Eagle Iron Works Co. v. Franklin County Collieries Co.

180 Ill. App. 76, 1913 Ill. App. LEXIS 740
CourtAppellate Court of Illinois
DecidedApril 23, 1913
StatusPublished

This text of 180 Ill. App. 76 (Eagle Iron Works Co. v. Franklin County Collieries Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eagle Iron Works Co. v. Franklin County Collieries Co., 180 Ill. App. 76, 1913 Ill. App. LEXIS 740 (Ill. Ct. App. 1913).

Opinion

Mr. Presiding Justice McBride

delivered the opinion of the court.

The Circuit Court of Franklin county rendered a decree in favor of the complainant herein, and to reverse such decree the defendant prosecutes this appeal. On September 5, 1907, complainant filed its bill for mechanic’s lien in the office of the clerk of the Circuit Court of Franklin county) alleging that it was a contractor and builder and that on October 8, 1906, the defendant, Franklin County Collieries Company, entered into a contract with appellee for the erection of certain machinery upon the S. W. 14 of the N. E. 14 of section 19, T. 5 S., B. 2 E. of the third principal meridian in Franklin county, and that one Theodore C. Keller was at the time the owner of said lands and of a majority of the stock in said defendant corporation. The bill further alleges that in pursuance of said contract the complainant did erect for the defendants on said premises one pair of double pivoted self dumping cages, one dumping chute, one weigh hopper, one double deck shaking screen, one eccentric shaft, one twenty-five horse power engine, one four compartment receiving hopper, one bar screened with apron, slack hopper for mine run chute, one wagon chute, one bar screened with aprons, slack hopper for wagon chute; that the defendant Franklin County Collieries Company agreed to pay therefor $3,800, one-third when the machinery was shipped, one-third when erected and ready for operation, and the balance in 45 days thereafter. That the defendant on the 5th day of August, 1907, took possession of said machinery and has used the same ever since; that defendant has paid to complainant the sum of $500 upon said contract and that there is a balance due of $3,291, with interest. That on December 25, 1907, defendants filed an answer to said bill admitting that the defendant corporation entered into a contract with the complainant for the erection of said machinery but denies that the complainant built and completed the said machinery according to the terms of said contract, and avers that the machinery was planned and designed by the complainant for the purpose of caring for coal hoisted from defendant’s mine and that the complainant prepared all of the details of said work and assumed the responsibility therefor. That the complainant without any fault of defendants failed to complete such equipment according to the terms and conditions of said contract, and that the equipment furnished by the complainant was so inadequate and imperfect as to be incapable of use and that it would be necessary for defendants to remove such equipment and place new machinery therein. That the complainant by its said contract guarantied the material, workmanship and operation of the machinery to be first-class and that it was not in compliance with said guarantee, not adapted to the purposes for which it was erected and that by reason of the failure of complainant to comply with its contract in the erection of said machinery the defendant has been greatly damaged, and denies that the defendant is indebted to the complainant and asks that an account may be taken of the damages sustained by the defendant and a decree rendered against complainant for such amount, and denies thiit it is in any manner indebted to the complainant.

Thereafter the defendants filed a cross-bill in said cause alleging substantially the same matters as are set forth in the answer and asks the court to direct an accounting of the damages sustained by it and for a decree in its favor. Thereupon the cause was referred to the master in chancery to take the testimony, which was taken by the master and reported to the court at a later term. Thereafter the defendants procured a change of venue from the judges of said circuit. On December 15, 1910, the defendant entered a motion to amend its answer by averring that the complainant was a foreign corporation and not authorized to transact business or bring suit in Illinois upon contracts entered into in said state, and averring'that such contract was entered into in the state of Illinois. Objections were made to the allowance of said amendment and the matter was taken under advisement by the court. Afterwards on June 15, 1911, a stipulation was entered into and filed by the parties to this suit asking that the order for change of venue heretofore made be set aside and that the presiding judge, Honorable W. H. Oreen, decide the case upon the record as made and render such decree as in Ms judgment should be made therein. That afterwards on December 15, 1911, a similar agreement was entered into between the parties with reference to a hearing and decision upon the evidence that had been taken and reported by the master, and agreeing that said cause should be taken and determined by the Honorable E. E. Newlin, presiding judge.

It is claimed that the court erred in not dismissing complainant’s bill because the complainant was a foreign corporation and had not taken proper steps to authorize it to transact business in Illinois.

We are of the opinion that according to the facts as stated in the stipulation filed in tMs case the plaintiff does not come within the rule which proMbits foreign corporations from transacting business or exercising its corporate powers in this state.

Many errors have been assigned herein but under the view we take of this ease it is only necessary to consider the errors pertaining to the question of the right of complainant to recover the full amount of its claim, its failure to complete its contract according to agreement, the right of defendant to recoup damages, and the right of the court to dismiss defendants’ cross-bill. As the solution of these questions depends upon our view of the evidence, they will all be considered and determined together.

It is admitted that the contract upon which this action is based was prepared by the agents of the complainant, after consultation with the agents of the defendant corporation. In the negotiations leading up to the making of the contract, and in the performanee of it, George Parker represented the complainant and T. O. Keller the defendant corporation. Prior to entering into the contract Keller advised Parker that he desired to sink a mine upon the premises in question and wanted to make it of a capacity of two thousand tons, or more, in eight hours, and that he wanted cages, screens, dumps and other machinery of sufficient capacity and strength and durability to hoist and properly screen the coal and to bring it into a four compartment receiver hopper, preparatory to loading it. That he was not experienced in such matters of machinery and left the matter to Mr. Parker to determine what would and what would not be feasible to accomplish this purpose, and in pursuance and for the purpose of accomplishing the objects proposed by Mr. Keller, Mr. Parker prepared the contracts, specifications and details and represented that the machinery specified in the contract would be sufficient to accomplish the object sought to be obtained by Mr. Keller, and in the preparation of the contract Mr. Parker inserted a clause guarantieing the material, workmanship and operation of the machinery to be first-class. The real question here is, Was the machinery of the character, durability and quality contracted for, and was the machinery and its operation first-class 1

The evidence in this cause is quite voluminous and we will not undertake to consider it in detail.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

O. H. Jewell Filter Co. v. Kirk
65 N.E. 698 (Illinois Supreme Court, 1902)
Hyde v. Love Bros.
63 Ill. App. 43 (Appellate Court of Illinois, 1896)

Cite This Page — Counsel Stack

Bluebook (online)
180 Ill. App. 76, 1913 Ill. App. LEXIS 740, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eagle-iron-works-co-v-franklin-county-collieries-co-illappct-1913.