Eagle Fabricators, Inc v. Raymond Rakowitz D/B/A Redline Welding & Steel Services

CourtCourt of Appeals of Texas
DecidedApril 14, 2011
Docket14-09-01027-CV
StatusPublished

This text of Eagle Fabricators, Inc v. Raymond Rakowitz D/B/A Redline Welding & Steel Services (Eagle Fabricators, Inc v. Raymond Rakowitz D/B/A Redline Welding & Steel Services) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eagle Fabricators, Inc v. Raymond Rakowitz D/B/A Redline Welding & Steel Services, (Tex. Ct. App. 2011).

Opinion

Affirmed and Opinion filed April 14, 2011.

In The

Fourteenth Court of Appeals

___________________

NO. 14-09-01027-CV

Eagle Fabricators, Inc., Appellant

V.

Raymond Rakowitz d/b/a Redline Welding & Steel Services, Appellee

On Appeal from the County Civil Court at Law No. 3

Harris County, Texas

Trial Court Cause No. 902,394

OPINION

            In this contract case, a jury found that appellant Eagle Fabricators, Inc. owed Raymond Rakowitz more than $78,000.00 for his construction services.  Eagle asks us to reverse the judgment on procedural and evidentiary grounds.  Because Eagle has not shown that the trial court erred in charging the jury or in setting aside an order consolidating this case with another, and because the evidence is legally and factually sufficient to support the judgment, we affirm.

I.  Factual and Procedural Background

            The City of Houston hired State Construction, L.P. to act as the general contractor in building a fire station, a high school, and a middle school.  To ensure that subcontractors were paid, State Construction posted a bond issued by Liberty Mutual Insurance Company.  State Construction hired subcontractor Eagle Fabricators, Inc. to fabricate and erect the steel used in the three projects, and Eagle hired Raymond Rakowitz d/b/a Redline Welding & Steel Services as a second-tier subcontractor to erect the steel.  Rakowitz agreed to use the steel fabrications provided by Eagle and to perform the work in accordance with Eagle’s drawings.  The drawings contained Eagle’s “Notice to Customer & Erector” that “back charges for down time, corrective work or replaced materials will not be accepted unless authorized by Eagle Fab before such costs are incurred.”[1] 

            Over the course of construction, it was discovered that many of the steel parts Rakowitz was to erect were improperly fabricated, and he could not continue the work without performing additional work at an increased cost.  Although Eagle disputes it, Rakowitz testified that he obtained advance oral authorization from Eagle for all additional work and sent Eagle work orders on a weekly basis.  According to Rakowitz, Eagle first instructed him to send invoices for the additional work to another company that performed fabrication services as a subcontractor to Eagle.  Rakowitz did not have a contract with the other subcontractor, and no payments were made in response to the invoices.  Rakowitz testified that he also sent invoices to State Construction to show the general contractor that Eagle had not paid for all of the work he performed for Eagle. 

            Rakowitz last worked on the construction projects on or about June 7, 2007.  On June 11, 2007, Rakowitz sent Eagle invoices for the outstanding charges and stated that he could not continue working unless the additional charges were paid, but Eagle made no further payments.  A month later, Eagle sent State Construction a sworn proof of claim that Eagle owed $28,000.00 to Rakowitz’s company for work on the fire station alone.  Of that sum, Eagle identified $23,485.00 as the amount due for “extras or adjustments” to the original agreed contract price.  Less than a week after submitting the sworn proof of claim, Eagle wrote to State Construction asking that State Construction bar Rakowitz’s company from the high school jobsite, and a few days later, Eagle notified Rakowitz by certified mail that he was fired from the high school and middle school projects. 

            The parties were unable to come to any agreement over the outstanding charges, and Rakowitz sued Eagle in Harris County Civil Court at Law No. 3.  In addition, Rakowitz sued Liberty Mutual on the construction bond in Harris County Civil Court at Law No. 2, seeking payment of amounts owed for his work for Eagle. 

            Just over a month before this case was scheduled to be tried, Eagle moved to consolidate it with Rakowitz’s case against Liberty Mutual.  Over Liberty Mutual’s objection, the trial court initially granted the request.  A week later, and just eighteen days before the trial setting, Eagle filed a cross-claim against Liberty Mutual for payments that State Construction allegedly owed Eagle.  Rakowitz moved for rehearing of the consolidation order, and Liberty Mutual moved to strike Eagle’s cross-claim.  The trial court granted both motions on the same day, in effect restoring the status quo ante. 

            Although the evidence at trial was conflicting, Rakowitz presented testimony and documentary evidence that he had not been paid in full for his work on any of the three projects.  The evidence shows that Eagle agreed in the purchase order to pay Rakowitz $88,000.00 for work on the fire station.  Rakowitz testified that he completed 95% of that work, which entitled him to a progress payment of $83,600.00.  Of that amount, Eagle paid $60,000.00, leaving an outstanding balance of $23,600.00, exclusive of the change orders.  Regarding the high school, Rakowitz offered evidence that he was to be paid $43,000.00 for the work he performed pursuant to the purchase order, and because he had completed 75% of that work, he was entitled to a progress payment of $32,250.00.  Eagle had paid $22,000.00 of this amount, leaving a balance of $10,250.00.  Concerning the construction of the middle school, Eagle agreed to pay Rakowitz $20,000.00 for the work addressed in the purchase order, and Rakowitz testified that he completed 70% of the work and was entitled to a progress payment of $14,000.00.  Eagle had paid him only $10,000.00, leaving an outstanding balance of $4,000.00.  Thus, according to the evidence Rakowitz presented, Eagle owed him $37,850.00 for the portion of the work Rakowitz performed that was described in the purchase orders.

            In addition, Rakowitz presented evidence that he performed additional work on the fire station as reflected in two sets of change orders.  His charges on these orders were $16,720.00 and $16,210.00, neither of which had been paid.  Rakowitz also presented evidence that he performed additional work on the high school reflected in a change order for which he was due $5,320.00.  The total due on the change orders was $38,250.00.

            The sum of the disputed amounts Rakowitz sought to recover for his work on these three projects was $76,100.00.  In addition, he sought recovery of $2,250.80 Eagle owed for work he performed on a fourth project, referred to as the Fifth Ward Multiservice Center.  In this appeal, Eagle does not dispute its liability on this claim.  Overall, then, the sum of the damages Rakowitz sought was $78,350.80.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Golden Eagle Archery, Inc. v. Jackson
116 S.W.3d 757 (Texas Supreme Court, 2003)
In Re Kellogg Brown & Root, Inc.
166 S.W.3d 732 (Texas Supreme Court, 2005)
In Re Weekley Homes, L.P.
180 S.W.3d 127 (Texas Supreme Court, 2005)
In Re Allied Chemical Corp.
227 S.W.3d 652 (Texas Supreme Court, 2007)
Goodyear Tire and Rubber Co. v. Mayes
236 S.W.3d 754 (Texas Supreme Court, 2007)
In Re Schmitz
285 S.W.3d 451 (Texas Supreme Court, 2009)
Tribble & Stephens Co. v. Consolidated Services, Inc.
744 S.W.2d 945 (Court of Appeals of Texas, 1987)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Mayes v. Goodyear Tire and Rubber Co.
144 S.W.3d 50 (Court of Appeals of Texas, 2004)
Uranga v. Texas Workforce Commission
319 S.W.3d 787 (Court of Appeals of Texas, 2010)
Dal-Briar Corp. v. Baskette
833 S.W.2d 612 (Court of Appeals of Texas, 1992)
Guaranty Federal Savings Bank v. Horseshoe Operating Co.
793 S.W.2d 652 (Texas Supreme Court, 1990)
McFarland v. Sanders
932 S.W.2d 640 (Court of Appeals of Texas, 1996)
Downer v. Aquamarine Operators, Inc.
701 S.W.2d 238 (Texas Supreme Court, 1985)
Cain v. Bain
709 S.W.2d 175 (Texas Supreme Court, 1986)
In the Interest of B.L.D.
113 S.W.3d 340 (Texas Supreme Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
Eagle Fabricators, Inc v. Raymond Rakowitz D/B/A Redline Welding & Steel Services, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eagle-fabricators-inc-v-raymond-rakowitz-dba-redli-texapp-2011.