Eagle Electric Co. v. Raymond Construction Co.

420 A.2d 60, 1980 R.I. LEXIS 1839
CourtSupreme Court of Rhode Island
DecidedSeptember 29, 1980
Docket78-303-Appeal
StatusPublished
Cited by9 cases

This text of 420 A.2d 60 (Eagle Electric Co. v. Raymond Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eagle Electric Co. v. Raymond Construction Co., 420 A.2d 60, 1980 R.I. LEXIS 1839 (R.I. 1980).

Opinion

OPINION

MURRAY, Justice.

These consolidated contract actions are before us on the appeals of the defendant, Raymond Construction Co., Inc. (Raymond), from judgments entered in the Superior Court in favor of the plaintiffs, Eagle Electric Co., Inc. (Eagle), and Brown’s Floor Covering, Inc. (Brown’s). 1

*62 All three parties supplied labor and materials while engaged in renovating a building. In connection with that endeavor Eagle and Brown’s both sought payment from Raymond. When Raymond refused to pay, Eagle and Brown’s brought suit. The defendant contends that the trial justice erred in finding that Raymond, as a general contractor, entered into an express or implied agreement with Eagle and Brown’s, as subcontractors.

In late 1968 Progress for Providence, Inc. 2 (Progress for Providence), a community-action agency, rented the building located at 358 Public Street in the city of Providence to house a training school for its Concentrated Employment Program (CEP). In preparation for the opening of the school, Progress for Providence entered into a contract in September 1968 with Raymond in which Raymond agreed to reconstruct the west wall of the building and to make the building structurally safe, at a cost of $12,500. The city building inspector refused to issue the building permit, however, until all the building code requirements for a school had been met.

Raymond began the additional work on the property necessary to obtain the permit. In December 1968, after the additional work on the project was substantially completed, John Long (Long), the director of CEP and Raymond DeLeo, the president of Raymond, entered into a written “cost-plus” contract for that work completed and for that remaining to comply with the building inspector’s demands. A provision of the agreement provided that Long would represent the owner of the property. All facets of the work that Raymond was not accustomed to performing would be performed under subcontracts. Though Raymond would request bids from the subcontractors, Long was the person who would accept the bids with thé advice of Raymond and subject to the approval of the owner of the property. The contract provided further that CEP would reimburse Raymond for any payments it made to subcontractors for work performed pursuant to subcontracts.

Both Eagle and Brown’s provided materials and labor during the renovation project, but despite several requests to Raymond for payment, they were never paid for their efforts. Consequently, Eagle and Brown’s instituted separate actions against Raymond in the Superior Court. Raymond denied it was liable to plaintiffs for the cost of goods and services provided and filed a third-party complaint against Progress for Providence. Thereafter both Eagle and Brown’s filed direct claims for payment against Progress for Providence. These actions were consolidated 3 for trial and heard before a justice of the Superior Court in a jury-waived trial.

At trial, Joseph L. Izzi (Izzi), the president of Eagle testified to the following facts. John Leach (Leach), owner of the Public Street property, introduced Izzi to DeLeo at the project site sometime in November 1968. At that time DeLeo informed Izzi that Raymond would be the general contractor on the job and that Henry Velleca (Velleca), an employee of Raymond, would be the superintendent on the job. DeLeo and Izzi discussed the electrical work to be done, and DeLeo requested Izzi to provide him with a detailed estimate of the total cost of that work.

Eagle began work on the project shortly after Izzi’s conversation with DeLeo. Eagle and Raymond subsequently exchanged a series of written communications relating *63 both to the requested cost estimates and to payment for the work being done. In one letter DeLeo wrote to Eagle, he stated:

“A copy of your submittal has been submitted for approval. We have been advised, however, that more detailed cost information is required.
It sjs * *
“Your immediate submittal, without further delay will assist us to obtain the required authorization and, therefore, make it possible to submit a requisition for payment.”

In further support of its contention that it was working on the project as a subcontractor of Raymond, Eagle introduced into evidence the series of cost estimates that it provided to Raymond and a document that purportedly was an authorization signed by defendant’s foreman for it to perform additional work on the project. As work was completed, Eagle forwarded its invoices to Raymond for payment, but they were never paid. The total cost of the electrical work performed amounted to $16,500.15. At trial Izzi recalled Raymond’s promise to pay his company for the work:

“Q Mr. Izzi, did Mr. DeLeo or any other officer of the Raymond Construction Company tell you that you would be paid through Raymond Construction Company?
“A Yes, because I called several times to collect even the first requisition and we were told, well, the money wasn’t coming yet, hold on. Wait. You know, and we kept going with the project. Kept going. We were getting everything together and matter of fact I even checked to make sure there were no payments made at the time, but we continued pursuit to collect our money.
“Q You were told by Mr. DeLeo that Raymond Construction Company would pay you?
“A That’s right. They never told me they wouldn’t pay me. Never.”

Bernard J. Brown, who was the president of Brown’s, testified as follows. John Leach, for whom he had previously performed work, referred him to DeLeo regarding floor covering needed at the Public Street property. Brown subsequently entered into an oral agreement with DeLeo to install floor covering at the property.

After submitting an oral bid for an initial portion of the job, Brown's received an oral authorization from Raymond to begin the work. Brown’s had no prior contact with Progress for Providence before beginning the work and received no promise from it regarding payment for work done. However, Long, the director of CEP, was on the job site daily and was directing Brown’s work.

After the floor covering had been partially installed, Long requested that some additional work be done on the property. Long told Brown to forward the bill to Raymond. Brown contacted DeLeo, who authorized Brown’s to proceed with whatever work Long wanted done. DeLeo stated that Brown’s should forward the bill to him, and that Brown’s would be paid when Raymond was paid for the project by Progress for Providence. Brown’s eventually completed installing the floor covering and submitted a bill totaling $5,117 to Raymond for payment.

John Long also testified and stated that as director of CEP he received all the bids submitted for work on .the project and selected which contractors would do the work. Long testified that he was on the job site daily and directed the renovation work being done, but he admitted that the technical supervision of the work was done by Velle-ca, Raymond’s foreman.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Campbell v. Tiverton Zoning Board
Superior Court of Rhode Island, 2007
Hilley v. Lawrence
Superior Court of Rhode Island, 2007
Ashley v. Kehew
Superior Court of Rhode Island, 2007
Lopez v. Blanchard, 98-1452 (2003)
Superior Court of Rhode Island, 2003
Fitzpatrick v. Pare
552 A.2d 1185 (Supreme Court of Rhode Island, 1989)
White v. LeClerc
468 A.2d 289 (Supreme Court of Rhode Island, 1983)
Anderson v. Town of East Greenwich
460 A.2d 420 (Supreme Court of Rhode Island, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
420 A.2d 60, 1980 R.I. LEXIS 1839, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eagle-electric-co-v-raymond-construction-co-ri-1980.