Eastern Transfer of New York, Inc. v. Cahill

268 A.D.2d 131, 707 N.Y.S.2d 521, 2000 N.Y. App. Div. LEXIS 4993
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMay 4, 2000
StatusPublished
Cited by1 cases

This text of 268 A.D.2d 131 (Eastern Transfer of New York, Inc. v. Cahill) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eastern Transfer of New York, Inc. v. Cahill, 268 A.D.2d 131, 707 N.Y.S.2d 521, 2000 N.Y. App. Div. LEXIS 4993 (N.Y. Ct. App. 2000).

Opinion

OPINION OF THE COURT

Graffeo, J.

This controversy emanates from the parties’ differing interpretations of an administrative enforcement order issued on consent (hereinafter the consent order) by respondent Department of Environmental Conservation (hereinafter DEC) in June 1990 relating to the operation of a solid waste transfer station in Kings County which is now owned by petitioner. Because we hold that the consent order, which expired on May 7, 1998, neither granted petitioner “vested rights” in the continued operation of the transfer station nor authorized the construction of a new putrescible waste processing facility on the site in the absence of compliance with permit and environmental review requirements, we affirm Supreme Court’s judgment.

The consent order was issued following resolution of two administrative enforcement actions brought against New York Carting Company, Inc. (hereinafter NY Carting), the initial owner of the transfer station. DEC had commenced an enforcement proceeding due, in part, to the operation of the transfer station without a permit in violation of ECL 27-0707 (1) and 6 NYCRR part 360. Under the terms of the consent order, NY Carting received temporary authorization to continue its operations for a period of 120 days and was required to submit a permit application within 90 days. Paragraph IV of the consent order stated, in pertinent part, as follows: “This Order is not a permit. This Order constitutes temporary authorization for [133]*133[NY] Carting to operate its facility to handle putrescible material and construction and demolition (‘C&D’) debris for a period of one hundred and twenty (120) days from the effective date of the Order. This temporary authority to operate shall expire automatically at the end of this 120-day period unless DEC agrees in writing to renew it.” Moreover, the consent order provided that if the transfer station was sold, the purchaser would be obligated to comply with its terms.

A “compliance schedule” incorporated in the consent order established limitations on the nature and amount of waste to be handled by the transfer station and set forth specific criteria for waste processing. The schedule further directed NY Carting to erect a fence 10 feet in height within 30 days to segregate putrescible materials from construction and demolition debris. Otherwise, activities authorized under the consent order were “limited to the receipt, unloading, sorting, materials recovery, compaction, temporary storage, and trans-shipment of putrescible material and C&D debris.”

In September 1990, NY Carting submitted a permit application which sought authority for continued operation of the transfer station and permission for construction of a new putrescible waste processing facility at the site. Shortly thereafter in 1991, ownership of the transfer station passed to Clean Venture. As the new owner, Clean Venture requested to be substituted as operator of the transfer station for purposes of the consent order, agreeing to be bound by its terms. DEC consented to the substitution.

Between 1992 and 1995, Clean Venture prepared a revised permit application while continuing to operate under the terms of the consent order, which was extended upon letter request every 120 days. In September 1995, DEC determined that Clean Venture’s permit application was complete, including its request seeking authority to construct a new 26,000 square-foot putrescible waste processing facility. DEC began its review of the application under applicable permit regulations (see, 6 NYCRR part 360) and the State Environmental Quality Review Act (ECL art 8 [hereinafter SEQRA]; see, 6 NYCRR part 617). After finding that construction of the new 26,000 square-foot facility would be “without significant impact upon natural resources,” DEC forwarded the application to the New York City Department of Sanitation for consideration under the City’s Environmental Quality Review law.

Before these agencies finally acted on the application, petitioner acquired the transfer station from Clean Venture in [134]*134August 1997. As a result of the change in ownership, petitioner asked to be substituted on the consent order and alerted DEC that it intended to formulate a new permit application for authorization to construct a larger facility. DEC substituted petitioner as a party to the consent order and requested information as to when the revised application would be submitted. Petitioner indicated several times during the following months that a new permit application and engineering report would soon be forwarded. Indeed, in a January 30, 1998 letter requesting extension of the consent order, then due to expire on February 7, 1998, petitioner asserted that its “new application and attendant engineering report is forthcoming.” However, it is undisputed that petitioner began construction of a new 37,000 square-foot putrescible waste processing facility (hereinafter the new facility) in January 1998.

Petitioner’s permit application was eventually submitted on February 6, 1998 seeking, inter alla, authority to continue its existing operation and permission to construct the new facility. After preliminary review, DEC issued a notice of incomplete application and requested additional information.

On February 10, 1998, DEC notified petitioner that its authority to operate the transfer station had been extended under the terms of the consent order for an additional 120 days, through May 7, 1998. DEC then inspected petitioner’s site and observed that construction on the new facility was underway. Thereafter, a notice of violation based on petitioner’s construction of the new facility without a permit was issued, followed by a second notice of violation in March 1998 after petitioner failed to cease construction of the new facility.

On the day the consent order was due to expire—May 7, 1998—petitioner requested a further extension. DEC refused the request based on petitioner’s failure to obtain the required permits prior to commencing construction and its continuance of construction activities despite the issuance of the notices of violation.

An administrative enforcement action was commenced by DEC to prohibit petitioner from continuing construction of the new facility. That same day, petitioner initiated this proceeding seeking injunctive relief enjoining DEC from interfering with its right to operate the existing transfer station, to construct the new facility and for a declaration of its right to [135]*135do so under the consent order.1 Petitioner obtained a temporary restraining order which allowed construction to proceed, but the order was vacated on May 29, 1998 after a hearing. In its counterclaim, DEC sought an injunction prohibiting petitioner from operating the existing transfer station and continuing construction on the new facility, and demanded that civil penalties be assessed based on statutory and regulatory violations. DEC’s administrative proceeding was stayed pending resolution of this litigation.

In a well-reasoned decision and order, Supreme Court dismissed the petition/complaint, declaring that petitioner was bound by the terms of the consent order and was not entitled to a declaration that it had continuing authority to operate the transfer station, and granted DEC’s counterclaim for injunctive relief. Furthermore, Supreme Court granted DEC summary judgment on its remaining counterclaims, finding that petitioner violated the permit statutes and regulations, but declined to impose civil penalties.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

B. Manzo & Son, Inc. v. New York State Department of Environmental Conservation
285 A.D.2d 504 (Appellate Division of the Supreme Court of New York, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
268 A.D.2d 131, 707 N.Y.S.2d 521, 2000 N.Y. App. Div. LEXIS 4993, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eastern-transfer-of-new-york-inc-v-cahill-nyappdiv-2000.