East Side v. Next, Inc.

2014 SD 59
CourtSouth Dakota Supreme Court
DecidedAugust 6, 2014
StatusPublished

This text of 2014 SD 59 (East Side v. Next, Inc.) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
East Side v. Next, Inc., 2014 SD 59 (S.D. 2014).

Opinion

#26776-aff in pt & rev in pt-GAS 2014 S.D. 59

IN THE SUPREME COURT OF THE STATE OF SOUTH DAKOTA

**** EAST SIDE LUTHERAN CHURCH OF SIOUX FALLS, SOUTH DAKOTA, a South Dakota Nonprofit Corporation, Plaintiff and Appellant,

v.

NEXT, INC., a South Dakota Corporation, Defendant, Third-Party Plaintiff and Appellee,

FIEGEN CONSTRUCTION CO., a South Dakota Corporation and BROWN ARCHITECTURE & DESIGN CO. n/k/a STUDIO 360 ARCHITECTURE, INC., a Nebraska Corporation, Third-Party Defendants, Fourth-Party Plaintiffs and Appellees,

M.J. DALSIN CO. OF S.D., INC., Fourth-Party Defendant, Fifth-Party Plaintiff and Appellee,

JEFF PRINS d/b/a AJ CONSTRUCTION, Fifth-Party Defendant.

**** APPEAL FROM THE CIRCUIT COURT OF THE SECOND JUDICIAL CIRCUIT MINNEHAHA COUNTY, SOUTH DAKOTA **** THE HONORABLE STUART L. TIEDE Judge **** ARGUED APRIL 29, 2014 OPINION FILED 08/06/14 RONALD A. PARSONS, JR. Johnson, Heidepriem & Abdallah, LLP Sioux Falls, South Dakota

and

WILLIAM D. KUNSTLE SAMUEL M. GOODHOPE LAURA T. BRAHMS Kading, Kunstle & Goodhope, LLP Sioux Falls, South Dakota Attorneys for plaintiff and appellant.

PAUL W. TSCHETTER ROGER A. SUDBECK Boyce, Greenfield, Pashby & Welk, LLP Sioux Falls, South Dakota Attorneys for defendant, third- party plaintiff and appellee Next, Inc. DEREK A. NELSON WILLIAM P. FULLER Fuller & Williamson, LLP Sioux Falls, South Dakota Attorneys for third-party defendant, fourth-party plaintiff and appellee Brown Architecture & Design Co.

MICHAEL L. LUCE Murphy, Goldammer & Prendergast, LLP Sioux Falls, South Dakota Attorneys for third-party defendant, fourth-party plaintiff and appellee Fiegen Construction Co.

GREGORY J. ERLANDSON Bangs, McCullen, Butler, Foye & Simmons, LLP Rapid City, South Dakota Attorneys for fourth-party defendant, fifth-party plaintiff and appellee M.J. Dalsin Co. of S.D., Inc. #26776

SEVERSON, Justice

[¶1.] East Side Lutheran Church (East Side) appeals from a summary

judgment ruling that barred its claim for failing to timely file suit within the

applicable six-year statute of limitations. We affirm in part and reverse in part.

Background

[¶2.] In April 2002, East Side contracted with NEXT, Inc. (NEXT) for

construction of a new addition to East Side’s church and renovation to its existing

structure. NEXT worked as East Side’s representative for the project and

contracted with third-party defendants Brown Architecture & Design Company

(Brown) and Fiegen Construction Company (Fiegen). Brown provided design and

architectural work on the project and Fiegen served as the general contractor.

Fiegen subcontracted with fourth-party defendant M.J. Dalsin Company (Dalsin) to

complete the roof construction associated with the project. 1 The project was

substantially completed in August 2003.

[¶3.] In the months immediately following the project’s completion, East

Side experienced a variety of problems throughout the structure. The problems

included ice dams, bats in the church, chipping concrete, hail penetration, and

drainage issues, but the overriding problem was water infiltration. 2 The water

infiltration persisted and resulted in this litigation.

1. Dalsin in turn sub-subcontracted with fifth-party defendant AJ Contracting to provide work on the roof construction. Dalsin obtained a default judgment against AJ Contracting prior to the circuit court’s summary judgment ruling.

2. Water was found in the west entrance, east vestibule, Pastor’s office, quilting room, prison ministry office, furnace room, north-side basement, kitchen, pre- (continued . . .) -1- #26776

[¶4.] East Side and NEXT communicated about, and NEXT attempted to

eradicate, the water infiltration from the date of the project’s completion until May

2009. On January 23, 2009, NEXT’s attorney sent a letter to East Side explaining

that Fiegen and Dalsin were “unwilling to perform any additional work[,]” and that

NEXT had, without admitting liability, “notified its insurance carrier of a potential

claim.” Later that spring, on May 28, 2009, NEXT’s attorney informed East Side’s

attorney that NEXT “will be undertaking no additional repairs to” the church. The

letter further stated that East Side “will need to either undertake its own repairs

and proceed with litigation or contact Fiegen and Dalsin regarding any such

repairs.”

[¶5.] In March 2010, East Side hired Michael Ollerich of American

Technical Services. Ollerich’s reports confirmed that the church was experiencing

water infiltration. Ollerich’s reports further indicated the project’s design contained

structural errors; the work completed contained construction errors; and the

structure was experiencing ventilation and insulation problems. East Side filed suit

against NEXT in July 2010. 3

[¶6.] NEXT, Brown, Fiegen, and Dalsin (Defendants) moved for summary

judgment on the basis that East Side filed its suit outside of the six-year statute of

________________________ (. . . continued) kindergarten room, kindergarten room, storage room, second-floor altar-guide room, and second-floor south furnace room. In addition, hail was found in the narthex. Gigi Rieder, East Side’s office manager, testified that the water infiltration was “throughout the structure.”

3. In addition to defending the lawsuit, NEXT sued third-party defendants Brown and Fiegen, Fiegen sued fourth-party defendant Dalsin, and Dalsin sued fifth-party defendant AJ Contracting.

-2- #26776

limitations. See SDCL 15-2-13. The Defendants argued that because East Side

knew of the water infiltration immediately after construction was completed, the

six-year statute of limitations began to run as early as August 2003. As a result,

the statute of limitations lapsed in 2009 and East Side’s July 2010 lawsuit was not

timely filed.

[¶7.] East Side opposed summary judgment and argued that its lawsuit is

based in part on the project’s structural design errors and construction errors.

Because it did not know of the structural design errors and construction errors until

Ollerich’s 2010 reports, it argued its claims did not accrue until 2010, making its

suit timely. East Side also argued that equitable estoppel tolled the statute of

limitations.

[¶8.] The circuit court granted summary judgment to Defendants on the

statute of limitations issue because East Side “had actual or constructive notice of a

cause of action immediately after the substantial completion [of the project] in

August of 2003.” The circuit court also granted summary judgment to Defendants

on the issue of equitable estoppel because there was no “genuine issue of material

fact regarding whether or not any of the [D]efendants misrepresented or concealed

material facts from [East Side] in order to induce [East Side] to change its position

in reliance upon either those misrepresentations or that concealment.” East Side

now appeals to this Court arguing the circuit court’s rulings on the statute of

limitations and equitable estoppel were error. 4

4. Our review of a summary judgment ruling is clear:

(continued . . .) -3- #26776

Decision

Statute of limitations

[¶9.] The parties agree that the six-year statute of limitations prescribed by

SDCL 15-2-13 controls East Side’s claims. East Side commenced this action in July

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Strassburg v. Citizens State Bank
1998 SD 72 (South Dakota Supreme Court, 1998)
Wissink v. Van De Stroet
1999 SD 92 (South Dakota Supreme Court, 1999)
Cooper v. James
2001 SD 59 (South Dakota Supreme Court, 2001)
Dakota, Minnesota & Eastern Railroad v. Acuity
2006 SD 72 (South Dakota Supreme Court, 2006)
Spencer v. Estate of Spencer
2008 SD 129 (South Dakota Supreme Court, 2008)
Gruhlke v. Sioux Empire Federal Credit Union, Inc.
2008 SD 89 (South Dakota Supreme Court, 2008)
Wilcox v. VERMEULEN
2010 SD 29 (South Dakota Supreme Court, 2010)
St. Pierre v. State Ex Rel. South Dakota Real Estate Commission
2012 S.D. 25 (South Dakota Supreme Court, 2012)
Johnston v. Centennial Log Homes & Furnishings, Inc.
2013 MT 179 (Montana Supreme Court, 2013)
Jandreau v. Sheesley Plumbing & Heating Co.
324 N.W.2d 266 (South Dakota Supreme Court, 1982)
Performing Arts Center Authority v. CLARK CONST. GROUP, INC.
789 So. 2d 392 (District Court of Appeal of Florida, 2001)
Huron Center, Inc. v. Henry Carlson Co.
2002 SD 103 (South Dakota Supreme Court, 2002)
De Smet Farm Mutual Insurance Co. of South Dakota v. Busskohl
2013 SD 52 (South Dakota Supreme Court, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
2014 SD 59, Counsel Stack Legal Research, https://law.counselstack.com/opinion/east-side-v-next-inc-sd-2014.