AlleN, J.

The first question to be settled is whether the North Carolina Railroad Company has acquired a right of way 100 feet wide on each side of its main track over the land in controversy, because if it has not done so, the Southern Railway Company, which derives its powers under a lease from the North Carolina Company, has no such right of way.

It must be remembered, in -the consideration of this question, that there is no evidence that the double track, as now laid, invades any house or yard as it existed in 1850 to 1851, nor that it invades the. dwelling or yard of the plaintiff.

Section 27 of the charter of the North Carolina Company relates wholly to the acquisition of a right of way by condemnation proceedings, and of course a right of way could be acquired by deed or contract from the owner.

By section 29 it is intended to provide for cases where there has been no condemnation proceeding, and evidence of the consent of the owner has been lost or cannot be produced, and it says that, in the absence of contract, there arises a presumption of a grant from the owner for the land on which the road is located, together with a space of 100 feet on each side of the center of the track, and if the owner fails to claim compensation for such right of way within two years after the road is finished over his land, he is barred.

Provisions like these cannot be construed in the light of conditions as they exist to-day, .but as they were when the charters were granted. As was well said by Justice Connor, in R. R. v. Olive, 142 N. C., 273 : “The point of view from which charters for railroads were drawn in this State fifty years ago must not be lost sight of in construing them in the light of present condi *363 tions. If, to induce the investment of capital in tbe construction of railroads and development of tbe country, large privileges were conferred, not inconsistent with the exercise of the sovereign power of the State in controlling them, we may not construe them away without doing violence to sound principle and fair dealing. When these rights of way were granted, or statutes enacted permitting their acquisition in the exercise of the right of eminent domain, it was contemplated that they should be of sufficient width to enable the company to safely operate the road and protect the adjoining lands from fire communicated by sparks emitted by the engines. Land was cheap and population sparse. The railroads, as the charters show, were to be built by the citizens of the State, the capital stock to be subscribed by large numbers of people; Legislatures were ready to make broad concessions to these domestic corporations, and, as shown by the record in this and other cases in this Court, the owners of lands, because the 'benefits which will arise from the building of said railroads to the owners of the land over which the same may be constructed, will greatly exceed the loss which may be sustained by them,’ were desirous to promote the building thereof, and to that end to give them rights of way over their lands. When the road has been constructed and the benefits enjoyed, although new and unexpected conditions have arisen, the rights granted may not be withdrawn, although the. long-deferred assertion of their full extent may work hardship.”

The effect of inaction on the part of the owner for a period of two years after the completion of the road has been considered in several cases in this Court, under charters similar to the one before us, and without difference of opinion, it has been held that under such circumstances, a presumption of a grant from t.he owner arises for the land on which the road is located and for the right of way provided for in the charter.

In R. R. v. McCaskill, 94 N. C., 751, Chief Justice Smith, discussing this question, says: “In whomsoever the estate was vested, there being no suggestion that they were under disabilities, it was, under the statute, as soon as the road was constructed, and toties quoties as it progressed towards conclusion, transferred to the corporation, of the required width of 100 feet *364 on either side, to be paid for as directed, when no written contract has been entered into for the purchase. In such case the inaction of the owner in enforcing his demand for compensation for land taken and appropriated after the finishing of the construction of the road thereon, for the space of two years thereafter, raises, under the statute, a presumption of a conveyance and of satisfaction, and hence becomes a bar to an assertion by legal process, of such claim. . . . The presumption of the conveyance arises from the company’s act in taking possession and building the railway, when in the absence of a contract the owner fails to take steps, for two years after it has been completed, for recovering compensation. It springs out of these concurring facts, and is independent of inferences which a jury may draw from them. If the grant issued, it would not be more effective in passing the owner’s title and estate. Thus vesting, it remains in the company as long as the road is operated, of the specific breadth, unaffected by the ordinary rules in reference to repelling presumptions.”

This statement of the law, as modified by R. R. v. Sturgeon, 120 N. C., 225, has been approved in R. R. v. Olive, 142 N. C., 272; Parks v. R. R., 143 N. C., 293; R. R. v. New Bern, 147 N. C., 168; Muse v. R. R., 149 N. C., 446, and in other cases.

Speaking of the effect of the Sturgeon case, Justice Connor said in Barker v. R. R., 137 N. C., 220: “It is there held that under similar conditions, construing the same language, the road acquired, not a title to the land, but an easement which entitles it to possession of the whole right of way only when it shall appear that it is necessary for its purposes in the conduct of its business. "We do not understand that in any of the decisions of this Court the doctrine of McCaskill’s case has been otherwise modified.”

It will be noted that the presumption does not arise except in the absence of a contract, and it may be that where permanent structures have been erected by the owner of the land, within 100 feet of the main line, and have been used for a long time without objection, and also in localities where it is customary to acquire rights of way by purchase, less in width than 100 feet, that the presumption would not arise when neither party introduces any evidence that there was no contract.

*365 It is also intimated in McGashill’s case and in Gudger v. R. R., 106 N. C., 484, tbat there may be a recovery for permanent improvements, made without objection, and in good faith, in the event the right of way is taken for the use of the railroad.

These questions are not, however, before us on this appeal.

■ It follows, therefore, that there is a presumption that the then owner of the land granted to the North Carolina Eailroad a right of way over the land in controversy, and if so, the subsequent use of the land by the owner or by those who claim under him, as shown by the evidence in this case, could not affect the right.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Charlotte v. BMJ OF CHARLOTTE, LLC
675 S.E.2d 59 (Court of Appeals of North Carolina, 2009)
Keziah v. Seaboard Air Line Railroad Company
158 S.E.2d 539 (Supreme Court of North Carolina, 1968)
R. R. v. . Manufacturing Co.
51 S.E.2d 301 (Supreme Court of North Carolina, 1949)
Carolina & Northwestern Railway Co. v. Piedmont Wagon & Manufacturing Co.
229 N.C. 695 (Supreme Court of North Carolina, 1949)
Southern Railway Co. v. Lissenbee
13 S.E.2d 561 (Supreme Court of North Carolina, 1941)
Powell v. Hamlet Ice Co.
183 S.E. 386 (Supreme Court of North Carolina, 1936)
Wearn v. . R. R
132 S.E. 576 (Supreme Court of North Carolina, 1926)
Wearn v. North Carolina Railroad
191 N.C. 575 (Supreme Court of North Carolina, 1926)
Griffith v. Southern Railway Co.
131 S.E. 413 (Supreme Court of North Carolina, 1926)
Norfolk Southern R. v. Stricklin
264 F. 546 (E.D. North Carolina, 1920)
Atlantic Coast Line Railroad v. Bunting
84 S.E. 1009 (Supreme Court of North Carolina, 1915)
Coit v. Owenby-Wofford Co.
81 S.E. 1067 (Supreme Court of North Carolina, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
72 S.E. 1062, 157 N.C. 358, 1911 N.C. LEXIS 54, Counsel Stack Legal Research, https://law.counselstack.com/opinion/earnhardt-v-southern-railway-co-nc-1911.