Eaton, Brown & Simpson, Inc. v. United States

62 Ct. Cl. 668, 1926 U.S. Ct. Cl. LEXIS 303, 1926 WL 2604
CourtUnited States Court of Claims
DecidedDecember 13, 1926
DocketNo. C-744
StatusPublished
Cited by5 cases

This text of 62 Ct. Cl. 668 (Eaton, Brown & Simpson, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eaton, Brown & Simpson, Inc. v. United States, 62 Ct. Cl. 668, 1926 U.S. Ct. Cl. LEXIS 303, 1926 WL 2604 (cc 1926).

Opinion

Geaham, Judge,

delivered the opinion of the court:

On the 30th of April, 1918, the plaintiff executed a contract with the defendant for grading a certain piece of ground, erecting buildings thereon, and constructing roads for an extension to the Naval Training Camp at Cape May, N. J. The specifications upon which plaintiff made its bid contained a contour map of the ground and most of the items and conditions of the contract, particularly the provisions with reference to changes in specifications and extras.

This suit grows out of claims by plaintiff for expenditures occasioned by changes in the specifications, extras, and damages for delays in the delivery of lumber and the conduct of the inspector. The facts are fully set forth in the findings.

In March, 1918, before executing the contract, plaintiff’s engineer made an inspection of the site, having with him a copy of the contour map. At that time he did not discover any errors therein. On or about April 25 another representative of plaintiff, a consulting engineer, made an inspection of the ground and found that the contour map was grossly in error, as to elevations and in other particulars. On April 30 plaintiff had a correct survey made of the site. The conditions were therefore known to the plaintiff before it executed the contract, and consequently it could not have been misled. There could, therefore, be no question of warranty.

After execution of the contract by agreement between the parties the said survey made by plaintiff’s engineer was accepted in place of the contour map attached to the specifications as representing the true condition of the ground, and the work was proceeded with in accordance with that survey, which required much more time and labor than would have been required under the original contour map attached to [681]*681the specifications. There were changes also made in the construction of the buildings in connection with which the plaintiff did extra work.

Section 11 of the specifications contains the following provision as to changes:

“ The Government reserves the right to make such changes in the contract, plans, and specifications as may be deemed necessary or advisable, and the contractor agrees to proceed with such changes as directed in writing by the Chief of the Bureau of Yards and Docks. The cost of said changes shall be estimated by the officer in charge, and, if less than $500, shall be ascertained by him. If the cost of said changes is $500 or more, as estimated by the officer in charge, the same shall be ascertained by a boai*d of not less than three officers or other representatives of the Government. The cost of the changes as ascertained above, when approved by the Chief of the Bureau of Yards and Docks, shall be added to or deducted from the contract price, and the contractor agrees and consents that the contract price thus increased or decreased shall be accepted in full satisfaction for all work done under the contract: Provided, That the increased cost shall be the estimated actual cost to the contractor at the time of such estimate and that the decreased cost shall be the actual or market value at the time the contract was made, both plus a profit of 10 per cent.”

The following provision as to extras is contained in section 18 of the specifications:

“ The contract price shall cover all expenses, of whatever nature or description, connected with the work to be done under the contract. Should the contractor at any time consider that he is being required to furnish any material or labor not called for by the contract, a written itemized claim for compensation therefor must be submitted by him to the officer in charge, who will refer the same at once with full report and recommendation to the Navy Department, Bureau of Yards and Docks, for decision and formal order covering approved items, if any. The failure or neglect of the contractor to present as above his claim for material or labor alleged to be extra within 60 days after being required to furnish or perform the same shall be deemed and construed as a waiver of all claim and right to additional compensation for the furnishing or performance of the alleged extra material or labor, and the contractor agrees to accept [682]*682the finding and action of the Navy Department, Bureau of Yards and Docks, in the premises as conclusive and binding.”

The contract required the work to be completed in 90 days from April 80, 1918. In April, 1919, the work had not been completed. On March 18, 1919, plaintiff presented to defendant a claim for reimbursement for loss covering twenty-five different items. Some of these losses, as stated, grew out of changes in the specifications, some were caused by extra work, and others were due to delays in delivery of lumber and to the conduct of the inspector. The claim was referred to a board of three representatives of the Government, who made a report thereon, recommending allowances on some of the items and rejecting others. This report was submitted to the Bureau of Yards and Docks, and some time after March 12, 1920, the acting chief of that bureau disapproved certain items and approved others, the total amount of the latter being $7,562.12.

The specifications provided that the additional cost of the changes as ascertained by the board should be added to the contract price “ when approved by the Chief of the Bureau of Yards and Docks.” This makes the approval of the latter official necessary in order to establish the claim; and until this approval had been secured the original price for the performance of the contract could neither be increased nor decreased by reason of the changes made in the specifications. Plaintiff could only, recover, therefore, for such items as were approved by said official, and, as set out in Finding XXY, the total amount of these items, $7,562.12, was paid to plaintiff. .Whether the action of the Acting Chief of the Bureau of Yards and Docks was right is not for us to inquire. The plaintiff in its contract agreed to an adjustment of its claims by the said bureau and is bound by the contract. We have only to construe and enforce it as we find it.

As to the items claimed as “ extras,” the contract provides that the finding and action of the Navy Department, through the Bureau of Yards and Docks, in approving or disapproving the contract “ shall be conclusive and binding.” That bureau approved some of plaintiff’s claims and disapproved [683]*683others, and its action is conclusive and binding upon the court.

The next question is the claim for delay in delivery of the lumber, the rejection of the lumber by the inspector and his conduct otherwise, and delays growing out of interference with the work.

As to the lumber, it does not appear whether the delays were due to the fault of the party who was to supply the lumber, inability to secure shipment, or delay in shipment. It is admitted that there was delay in some instances of as much as six weeks. However, the defendant can not be held liable for these delays. The contract contained the following provision:

“ Fifth. It is understood and declared to be the meaning of the first clause of paragraph 2 of said Addendum No. 1A that the party of the second part will arrange' with the lumber director of the War Industries Board for the party of the first part to purchase the lumber required for the work hereunder, f. o. b. mills, at the prices named in the schedule of lumber prices attached to said Addendum No. 1A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

S&E Contractors, Inc. v. United States
406 U.S. 1 (Supreme Court, 1972)
Hegeman-Harris & Company, Inc. v. The United States
440 F.2d 1009 (Court of Claims, 1971)
Edwards v. United States
80 Ct. Cl. 118 (Court of Claims, 1934)
Levering & Garrigues Co. v. United States
71 Ct. Cl. 739 (Court of Claims, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
62 Ct. Cl. 668, 1926 U.S. Ct. Cl. LEXIS 303, 1926 WL 2604, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eaton-brown-simpson-inc-v-united-states-cc-1926.