Eagleford Recycling Services, LLC

CourtUnited States Bankruptcy Court, M.D. Florida
DecidedAugust 3, 2023
Docket8:21-bk-05810
StatusUnknown

This text of Eagleford Recycling Services, LLC (Eagleford Recycling Services, LLC) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, M.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eagleford Recycling Services, LLC, (Fla. 2023).

Opinion

ORDERED. Dated: August 03, 2023

Catherine Peek McEwen United States Bankruptcy Judge

UNITED STATES BANKRUPTCY COURT MIDDLE DISTRICT OF FLORIDA TAMPA DIVISION www.flmb.uscourts.gov In re: Case No. 8:21-bk-05810-CPM Chapter 11 Eagleford Recycling Services, LLC, Debtor. eS MEMORANDUM OPINION ON PREJUDGMENT INTEREST RATE In determining whether there is a triable issue concerning the applicable interest rate for a claim in this case, the Court must predict how the Texas Supreme Court would interpret Texas statutory law on construction payment disputes. Under the Texas Prompt Payment Act (“TPP Act”), which generally incentivizes owners to promptly pay contractors for properly performed work, “unpaid amount|[s] required under the Act” accrue prejudgment interest at 18 percent per annum.! The ultimate

' Tex. Prop. Code § 28.004 (2015) (emphasis added).

question for the Court in the present case is when an unpaid amount is required, so as to accrue interest at the 18 percent rate. In this case, PetroSwift, LLC has filed a $428,503.93 proof of claim arising out

of a Texas state court “Agreed Judgment.” One, by the way, that was not agreed to by the Debtor, as the judgment deals only with liability to PetroSwift by another party to the same action. The judgment is for amounts due on a construction contract. In its proof of claim, PetroSwift seeks prejudgment interest at 18 percent under the TPP Act and as included in its final judgment. The Debtor has objected

because it says the TPP Act does not subject to interest accrual at 18 percent amounts withheld because of a good-faith dispute. PetroSwift now asks the Court to determine that it is entitled to prejudgment interest at 18 percent under the Act as a matter of law.2 At this point, you may be wondering how this Court has authority to review a

state court judgment. The Court wondered similarly, as it must.3 After all, doesn’t the Rooker-Feldman doctrine bar federal courts from reviewing state court judgments?4 The Eleventh Circuit has made clear that Rooker-Feldman applies only if the state

2 Doc. No. 132. 3 Am. Civil Liberties Union of Fla., Inc. v. Dixie County, Fla., 690 F.3d 1244, 1249 (11th Cir. 2012) (quoting Hallandale Prof’s Fire Fighters Local 2238 v. City of Hallandale, 922 756, 759 (11th Cir. 1991)). 4 Behr v. Campbell, 8 F.4th 1206, 1212 (11th Cir. 2021) (“To whatever extent we have not been clear enough before, we aim to be now. Rooker-Feldman means that federal district courts cannot review or reject state court judgments rendered before the district court litigation began.”). court proceeding has ended before the federal court proceeding began.5 Here, the state court proceeding has not ended. Under Texas law, a final judgment is “final” for appellate purposes only if it actually disposes of all parties and all claims in the

proceeding or expressly states that it disposes of all parties and all claims even if it does not actually do so.6 The agreed final judgment here does not dispose of all claims between all parties (nor does it say it does). Indeed, PetroSwift concedes that it has unadjudicated fraudulent transfer claims pending in the Texas state court proceeding.7

Because the Texas state court proceeding has not ended, Rooker-Feldman does not apply. And of course, given that Rooker-Feldman is no bar to the exercise of jurisdiction over this dispute, the resolution of an objection to a proof of claim is well within the Court’s jurisdiction over bankruptcy cases and disputes arising under the

Bankruptcy Code.8 Thus, this Court may consider whether PetroSwift is entitled to prejudgment interest at 18 percent under the TPP Act.

5 Id. (explaining that Rooker-Feldman “bars only ‘cases brought by state-court losers complaining of injuries caused by state-court judgments rendered before the district court proceedings commenced and inviting district court review and rejection of those judgments’”) (quoting Exxon Mobil Corp. v. Saudi Basic Indus. Corp., 544 U.S. 280, 284 (2005)) 6 Lehmann v. Har-Con Corp., 39 S.W.3d 191, 195, 200 (Tex. 2001), superseded by statute on other grounds as recognized by Indus. Specialists, LLC v. Blanchard Refin. Co., 652 S.W.3d 11, 14 –15 (Tex. 2022). 7 Doc. No. 132, p. 17 (“The only unadjudicated relief in the Texas Action were [. . .] the fraudulent transfer claims.”) 8 28 U.S.C. § 1334(b); 28 U.S.C. § 157(b)(2)(B). Sections 28.002 and 28.003 of the TPP Act create an exception to the general rule that owners must promptly pay contractors: owners are entitled to withhold from payment any amount that is subject to a good-faith dispute. Because an amount

that is subject to a good-faith dispute is not required to be paid under the TPP Act, it is not yet due and thus does not accrue prejudgment interest at 18 percent — even if it is later found to be owing to the contractor. PetroSwift has failed to demonstrate as a matter of law that the amount owed on its final judgment was not the subject of a good-faith dispute. Therefore, the Court cannot determine that PetroSwift is entitled

to prejudgment interest at 18 percent as a matter of law. I. Background Sometime before April 2015, Dewitt Recyclable Products (“DRP”) was permitted by the Railroad Commission of Texas to operate an oilfield waste disposal facility.9 In April 2015, DRP contracted with PetroSwift to construct the facility on

property it owned in Cuero, Texas.10 Between June 2015 and February 2016, PetroSwift invoiced DRP a total of $783,754.06 for its work on the project.11 DRP paid the invoiced amount in full. But, according to DRP, as the project was nearing completion in late spring or early summer 2016, PetroSwift walked off the job.12

9 Doc. No. 130-4, p. 3 at ¶ 5. 10 Id. p. 3 at ¶¶ 4 – 6. 11 Doc. No. 130-3, Ex. B. 12 Doc. No. 130-4, ¶ 6; Aff. of David Elks, Doc. No. 135, ¶¶ 2 – 8; Decl. of Stephanie Kleinecke, Doc. No. 135, ¶¶ 2 – 9. DRP also believed there was an issue with some of PetroSwift’s work.13 So DRP refused to pay the final three invoices, which totaled $205,444.39.14 When DRP refused to pay, PetroSwift recorded a mechanic’s and

materialmen’s lien against the property and later sued DRP in Texas state court to foreclose the mechanic’s lien and recover damages for breach of contract and open account.15 DRP counterclaimed for breach of contract and breach of the Texas Deceptive Trade Practices Act.16 While the action was pending, the property was transferred three times — first

to Jim Wright and then to Cuero Land Management, LLC, then ultimately to the Debtor.17 Both Cuero Land Management and the Debtor intervened in the lien foreclosure action and asserted claims against PetroSwift.18 Those claims were largely predicated on the same allegations: PetroSwift built the main waste-receiving pit using only half as much rebar as provided for in the engineering drawings; and

PetroSwift failed to adequately wet and vibrate the concrete, causing damages to the waste receiving pit.19 Ultimately, the Texas state court disposed of Cuero Land

13 Decl. of Stephanie Kleinecke, Doc. No. 135, ¶¶ 2 – 9. 14 Id. ¶¶ 2 – 9; Doc. No. 130-3, Ex. B. 15 Doc. Nos. 130-2 & 130-3. 16 Doc. No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nicole Loren v. Charles M. Sasser, Jr.
309 F.3d 1296 (Eleventh Circuit, 2002)
Exxon Mobil Corp. v. Saudi Basic Industries Corp.
544 U.S. 280 (Supreme Court, 2005)
Martinez v. Hutton (In Re Harwell)
628 F.3d 1312 (Eleventh Circuit, 2010)
Daniel C. Greer v. United States
207 F.3d 322 (Sixth Circuit, 2000)
Lehmann v. Har-Con Corp.
39 S.W.3d 191 (Texas Supreme Court, 2001)
Samuel Troice v. Proskauer Rose, L.L.P., et
816 F.3d 341 (Fifth Circuit, 2016)
Jodie Kelly v. Paul Rembach
868 F.3d 371 (Fifth Circuit, 2017)
Mark Silguero and Amy Wolfe v. Csl Plasma, Incorporated
579 S.W.3d 53 (Texas Supreme Court, 2019)
Rebekka Anne Behr v. James Campbell
8 F.4th 1206 (Eleventh Circuit, 2021)
Vast Construction, LLC v. CTC Contractors, LLC
526 S.W.3d 709 (Court of Appeals of Texas, 2017)
Troice v. Greenberg Traurig, L.L.P.
921 F.3d 501 (Fifth Circuit, 2019)
LSQ Funding Group, L.C. v. EDS Field Services
879 F. Supp. 2d 1320 (M.D. Florida, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Eagleford Recycling Services, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eagleford-recycling-services-llc-flmb-2023.