Eagle Water, LLC v. Arch Ins. Co.

360 F. Supp. 3d 426
CourtDistrict Court, W.D. Louisiana
DecidedDecember 28, 2018
DocketCIVIL ACTION NO. 17-250
StatusPublished
Cited by3 cases

This text of 360 F. Supp. 3d 426 (Eagle Water, LLC v. Arch Ins. Co.) is published on Counsel Stack Legal Research, covering District Court, W.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eagle Water, LLC v. Arch Ins. Co., 360 F. Supp. 3d 426 (W.D. La. 2018).

Opinion

ELIZABETH ERNY FOOTE, UNITED STATES DISTRICT JUDGE

Currently pending before the Court is a motion for summary judgment filed by the Defendant, Arch Insurance Company ("Arch"). [Record Document 30]. After a review of the motion, opposition, reply, and supplements thereto filed by the parties, and for the following reasons, Arch's motion for summary judgment shall be GRANTED .

FACTS

The facts giving rise to this insurance dispute are fairly straightforward. Plaintiff, Eagle Water, LLC ("Eagle Water"), owns a sewer system that services the Kingston Plantation neighborhood in Bossier City, Louisiana. Record Document 1-2, p. 3. For that sewer system, Eagle Water secured insurance from Arch. Record Document 32, pp. 6-7.

On January 5, 2016, a localized sewer collapse occurred near a manhole in Kingston Plantation. Record Document 30-2, p. 1. In addition to the collapsed manhole, Eagle Water discovered a sinkhole in a homeowner's yard. Record Document 32, p. 4. Eagle Water hired Pulley Construction to repair the sewer system. Record Document 32-3, p. 1. It also notified Arch of the situation, and Arch sent an adjustor to the site. Record Document 32-1, p. 3. Over the following seven to eight months, Pulley Construction excavated streets, driveways, sidewalks, and yards in order to install a bypass pump system and prevent sewage backup into any of the residences in the neighborhood. Id. at pp. 2-3, 6. Pulley Construction's work also involved repairing sewer mains and excavating and replacing the sunken manhole. Record Document 30-1, pp. 10-11. Eagle Water paid Pulley Construction $ 608,952.19 to perform this work. Record Document 32-1, p. 1. An engineer hired by Eagle Water represented that if the bypass system had not been installed, "there may have been" (1) a backup of raw sewage into the homes served by the affected manhole; (2) a raw sewage spill onto lawns; and/or (3) raw sewage that spilled into the storm sewer system and consequently into Willow Chute Bayou. Id. at p. 6.

*428In August of 2016, Arch denied Eagle Water's claim for reimbursement, and this suit followed. Eagle Water seeks a declaratory judgment that coverage exists under the insurance contract; recovery of the $ 608,952.19 it paid Pulley Construction for measures that prevented and/or minimized the damages Arch would have had to pay otherwise; and attorney's fees, costs, and penalties. Arch filed the instant motion for summary judgment contending no coverage exists for Eagle Water's repair work in Kingston Plantation. Eagle Water opposes that motion, submitting that while coverage is not guaranteed under the plain language of the contract, persuasive jurisprudence compels the conclusion that coverage should not be barred under the circumstances of this case.

Based upon the briefing, it is clear to the Court that Arch does not necessarily dispute that Eagle Water's actions prevented the backup and/or spillage of sewage. Rather, as a factual matter, it disputes whether all of Pulley Construction's work was designed to address the initial manhole collapse or, instead, whether the scope of the project expanded over time to address other issues. The resolution of those factual disputes is not material, however, as this case turns on the legal question of whether coverage exists under the terms of the governing insurance contract.

LAW AND ANALYSIS

Federal Rule of Civil Procedure 56(a) directs that a court "shall grant summary judgment if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law."1 Summary judgment is appropriate when the pleadings, answers to interrogatories, admissions, depositions and affidavits on file indicate that there is no genuine issue of material fact and that the moving party is entitled to judgment as a matter of law. See Celotex Corp. v. Catrett, 477 U.S. 317, 322, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). When the burden at trial will rest on the non-moving party, the moving party need not produce evidence to negate the elements of the non-moving party's case; rather, it need only point out the absence of supporting evidence. See id. at 322-323, 106 S.Ct. 2548.

Once the movant carries its initial burden, it is incumbent upon the non-moving party to demonstrate the existence of a genuine dispute as to a material fact. See Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 106 S.Ct. 1348, 89 L.Ed.2d 538 (1986) ; Wallace v. Texas Tech. Univ., 80 F.3d 1042, 1047 (5th Cir. 1996) (citations omitted). If the motion is properly made, however, Rule 56(c) requires the nonmovant to go "beyond the pleadings and designate specific facts in the record showing that there is a genuine issue for trial." Wallace, 80 F.3d at 1047 (citations omitted). This burden is not satisfied with some metaphysical doubt as to the material facts, by conclusory or unsubstantiated allegations, or by a mere scintilla of evidence. See Little v. Liquid Air Corp., 37 F.3d 1069, 1075 (5th Cir. 1994) (citations omitted). However, "[t]he evidence of the non-movant is to be believed, and all justifiable inferences are to be drawn in his favor." Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 255, 106 S.Ct. 2505

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
360 F. Supp. 3d 426, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eagle-water-llc-v-arch-ins-co-lawd-2018.