Eastern Oil Co. v. Beatty

1918 OK 625, 177 P. 104, 71 Okla. 275, 1918 Okla. LEXIS 942
CourtSupreme Court of Oklahoma
DecidedNovember 12, 1918
Docket5912
StatusPublished
Cited by35 cases

This text of 1918 OK 625 (Eastern Oil Co. v. Beatty) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eastern Oil Co. v. Beatty, 1918 OK 625, 177 P. 104, 71 Okla. 275, 1918 Okla. LEXIS 942 (Okla. 1918).

Opinion

MILEX, J.

This action was commenced in the court below on July 25. 1912, by defendants in error, as plaintiffs therein, to cancel and remove as a cloud upon their title to 80 acres of land, of which they were the owners, an oil and gas lease thereon, which ■they had executed and delivered on the 14th day of September, A. D. 1910, to the plaintiff in error, defendant below. There was judgment for the plaintiffs for cancellation as prayed, to reverse which this proceeding in error is prosecuted.

The lease in question was executed for a consideration or cash bonus of $2,100, paid at the time of its execution and delivered, and an additional bonus of $2,000 to be paid out of 25 per cent, of the working interest of the oil produced from said land. It was for a term of 10 years from date thereof, and as long thereafter as oil m gas, or •ither of them, should be produced therefrom. The lessee covenanted and agreed to pay royalties of one eighth of all oil produced or the market price therefor, and $150 per year for the gas from each and every gas well, if the product should be marketed and used off of the premises. The lessee further agreed to complete a well on said premises wuhin 90 days from the date of the lease, or pay at the rate of .$20 quarterly in advance for each additional three months such completion should be delayed. It was agreed that the completion of a well shornd be and operate as a full liquidation of all rentals for delay under that provision during the remainder of the term. It was aiso agreed that such payments should be deposited to the credit of the lessors in the Central National Bank of Tulsa, Okla. It was further agreed that, upon the payment of $1 at any time after giving three months’ notice, the lessee should have the right to surrender the lease for cancellation, after which all payments and liabilities thereafter to accrue under and by virtue of its terms should cease and determine, and the grant become absolutely null and void.

There was no material conflict in the evidence. It appears therefrom that the lessee had not commenced operations and no well was completed on the premises at the time of the trial. The lessee, however, had i>aid and the lessors had accepted all payments due for all quarterly periods of delay up to the quarter 'commencing on June 14, 1912. The lessee tendered the payment for'delay for that quarter in advance, but the lessors refused to accept the same or any subsequent quarterly payments for delay. The lessee thereupon deposited the payment due for the quarter beginning June 14, 1912, and for each subsequent quarter to the credit of the lessors in the bank designated in the agreement. On September 27, 1911, the lessors notified the lessee in writing that a well had been- drilled upon land adjoining the leased premises, producing oil in paying quantities, and that the same was being operated and draining the oil from' beneath their land, and made demand that the lessee drill an offset well on their land, and unless this was done they would institute action for the cancellation of the lease and damages for failure fco' drill said well. And again on June 14, 1912, they notified the lessee that the said well on the adjoining premises was draining the oil from beneath their land, and demanded that the lessee commence an offset well on their property within .the next 30 days; and continue the drilling thereof without unnecessary delay to final completion; and that, unless this *277 was done, they would declare the lease forfeited, and terminate the rights and privileges of the lessee thereunder, and would institute an action for cancellation of the lease and for damages for failure to develop and protect the property. They further notified the lessee that they would not accept any further payments for delay.

Special findings of fact and conclusions’ of law were not requested, and there was a general finding only for the plaintiffs, soi it does not appear upon which of the several grounds urged the decree of cancellation was made.

The defendants in error in their brief insist that the judgment should be sustained upon any one of three grounds, namely: First, that the lease is “unilateral, and therefore subject to be terminated” by them; second, for breach of the implied covenant to develop the property; and, third for breach of the implied covenant to protect the premises from drainage by wells drilled upon adjacent land.

It is now well settled by previous decisions of this court that the lease, having been executed for a valuable consideration, to wit, $2,100 cash in hand, in addition to the covenant to develop and pay royalites, or to pay rentals in lieu of such development, is valid, notwithstanding the so called surrender clause, and is not subject to cancellation on the ground that the contract is unilateral and void for want of mutuality, and that the' right' given the lessee to terminate does not confer a corresponding" right of termination upon the lessors. Northwestern Oil & Gas Co. v. Branine, 71 Okla. 107, 175 Pac. 533; Pucini et al. v. Bumgarner, 71 Okla. 105, 175 Pac. 537. Therefore the judgment 'of the trial court cannot be sustained upon the first ground above stated.

As to the second ground, it is sufficient to ,say that no covenant to develop the property can be implied in the face of an express stipulation for periodical payments for delay thereof not extending beyond a definite teim. Although development on other lands in the vicinity may show the premises to be situated in oil and gas territory, and prove the adaptability of their land for successful and profitable mining operations, the lessors have no legal cause for complaint so long as they receive compensation for the delay for which they have contracted, and the operations on neighboring lands do not drain their premises. This court has never held, and, so far as we are aware, neither has any other court, that under such conditions a covenant for diligent operation, or operation at all, will be implied.

In one class of cases covenants for development have been held to arise by implication where prospective royalties were held to be the sole or a substantial part of the consideration, no provision being made in the leases for the time of beginning operations or compensation for delay. In such circumstances it has been held that operations must commence within a reasonable time and be prosecuted with diligence. In another class of cases, in which after a well had been commenced or completed, and the provision in the lease for payment .for delay in commencing or completing a well, as the case may be, was no longer operative, covenants for diligent operation thereafter have been implied. In yet another class of cases, in which, although the lease provided for the time in which a well should be commenced- or completed, and for payments for periodical delays, but .there was no fixed term or limitation of time beyond which development may be delayed by such payments, it was held that the lessor may refuse such payments for delay and demand development within a reasonable time thereafter, and terminate the lease for failure of the lessee to comply therewith. But in no case, so far as we are advised, except, perhaps, in Indiana, where the lease is for a definite term and provides for the payment of a stipulated sum for delay during that term, and that provision is still effective, has it been held that the lessor can refuse the stipulated payments for delay and recover damages, or invoke a. forfeiture for failure to develop upon demand.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rogers v. Heston Oil Co.
1984 OK 75 (Supreme Court of Oklahoma, 1984)
Haken v. Harper Oil Co.
1979 OK CIV APP 32 (Court of Civil Appeals of Oklahoma, 1979)
Jordan v. Texaco Inc.
297 F. Supp. 1140 (W.D. Oklahoma, 1969)
Spiller v. Massey & Moore
406 P.2d 467 (Supreme Court of Oklahoma, 1965)
Gazin v. Pan American Petroleum Corporation
367 P.2d 1010 (Supreme Court of Oklahoma, 1962)
Producers Pipe and Supply Co. v. James
1958 OK 255 (Supreme Court of Oklahoma, 1958)
Gregg v. Harper-Turner Oil Co.
199 F.2d 1 (Tenth Circuit, 1952)
Cosden v. Carter Wolf Drilling Co.
183 F.2d 761 (Tenth Circuit, 1950)
Carter Oil Co. v. Dees
92 N.E.2d 519 (Appellate Court of Illinois, 1950)
Magnolia Petroleum Co. v. Vaughn
1945 OK 220 (Supreme Court of Oklahoma, 1945)
Hood v. Southern Production Co.
19 So. 2d 336 (Supreme Court of Louisiana, 1944)
Poindexter v. Lion Oil Refining Co.
167 S.W.2d 492 (Supreme Court of Arkansas, 1943)
Indian Territory Illuminating Oil Co. v. Rosamond
1941 OK 410 (Supreme Court of Oklahoma, 1941)
Myers v. Shell Petroleum Corp.
110 P.2d 810 (Supreme Court of Kansas, 1941)
Central States Production Corp. v. Jordan
1939 OK 35 (Supreme Court of Oklahoma, 1939)
Carter Oil Co. v. Mitchell
100 F.2d 945 (Tenth Circuit, 1939)
Ramsey Petroleum Corporation v. Davis
1938 OK 659 (Supreme Court of Oklahoma, 1938)
Carter Oil Co. v. Samuels
1937 OK 638 (Supreme Court of Oklahoma, 1937)
Phoenix Oil Co. v. Mid-Continent Petroleum Corp.
1936 OK 250 (Supreme Court of Oklahoma, 1936)
Wilcox v. Ryndak
1935 OK 909 (Supreme Court of Oklahoma, 1935)

Cite This Page — Counsel Stack

Bluebook (online)
1918 OK 625, 177 P. 104, 71 Okla. 275, 1918 Okla. LEXIS 942, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eastern-oil-co-v-beatty-okla-1918.