East Coast Storage Equipment Co Inc v. ZF Transmissions Gray Court LLC

CourtCourt of Appeals for the Fourth Circuit
DecidedDecember 30, 2025
Docket24-1248
StatusUnpublished

This text of East Coast Storage Equipment Co Inc v. ZF Transmissions Gray Court LLC (East Coast Storage Equipment Co Inc v. ZF Transmissions Gray Court LLC) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
East Coast Storage Equipment Co Inc v. ZF Transmissions Gray Court LLC, (4th Cir. 2025).

Opinion

USCA4 Appeal: 24-1248 Doc: 60 Filed: 12/30/2025 Pg: 1 of 13

UNPUBLISHED

UNITED STATES COURT OF APPEALS FOR THE FOURTH CIRCUIT

No. 24-1248

EAST COAST STORAGE EQUIPMENT CO INC,

Plaintiff - Appellant,

v.

ZF TRANSMISSIONS GRAY COURT LLC; ZF NORTH AMERICA INC,

Defendants - Appellees,

and

THS CONSTRUCTORS INC,

Defendant.

Appeal from the United States District Court for the District of South Carolina, at Greenville. Timothy M. Cain, Chief District Judge. (6:21-cv-01574-TMC)

Argued: May 7, 2025 Decided: December 30, 2025

Before NIEMEYER and BENJAMIN, Circuit Judges, and KEENAN, Senior Circuit Judge.

Vacated and remanded by unpublished opinion. Judge Benjamin wrote the opinion, in which Judge Keenan joined. Judge Niemeyer wrote a dissenting opinion. USCA4 Appeal: 24-1248 Doc: 60 Filed: 12/30/2025 Pg: 2 of 13

ARGUED: Adam C. Bach, TONNSEN BACH, LLC, Greenville, South Carolina, for Appellant. Sean P. McNally, TROUTMAN PEPPER LOCKE LLP, Charlotte, North Carolina, for Appellees. ON BRIEF: Emily R. Godwin, TONNSEN BACK, LLC, Greenville, South Carolina, for Appellant. William J. Farley III, TROUTMAN PEPPER HAMILTON SANDERS LLP, Charlotte, North Carolina, for Appellees.

Unpublished opinions are not binding precedent in this circuit.

2 USCA4 Appeal: 24-1248 Doc: 60 Filed: 12/30/2025 Pg: 3 of 13

DEANDREA GIST BENJAMIN, Circuit Judge:

This case arises from a construction project contract dispute between East Coast

Storage Equipment Co., Inc. (“East Coast”), a manufacturing company, and ZF

Transmissions Gray Court, LLC, and ZF North America, Inc. (collectively, “ZF”), two

technology companies. The district court granted summary judgment to ZF on all claims,

finding that East Coast received the full benefit of its bargain. We disagree—and therefore

vacate the district court’s judgment and remand for further proceedings.

I.

East Coast is “a manufacturer, custom fabricator, erector, installer, and distributor

of” racking systems. 1 J.A. 14. 2 The two companies comprising ZF are“global technology

compan[ies] that suppl[y] industrial technology and technology systems to the automotive

industry. Id. at 15

Corey Collins, a launch manager at ZF, contacted John Geddes, East Coast’s

director of sales and racking specialist, to discuss the potential design, manufacture, and

installation of a racking system for ZF’s expansion at its Gray Court, South Carolina,

facility. A few days later, Geddes and another East Coast representative met with

Racking systems, or “automated storage and retrieval system[s] (‘ASRS’) . . . [are] 1

an automated system that retrieves automotive parts from storage racks in order to fulfill customer orders.” J.A. 71.

Citations to “J.A.” refer to the joint appendix filed by the parties. The J.A. contains 2

the record on appeal from the district court. Page numbers for citations to the J.A. utilize the “JA#” numbering at the bottom of the page on each document.

3 USCA4 Appeal: 24-1248 Doc: 60 Filed: 12/30/2025 Pg: 4 of 13

representatives from ZF and Ghafari Associates, LLC, the architect for the project. At the

meeting, the attendees discussed the roles of each participant in issuing a request for

quotation (“RFQ”) 3 to prospective general contractors. The meeting minutes distributed

by ZF specified each participant’s role and indicated that East Coast would provide detailed

racking drawings to be included in the RFQ.

After the meeting, Christoph Zepf, ZF’s director of purchasing, spoke separately

with Geddes. Zepf and Geddes have differing accounts of this conversation. Geddes

testified that during this private conversation, Zepf promised that in exchange for East

Coast’s racking drawings, ZF would guarantee East Coast exclusive rights to supply the

racking structures for the project and its revenue would come from the contract with the

winning bidder. Zepf testified that he only promised that East Coast would be included in

the RFQ process as a preferred supplier: he did not guarantee that East Coast would be

selected by the general contractor or any monetary compensation.

A little over a month after this meeting, East Coast submitted design drawings to

ZF, which were sent to bidders the same day. With East Coast listed as its racking system

supplier, THS Constructors, Inc. (“THS”), “a foreign construction services corporation,”

J.A. 15, ultimately won the project. ZF and THS executed an agreement to confirm that

THS would serve as the project’s general contractor. East Coast and THS subsequently

executed a subcontract, which included immediate payment to East Coast.

3 An RFQ is used to solicit bids from general contractors. See J.A. 16, 20.

4 USCA4 Appeal: 24-1248 Doc: 60 Filed: 12/30/2025 Pg: 5 of 13

After several days without receiving the agreed payment, East Coast’s counsel

formally requested immediate payment from THS. While awaiting payment, East Coast

continued to work on the project by meeting with a steel manufacturer in preparation for

steel manufacturing to commence. THS sent ZF a draft response to East Coast’s request.

ZF encouraged THS to terminate its relationship with East Coast and find an alternative

racking supplier—all unbeknownst to East Coast.

The day after ZF and THS discussed East Coast’s request for payment and

terminating East Coast from the project, East Coast requested access to the project site for

its racking manufacturer’s engineer to verify dimensions. ZF denied East Coast’s request,

claiming it was untimely made. East Coast indicated it would reschedule the visit for two

weeks later, but ZF never confirmed access would be granted.

The following week, per ZF’s request to solicit other racking suppliers, THS

informed ZF that it had solicited six potential substitute racking suppliers and forwarded

proposals from one of them. That same day, THS’ counsel sent a letter to East Coast’s

counsel advising East Coast to put a hold on the project. Days later, East Coast contacted

ZF, seeking clarification on THS’ letter. ZF responded that it was consulting with counsel

and would reply soon.

ZF later sent a letter to both THS and East Coast, stating that it would not be

involved in any contractual dispute between them and that it “expect[ed] each entity

engaged in its construction project to fully perform each and every commitment and

obligation.” J.A. 346. However, internal communications between ZF and THS

representatives indicate that ZF had been actively involved in the decision to terminate East

5 USCA4 Appeal: 24-1248 Doc: 60 Filed: 12/30/2025 Pg: 6 of 13

Coast and had been reviewing potential substitutes for East Coast. See J.A. 337–39. East

Coast continued working on the project unaware of ZF’s intention to terminate East Coast’s

relationship with both ZF and THS.

The following week, ZF directed THS to choose an alternate racking system

supplier. East Coast again requested payment from THS in accordance with their

agreement. The next day, THS sought ZF’s approval for replacing East Coast and paying

East Coast for the estimated costs that it had incurred with the project.

ZF approved a revised request for payment from THS, which excluded payment to

East Coast for its costs working on the project. That same day, THS sent East Coast a letter

formally terminating its involvement in the project. East Coast was never compensated for

Free access — add to your briefcase to read the full text and ask questions with AI

Related

R.B. Ventures, Ltd. v. Shane
112 F.3d 54 (Second Circuit, 1997)
Player v. Chandler
382 S.E.2d 891 (Supreme Court of South Carolina, 1989)
Branche Builders, Inc. v. Coggins
686 S.E.2d 200 (Court of Appeals of South Carolina, 2009)
Armstrong v. Collins
621 S.E.2d 368 (Court of Appeals of South Carolina, 2005)
Roberts v. Gaskins
486 S.E.2d 771 (Court of Appeals of South Carolina, 1997)
Hughes v. Edwards
220 S.E.2d 231 (Supreme Court of South Carolina, 1975)
Fuller v. Eastern Fire & Casualty Insurance
124 S.E.2d 602 (Supreme Court of South Carolina, 1962)
Stevens & Wilkinson of South Carolina, Inc. v. City of Columbia
762 S.E.2d 696 (Supreme Court of South Carolina, 2014)
Iraq Middle Market Development v. Mohammad Harmoosh
947 F.3d 234 (Fourth Circuit, 2020)
Gibson v. Epting
827 S.E.2d 178 (Court of Appeals of South Carolina, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
East Coast Storage Equipment Co Inc v. ZF Transmissions Gray Court LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/east-coast-storage-equipment-co-inc-v-zf-transmissions-gray-court-llc-ca4-2025.