This text of 322 P.2d 810 (Earl E. Roher Transfer & Storage Co. v. Hutchinson Water Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Earl E. Roher Transfer & Storage Co. v. Hutchinson Water Co., 322 P.2d 810, 182 Kan. 546, 1958 Kan. LEXIS 272 (kan 1958).

Opinion

The opinion of the court was delivered by

Robb, J.:

These actions were commenced separately and in each case an appeal was taken from an order of the trial court sustaining a demurrer of appellee filed against the petition of appellant. This court ordered consolidation of the appeals for consideration here.

The parties will hereafter be referred to as plaintiff and defendant, and we will refer to the petitions in the singular since they are identical with the exception of the name and capacity of the parties plaintiff and the element of damages.

The pertinent portions of the petition may be summarized as follows:

On September 12, 1950, the qualified voters of the city of Hutch *547 inson approved ordinance No. 3361 granting a franchise to defendant to operate a water plant for the city and to furnish water thereto; plaintiff was a citizen and taxpayer of the city and was thereby entitled to the rights and benefits enumerated under the contract between the city and the defendant; section 5 of the ordinance above referred to provides that “The grantee . . . shall maintain its water supply and system ... so that there shall be available for fighting fires the number of hose streams (with pressure of not to exceed 115 pounds at the pump discharge at its central pumping plant) as determined by the following formula:

“The number of fire streams shall be 2.8 times the square root of the population of the City in thousands. Fire streams in the business district shall be construed to mean the discharge of 240 to 250 gallons per minute. ... Of the total number of fire streams as figured by the above formula not less than two-thirds of the number shall be considered as available to play on a single block in the mercantile district . . .
“Fire pressures within the area covered by the gridironed portion [network of pipes] of the water distribution system will be ninety pounds per square inch for the mercantile districts ... as measured at the fire hydrants when the required number of fire streams are in play.”

The petition further alleged:

Plaintiff’s property was located in the mercantile district and defendant was obligated to furnish plaintiff with ninety pounds of water pressure; on July 18, 1954, through no fault of plaintiff, fire broke out on plaintiff’s property; the city fire department arrived in due time but was hindered in its attempts to extinguish the fire because of the failure to have sufficient water supply and pressure; at the time of the fire, ninety pounds of water pressure per square inch was not provided but only sixty to seventy pounds of pressure was available when the fire department began fighting the fire, and after a few minutes the pressure dropped to forty pounds where it remained until the fire was finally extinguished; because of defendant’s failure, the fire department could not utilize its equipment to its practical advantage; plaintiff thereby sustained damage far in excess of any amount he would have sustained had the pressure been what defendant was obligated to furnish under the contract; defendant had knowledge of the inadequate water supply and pressure to the fire hydrants; it had been constantly brought to defendant’s attention, and defendant had negligently failed to remedy the situation. Defendant’s negligence in failing to maintain the water supply and pressure was the proximate cause of plaintiff’s damage. The remainder of the petition had to do with damages.

*548 The ordinance under consideration was made a part of the petition by stipulation. The salient parts thereof read:

“Section 1. That in consideration of the benefits to the City of Hutchinson, Kansas, and its inhabitants . . . there is hereby granted to the Hutchinson Water Company, Inc., . . . the right ... to supply the City of Hutchinson, Kansas, and the inhabitants thereof with water for all purposes for which water may be used . . . and . . . for all purposes for which water is furnished, distributed, sold, and used, all upon the terms and conditions hereinafter set forth.
“Section 3. That the City does hereby agree to pay for the use of fire hydrants and for water required for municipal fire protection . . . That all public fire hydrants shall be used exclusively for the extinguishment of fires, necessary drill and practice of the Fire Department, the flushing of city streets, sewers, and gutters, and other public or private uses approved by the Chief of the Fire Department, and the Hutchinson Water Company, Inc., . . . but all uses of fire hydrants in the City of Hutchinson shall be under the direction and supervision of the Chief of the Fire Department . . .
“Section 4. That as consideration for the rights and privileges granted herein, the Hutchinson Water Company, Inc., binds and obligates itself, its successors and assigns, during the full term of this ordinance, to furnish the City of Hutchinson, Kansas, and its inhabitants, water, upon the terms and conditions stated in this ordinance . . .
“Section 8. The Hutchinson Water Company, Inc,, hereby agrees to save the City of Hutchinson, Kansas, harmless from any liability, loss, damage, or expense which it may sustain by reason of the grantee’s negligence, default, or misconduct in the construction, operation, or maintenance of its water system.
“Section 13. That the Hutchinson Water Company, Inc., within thirty days after the passage, approval, and publication of this Ordinance file with the City Clerk its written acceptance of this franchise, whereupon the same shall become and be a binding contract between the City of Hutchinson, Kansas, and the Hutchinson Water Company, Inc., its successors or assigns; otherwise this grant shall be null and void.”

At this point in the proceedings the defendant demurred on the ground the petition did not state facts sufficient to constitute a cause of action against defendant and in favor of plaintiff. The trial court, in sustaining the demurrer to the petition, wrote an extensive and comprehensive memorandum opinion wherein many decisions from foreign jurisdictions were cited and discussed, as well as three Kansas cases. Plaintiff thereafter perfected this appeal.

The parties are in accord that this is an action in contract; Plaintiff cites authority from other jurisdictions holding that watef companies are liable under situations like the one involved here but such authorities are admittedly in the minority. Kansas has fol *549 lowed the majority rule, which was pronounced in Mott v. Water Co., 48 Kan. 12, 28 Pac. 989, as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

– GFTLenexa, LLC v. City of Lenexa –
453 P.3d 304 (Supreme Court of Kansas, 2019)
Byers v. Snyder
237 P.3d 1258 (Court of Appeals of Kansas, 2010)
Weinberg v. Dinger
524 A.2d 366 (Supreme Court of New Jersey, 1987)
Stewart v. Arrington Construction Company
446 P.2d 895 (Idaho Supreme Court, 1968)
Davis v. Nelson-Deppe, Inc.
424 P.2d 733 (Idaho Supreme Court, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
322 P.2d 810, 182 Kan. 546, 1958 Kan. LEXIS 272, Counsel Stack Legal Research, https://law.counselstack.com/opinion/earl-e-roher-transfer-storage-co-v-hutchinson-water-co-kan-1958.