EAGLE PLUMBING, HEATING & AIR CONDITIONING, INC. v. Ragusa

517 So. 2d 280, 1987 WL 1483
CourtLouisiana Court of Appeal
DecidedNovember 10, 1987
DocketCA 86 1255
StatusPublished
Cited by4 cases

This text of 517 So. 2d 280 (EAGLE PLUMBING, HEATING & AIR CONDITIONING, INC. v. Ragusa) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
EAGLE PLUMBING, HEATING & AIR CONDITIONING, INC. v. Ragusa, 517 So. 2d 280, 1987 WL 1483 (La. Ct. App. 1987).

Opinion

517 So.2d 280 (1987)

EAGLE PLUMBING, HEATING & AIR CONDITIONING, INC.
v.
Michael RAGUSA and Ambulatory Hospitals of America, Inc.

No. CA 86 1255.

Court of Appeal of Louisiana, First Circuit.

November 10, 1987.

James A. Dukes, Hammond, for plaintiff-appellee.

Anne E. Tate, New Orleans, for defendant—Ambulatory Hospitals of America, Inc.—appellant.

Iddo Pittman Jr., Hammond, for defendant, Michael Ragusa, appellee.

Before WATKINS, CARTER and CHIASSON,[*] JJ.

*281 CHIASSON, Judge.

This suit arises out of a contract to renovate a building in Covington, Louisiana owned by Covington Surgery Center (CSC) for use as an outpatient surgery facility. CSC is a limited partnership with Ambulatory Hospitals of Louisiana, Inc. (Ambulatory) as a general partner in CSC. CSC contracted with defendant Michael Ragusa as general contractor for renovation of the building by contract dated June 19, 1984. The general contract was recorded in the mortgage records of St. Tammany Parish. The general contract contemplated Ragusa's use of subcontractors and specifically provided for reimbursement to Ragusa for payments to subcontractors.

Plaintiff-appellee, Eagle Plumbing, Heating and Air Conditioning, Inc. (Eagle), was a subcontractor to Ragusa for certain plumbing, air conditioning and heating work on the CSC facility. Eagle's bid on the job was addressed to Michael Ragusa as general contractor, and was signed by Buster Smith for Eagle and by "Gregory W. Hunter/MAR" on behalf of Ragusa. Various change orders were attached to the contract and these orders are addressed to Ragusa and bear the same signatures as the contract between Eagle and Ragusa. All invoices pertaining to this job submitted by Eagle were addressed to Ragusa and all payments that Eagle received were by checks drawn on the account of Ragusa.

At some point prior to completion of its work under the sub-contract with Ragusa, Eagle became concerned that Ragusa's payments to Eagle were falling behind. Charles Smith, a vice president of Eagle, telephoned Clifton Thomason, a vice president of Ambulatory, concerning this problem. Thomason was the architect on the project and the representative of the owner with whom Eagle had had previous contacts in interpreting the construction requirements. Eagle was satisfied after this conversation that they would be paid and completed performance of its subcontract on the project. Eagle relied on this conversation, and the trial court interpreted it as the basis for a "new, primary contract" between Ambulatory and Eagle.

Renovation of the surgery center was substantially completed on October 21, 1984, and a certificate of substantial completion was executed on that date. The certificate included the owner's formal acceptance of the project and was recorded with the St. Tammany Recorder of Mortgages on October 22, 1984.

On December 10, 1984, more than thirty (30) days after recorded acceptance of the project, the Recorder of Mortgages for St. Tammany Parish issued a clear lien and privilege certificate for the property. Ragusa executed an affidavit that all debts and claims on the construction project had been paid and an affidavit of release of liens on December 14, 1984. He then forwarded to Ambulatory an application and certificate for final payment dated December 18, 1984 and was paid by Ambulatory on January 10, 1985.

Despite Ragusa's sworn statement in the contractor's Affidavit of Payment of Debts and Claims, Eagle had apparently not been paid in full on its subcontract. Eagle therefore filed suit against Ragusa and Ambulatory on May 2, 1985. In its petition Eagle relied on its subcontract as a basis for its claim against Ragusa.

The petition states that Ambulatory was joined "because the contract entered into by said defendant, AHA, Inc., stated at Sec. 1.06 Subsection 5, Paragraph 6, that they would not make any final payment to the general contractor without a signed release of lien from every subcontractor and separate contractor who particiated in the job." The petition further stated that Eagle had signed no release of lien, but believed that full payment was made to the contractor without such release, "contrary to the specific terms of their contract."

It is undisputed that Ragusa did not obtain a release of lien from Eagle and that Ambulatory paid Ragusa in full. It is also undisputed that Eagle never filed any lien against the project for which Ambulatory could have required a release. At the time of Ragusa's application for final payment, the statutory period for filing liens had *282 expired and the Recorder of Mortgages certificate showed that no liens had been filed. There were therefore no subcontractor liens to be released. Ragusa filed for relief in the United States Bankruptcy Court on November 18, 1985, more than a year after completion of the project and six months after suit was filed.

After answering, Ambulatory filed a motion for summary judgment asserting that (1) Eagle had no cause of action against Ambulatory on the basis of a provision in the general contract between Ambulatory and Ragusa to which Eagle was not a party; (2) Eagle could not satisfy the requirements for showing a stipulation pour autrui in the general contract; and (3) Eagle's only potential rights against the owner of the construction project would have been under the Private Works Act, La.R.S. 9:4801, et seq. and Eagle failed to perfect any such rights. In support of its motion for summary judgment, Ambulatory filed the affidavit of Clifton Thomason, Vice President for Ambulatory, with attached exhibits. At the hearing on the motion for summary judgment on February 28, 1986, the affidavit of Clifton Thomason with the attached exhibits was introduced into and accepted into evidence. The affidavit of Charles Smith filed on behalf of Eagle the day of the hearing, was also accepted into evidence. At the close of the hearing, the court denied Ambulatory's motion for summary judgment and the matter remained set for trial on March 17, 1986.

On March 18, 1986, the matter was tried before the Honorable Thomas W. Tanner. Plaintiff presented the testimony of Charles H. Smith (Smith) and Owen Jordan (Jordan) and filed into evidence in connection with that testimony various invoices and evidence of payment, found in the record at pages 5 through 19. Defendant placed in evidence the testimony of Clifton Thomason (Thomason) and introduced into evidence in connection with that testimony two additional exhibits, the application and certificate for payment by the general contractor and the Ambulatory check for final payment to that contractor.

At the close of trial, the judge took the matter under advisement. On June 12, he filed reasons for judgment finding "a new, primary contract between the owner and Eagle Plumbing" and casting Ambulatory in judgment in the amount of $18,525.50, with interest from the date of judgment.

ASSIGNMENTS OF ERROR

Appellant, Ambulatory, contends that the trial court erred in:

1. finding that a "new, primary contract" had been confected between Ambulatory and Eagle;

2. holding Ambulatory liable to Eagle; and

3. alternatively, the trial court's assessment of quantum is not supported by the evidence and is manifestly erroneous.

In an action based on contract, the plaintiff must establish the elements of a contract by proving an offer, an acceptance and a meeting of the minds of the parties on the terms of the contract. LSA-C.C. art. 1927. In the instant case Eagle does not rely on any writing in support of the alleged contract between Ambulatory and Eagle.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shaw v. Restoration Hardware
93 F.4th 284 (Fifth Circuit, 2024)
Chaisson v. Chaisson
690 So. 2d 899 (Louisiana Court of Appeal, 1997)
Newt Brown, Contractor, Inc. v. Michael Builders, Inc.
569 So. 2d 288 (Louisiana Court of Appeal, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
517 So. 2d 280, 1987 WL 1483, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eagle-plumbing-heating-air-conditioning-inc-v-ragusa-lactapp-1987.