Eastern Metal Bill Products Co. v. Reilly

1983 Mass. App. Div. 227, 1983 Mass. App. Div. LEXIS 85
CourtMassachusetts District Court, Appellate Division
DecidedJuly 21, 1983
StatusPublished
Cited by1 cases

This text of 1983 Mass. App. Div. 227 (Eastern Metal Bill Products Co. v. Reilly) is published on Counsel Stack Legal Research, covering Massachusetts District Court, Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eastern Metal Bill Products Co. v. Reilly, 1983 Mass. App. Div. 227, 1983 Mass. App. Div. LEXIS 85 (Mass. Ct. App. 1983).

Opinion

Umana, J.

This is an action for goods sold and delivered in which the plaintiff seeks to recover for such goods in the amount of $384.15. The defendant filed an answer and counterclaim. The court found for the plaintiff on its complaint in the sum of $384.15, and the court found for the defendant on its counterclaim in the sum of $7,621.00.

At the trial, there was evidence that sometime in 1976 the defendant, Francis X. Reilly, contracted with the plaintiff for the procurement of certain aluminum extrusions which were to become handrails on a project in Rhode Island. Reilly informed Eastern that he was a sub-contractor on the job and that he was subject to $500 per day delay charges. These extrusions were to be installed as side and center-lighted handrails.

Delivery of these special extrusions was made in November, 1976. When they were received, Reilly noted that they were deeply gouged, pitted, scratched and damaged on their ends. Reilly immediately telephoned Gerry Gorham at Eastern Metals informing him that the extrusions were defective and inquiring about a shipment of replacements. Gorham offered a new shipment but told Reilly it could not be made for eighteen weeks. Reilly explained that he was already behind schedule and that he could not wait eighteen weeks. Gorham and Reilly discussed the matter and it was agreed that Reilly should attempt to remedy the shipment by cutting out the worst sections and by sanding and grinding the remainder of the extrusions so that they would be put in useable condition.

Reilly and his employees expended a great deal of shop and on-site time in performing this work. In all, Reilly compiled additional costs for labor, anodizing, trucking and other costs, the total of which exceeded $15,000.00.

The plaintiff claims to be aggrieved by the trial judge’s rulings on the following requests:

2. That a finding for the defendant is not warranted.
COURT: Denied. A finding for the defendant on the plaintiffs complaint is warranted, but I do not so find. There was evidence that the defendant rejected the aluminum extrusions at issue, however I find that he accepted the goods as non-conforming and that he worked on the extrusions, cutting, grinding and sanding them until they were sufficiently smooth to use.
5. That the defendant having accepted and used the merchandise in [228]*228question, is not estopped from objecting to the quality of the merchandise. M.G.L. c. 106, § 2-605.
COURT: Denied as an incorrect statement of M.G.L. c. 106, § 2-605. When the defendant, Reilly, inspected the extrusions he saw that they were pitted, gouged, and too rough for use as hand railings. Immediately he called Gerry Gorham at Eastern Metal and informed him that the goods were not acceptable and clearly informed Gorham as to the defects. He told Gorham that he wanted another shipment, but because the items could not be supplied to the defendant for at least 13-18 weeks, and because the defendant would therefore be in breach of his contract with the general contractor, and subject to severe delay penalties, Gorham instructed him to attempt to smooth down the items, cutting out the worst parts. His conversation with Gorham constituted notice of breach pursuant to M.G.L. c. 106, § 2-607.
6. That the defendant has accepted goods from the plaintiff because:
(a) After a reasonable opportunity to inspect the goods the defendant has signified to the plaintiff that the goods were conforming or that he would take or retain them in spite of their non-conformity; and
(b) The defendant had failed to make an effective rejection, in accord with subjection (1) of M.G.L. c. 106, § 2-605; and
(c) The defendant has done acts inconsistent with the seller’s ownership, for example, inter alia, use of goods in violation of M.G.L. c. 106, § 2-605.
COURT: Granted that the defendant accepted the goods but he did notify the plaintiff of the breach pursuant to M.G.L. c. 106, §2-607 (3)(a).
8. That, a finding for the defendant (plaintiff-in-counterclaim) is not warranted.
COURT: Denied, a finding for Reilly is warranted. Furthermore, I find for Reilly in the amount of $7,621 on the counterclaim due to the Eastern Metal’s breach of warranty by delivery of the defective aluminum extrusions.
15. That the defendant is not allowed to bring a compulsory counterclaim at any time other than at the time of filing his answer. The defendant did not bring the compulsory counterclaim until well after he had filed his answer and therefore, the counterclaim is void pursuant to Dist./Mun. Cts. R. Civ. P., Rule 13(a). Potier v. A.W. Perry, Inc., 286 Mass. 602 (1934).
COURT: Denied as an incorrect statement of Dist./Mun. Cts. R. Civ. P., Rule 13(a), and as not applicable. Assuming that the counterclaim in this case is compulsory in that it arises out of the same transaction and because it satisfies the other recognized tests, the counterclaim has been brought by the defendant in pleading to the complaint. Furthermore, there was no motion to strike or dismiss the counterclaim nor was there objection at trial to the introduction of evidence on the counterclaim. Any objection to the counterclaim is therefore deemed waived.
16. That the defendant, at the time of moving to amend his answer by ordering the counterclaim, had not suffered any damages. The defendant states, under oath, in the affidavits attached hereto, that the damages were not determined at the time of filing the counterclaim. Therefore, the counterclaim is null and void pursuant to Dist./Mun. [229]*229Cts. R. Civ. P., Rule 13 and as not applicable since any objection to the counterclaim has been deemed waived. (See ruling on Request #15).

The court also made the following findings of fact:

The defendant is alighting contractor and has been in the business of supplying lighting, ceilings, fixtures and components thereof for thirty years. In early 1976, the defendant became a sub-contractor/supplier on a construction job in Rhode Island. He was to supply handrail lighting, the installation of which was to commence in October, 1976. He contacted the plaintiff and provided drawings of a particular aluminum extrusion which was to become the handrails. Eastern Metals sent back an alternative drawing, which Reilly approved and adopted. He informed Eastern Metal that he needed the handrails the second week in October and the plaintiff agreed that it could make the October delivery date. Eastern stated that it did not have the items on the shelf, so a special die would have to be made for the job. Reilly informed Eastern that he was subject to $500/day delay charges by the general contractor.
The extrusions at issue were delivered approximately two weeks late, in November, 1976. When Reilly received the items he opened the boxes and found that the handrails were unsatisfactory, because their surfaces were too rough in that they were gouged, pitted and marred by slits and scrapes. He called Gerry Gorham at Eastern Metal and inquired about a new shipment of non-defective extrusions. Gorham informed him it would take thirteen to eighteen weeks for delivery of new handrails.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wilshire Credit Corp. v. Scott
1997 Mass. App. Div. 91 (Mass. Dist. Ct., App. Div., 1997)

Cite This Page — Counsel Stack

Bluebook (online)
1983 Mass. App. Div. 227, 1983 Mass. App. Div. LEXIS 85, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eastern-metal-bill-products-co-v-reilly-massdistctapp-1983.