract is created "where there is an offer by one side, acceptance on *Page 3 the part of the other, and a meeting of the minds as to the essential terms of the agreement." McCarthy, Lebit, Crystal Haiman Co., L.P.A.v. First Union Mgt., Inc. (1993), 87 Ohio App.3d 613, 620,622 N.E.2d 1093. Later acts and agreements may modify the terms of a contract; unless otherwise specified, neither consideration nor a writing is necessary. Smaldino v. Larsick (1993), 90 Ohio App.3d 691, 698,630 N.E.2d 408; Software Clearing House, Inc. v. Intrak, Inc. (1990),66 Ohio App.3d 163, 172, 583 N.E.2d 1056. Where one party assents to any modification or change in the terms of the contract, the assent, either express or implied, if acted on by the other party, would be binding upon the first party. See O.F. Mehurin Son v. Stone (1881),37 Ohio St. 49, 57-58.

{¶ 12} Here, there never was a meeting of the minds between Eaton and Ann-L regarding the removal of the debris. From a review of Eaton's testimony, it appears that she believed that she would be charged $150 for the debris to be completely removed from the site. She testified that Ann-L merely pushed back the debris away from the site and that the debris still needed to be removed afterwards by her son-in law. A stipulation was then entered that she refused to agree to a verbal addendum or change in the contract. However, she further agreed that she accepted the work.

{¶ 13} Given these facts the trial court applied the doctrine of quantum meruit and awarded Ann-L $150 for services performed. Quantum meruit is generally awarded when one party confers some benefit upon another without receiving just compensation for the reasonable value of services rendered. Fox Assoc. Co., L.P.A. v. Purdon (1989),44 Ohio St.3d 69; Rice v. Wheeling Dollar Sav. Trust Co. (1951),155 Ohio St. 391.

{¶ 14}

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2007 Ohio 2759, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eaton-v-ann-l-corp-06-co-53-6-1-2007-ohioctapp-2007.