East Hills Condominiums Ltd. Partnership v. Tri-Lakes Escrow, Inc.

280 S.W.3d 728, 2009 Mo. App. LEXIS 147, 2009 WL 429212
CourtMissouri Court of Appeals
DecidedFebruary 23, 2009
DocketSD 28892
StatusPublished
Cited by4 cases

This text of 280 S.W.3d 728 (East Hills Condominiums Ltd. Partnership v. Tri-Lakes Escrow, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
East Hills Condominiums Ltd. Partnership v. Tri-Lakes Escrow, Inc., 280 S.W.3d 728, 2009 Mo. App. LEXIS 147, 2009 WL 429212 (Mo. Ct. App. 2009).

Opinion

ROBERT S. BARNEY, Judge.

Appellant Tri-Lakes Escrow, Incorporated, a/k/a and d/b/a TriLakes Title Company (“Appellant”) appeals the Judgment of the trial court entered in favor of East Hills Condominiums Limited Partnership (“Respondent”). In its Judgment, the trial court found the parties had entered into a written agreement as well as “an express trust for the distribution of funds;” Appellant breached the parties’ agreement; and Respondent was damaged in the amount of $501,305.00. Appellant asserts three points relied on challenging the trial court’s application of the ten-year statute of limitations set out in section 516.110(1) as well as the inclusion of certain items in the amount of damages awarded. 1

The record reveals that in early 1998 Respondent decided to create a condominium development in Branson, Missouri, known as the Foothills which was planned to have 136 condominium units located in six buildings. Respondent hired Killian Construction (“Killian”) to be the general contractor on the Foothills project. Respondent secured financing through Great Southern Savings Bank (“Great Southern”), and engaged Appellant to serve as the escrow agent.

On August 18, 1993, the parties entered into the “FOOTHILLS CONDOS-EAST HILLS DEVELOPMENT ESCROW DISBURSAL CONTRACT” (“the Agreement”). The Agreement purported to be a four-way contract between Respondent as “Owner,” Killian as “Contractor,” Great Southern as “Lender,” and Appellant as “Agent.” 2 The Agreement provided “for disbursals of the proceeds of that certain loan ... in the amount of $6,779,373.00 to be used in the construction of the ...” Foothills development. Article I of the Agreement set out the responsibilities of each party. Killian “agree[d] to furnish all labor, material, supplies and equipment required for the completion of the construction of the project....” Great Southern “agree[d] to furnish the proceeds of the *730 construction loan to [Appellant] for payment to [Killian].... ” Respondent “agree[d] to furnish all funds in excess of the proceeds of the construction loan to [Appellant] for payment to [Killian].... ” The Agreement further provided Appellant “shall make all payments on behalf of [Respondent] and [Great Southern] to [Kil-lian] in the manner and at such times and places hereinbelow set forth.” Article IIA of the Agreement, which detailed “Payments,” set out the following:

Before payment shall be due ... [Killi-an] shall submit to [Appellant] individual ‘Contractor’s Request for Payment Certificate’, ... executed by or on behalf of each general contractor, subcontractor, workman or materialman upon whose behalf payment is requested, together with the certificate of the Architect certifying the amount due upon said application for payment.
Thereafter, [Appellant] shall provide [Killian] with individual “Waiver of Lien,’ for each general contractor, subcontractor, workman or materialman, in substantial form as that shown on Exhibit ‘D’, attached hereto and made a part hereof ... which Waiver upon due execution and presentation to [Appellant] shall be paid.

Further, Article II B of the Agreement stated:

Upon completion of each individual contractors’, subcontractors’, workman’s or materialmen’s portion of the Project, [Killian] shall furnish [Appellant] ... a Final Request therefor[e], and shall be entitled to receive, within ten (10) days thereafter, the balance of funds certified therein.
Thereafter, [Appellant] shall provide [Killian] with individual ‘Waiver of Lien’, in substantial form as that shown in Exhibit ‘D,’ attached hereto and made a part hereof ... which Waiver upon due execution and presentation to [Appellant] shall be paid.

By early January of 1994, problems had arisen on the Foothills project such that Killian “pull[ed] off’ the project on January 10, 1994, and ceased construction. Thereafter, Respondent was notified by numerous subcontractors and vendors that they had not been paid for their work on the project although Appellant reported to Respondent that it had paid Killian. 3 When Respondent approached Appellant with its concerns, Appellant was unable to produce the required paperwork to prove its disbursements under the Agreement and to prove that it obtained lien waivers on all the disbursals.

On August 14, 2003, Respondent filed its “Petition” in which it asserted in Count I that Appellant had breached an express trust by “failing to properly account for money it held in trust for [Respondent] and failed to properly account for all payments relative to labor and materials ... by obtaining validly executed Lien Waivers as provided in [the] Agreement” and in Count II that Appellant breached a contract “for the payment of money or property.”

On October 30, 2003, Appellant filed a “Motion to Dismiss” Respondent’s petition on the basis that Respondent’s claims were essentially for breach of contract and were barred by the five-year statute of limitations set out in section 516.120. 4 This motion was overruled by the trial court.

*731 The trial in this matter was held on August 27, 2007. At trial, Leora Zook-Piatt (“Ms. Zook-Piatt”), Appellant’s “[s]enior construction disbursal officer,” testified that a typical draw request on a construction project consisted of several documents as well as invoices. She stated each draw request had a cover sheet which had to be signed by the contractor, the property owner, the lender, and, if required, the project’s architect. She stated that once the required signatures were obtained on the cover sheet, she reviewed the invoices and matched them up to the entries on the pay list. She related the invoices attached to the draw request always “must be equal to or greater than the amount” stated in the draw request. Once she matched up the invoices to the entries on the pay list Ms. Zook-Piatt prepared a “requisition certificate,” which informed the lender of the amount of the request. If the lender approved the draw request, it then provided the funds, in most cases, directly to Appellant. The lender very rarely paid vendors and subcontractors directly. When funds were transferred from the lender to Appellant, they were held in an account by Appellant.

Ms. Zook-Piatt also testified she then “disburse[s] the checks accordingly and collect[s lien] waivers.” She stated she “[a]ccumulate[s] the appropriate lien waivers that’s going to equal the amount that is being disbursed” prior to issuing the checks to those listed on the pay list. She stated that even when she issued a reimbursement check to a contractor for work done by a subcontractor she was required to obtain a lien waiver from the subcontractor. She stated the lien waivers were important to protect the interests of the property owner and the lender so that they could avoid liens in the future as well as double payments. She admitted that ultimately it was her obligation to obtain the lien waivers whether she did so when she disbursed the checks or at a later date. 5

As for the documents relating to the Foothills project, Ms.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ries v. Shoemake
359 S.W.3d 137 (Missouri Court of Appeals, 2012)
Hanna v. Director of Revenue
347 S.W.3d 95 (Missouri Court of Appeals, 2011)
Hauter v. Hauter
351 S.W.3d 228 (Missouri Court of Appeals, 2011)
Fields v. Advanced Health Care Management Services, LLC
340 S.W.3d 648 (Missouri Court of Appeals, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
280 S.W.3d 728, 2009 Mo. App. LEXIS 147, 2009 WL 429212, Counsel Stack Legal Research, https://law.counselstack.com/opinion/east-hills-condominiums-ltd-partnership-v-tri-lakes-escrow-inc-moctapp-2009.