Eagle CDI, Inc. v. Michael J. Orr

CourtCourt of Appeals of Tennessee
DecidedMay 31, 2017
DocketE2016-01399-COA-R3-CV
StatusPublished

This text of Eagle CDI, Inc. v. Michael J. Orr (Eagle CDI, Inc. v. Michael J. Orr) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eagle CDI, Inc. v. Michael J. Orr, (Tenn. Ct. App. 2017).

Opinion

05/31/2017

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE January 24, 2017 Session

EAGLE CDI, INC., ET AL. v. MICHAEL J. ORR, ET AL.

Appeal from the Chancery Court for Monroe County No. 18-704 J. Michael Sharp, Judge ___________________________________

No. E2016-01399-COA-R3-CV ___________________________________

This appeal involves a contract dispute between a general contracting company and a husband and wife who sought the company’s assistance to build a log cabin home. After the husband and wife defaulted on the original construction contract, the husband and wife and the company signed a second contract, a promissory note, for the remaining balance. The husband and wife subsequently defaulted on the promissory note. The trial court held that the husband and wife breached the second contract, the terms were clear and unambiguous, and a potential ambiguity in the first contract regarding a non- refundable deposit and/or retainer was legally irrelevant in determining the amount owed under the second contract. Because the second contract was clear and unambiguous, we hold that the total sum owed by the husband and wife is proper despite any ambiguity in the first contract. Further, we hold that the trial court properly denied the husband and wife’s motion to amend their answer because of undue delay. Accordingly, we affirm the trial court’s judgment.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed; Case Remanded

JOHN W. MCCLARTY, J., delivered the opinion of the Court, in which D. MICHAEL SWINEY, C.J., and FRANK G. CLEMENT, P.J., M.S., joined.

D. Mitchell Bryant, Athens, Tennessee, for the appellants, Michael J Orr and Mary E Orr.

Gary M. Prince and N. Craig Strand, Knoxville, Tennessee, for the appellees, Eagle CDI, Inc. and Dan Mitchell. OPINION

I. BACKGROUND

This appeal arises from a contract dispute between Eagle CDI, Inc. (“Eagle”), its president Dan Mitchell (“Mitchell”) and Mr. Michael Orr and Mrs. Mary Orr (collectively “the Orrs” and individually “Mr. Orr” and “Mrs. Orr”). The Orrs were seeking to build a log cabin house in Monroe County, Tennessee. The Orrs purchased a log cabin kit and then contacted Eagle, a general contractor, with the purpose of contracting for Eagle to aid in the construction process. The Orrs and Eagle entered into the Construction Contract on February 1, 2013.

The pertinent aspects of the Construction Contract described the costs to be paid to Eagle as follows:

CONTRACTOR shall be compensated for services herein on a modified cost plus basis. Cost shall be defined as follows:

(a) The materials and equipment reasonably and necessarily incurred in the construction herein. (b) Permits (c) Actual cost of on-site utilities, insurance (d) Actual costs of sub-contract items (e) The CONTRACTOR shall receive an Administrative Expense to be calculated at a rate of 15.5% of the costs stated above.

In addition to the costs described above, the CONTRACTOR shall receive additional compensation to be calculated as 10% of the costs stated above.

***

All sums shall be paid as follow: A Non-Refundable Deposit in the amount of $45,000 based upon the estimated scope of work requested to perform for construction of $498,430.62, with draws based upon work completion and this contract.

The record is undisputed that on February 4, 2013, the Orrs paid Eagle the $45,000 sum contracted for in the second clause quoted above. Eagle submitted Invoice #730 to the Orrs concerning the $45,000 payment. The invoice reflected the full payment of $45,000 -2- by the Orrs. The Description column on the invoice stated “ECDI DEPOSIT INVOICE NON-REFUNDABLE CUSTOMER DEPOSIT/RETAINER” and the Item column stated “DEPOSIT/RETAIN….”

Mr. Orr has significant construction experience, numerous Ph.Ds., and he has worked around the world in various capacities, including at Caterpillar. Mr. Orr and Eagle President Dan Mitchell arranged that Mr. Orr would oversee management of the project, and, as such, the 15.5% administrative fee mentioned in the contract would be waived. Mr. Orr directly paid subcontractors and directly purchased materials during this time. He did so through the use of a construction loan of approximately $343,200. However, Eagle later charged the Orrs the administrative fee beginning with the November 6, 2013 invoice. Eagle contends Mr. Orr ceased managing the project sufficiently, thus resulting in Eagle managing the project from that point forward.

The Orrs continued to pay Eagle as billed as reflected by Eagle’s invoices from February 2013 until November 2013. The Orrs failed to pay the amount reflected on Invoice #755, dated November 6, 2013, for the amount of $31,382.81. They further failed to pay a second billed amount reflected on Invoice #762 for $91,187.01 and dated February 27, 2014. Eagle continued to work on the project after the Orrs’ first failure to pay after Mr. Orr assured Mitchell in November 2013 that funds from an inheritance were forthcoming.

The Orrs and Mitchell met at an undetermined date in January 2014. Mr. Orr testified that he did not remember the details of the conversation. Mitchell testified that they discussed the completion of the project and the need for the construction financing to be completed and Eagle’s lien rights released so the Orrs could seek permanent financing for the house. Both parties agree a Promissory Note was mentioned as a way for the Construction Contract to be completed, allowing for permanent financing from a bank for the Orrs. The Orrs received the certificate of occupancy on January 24, 2014, and they had moved into the residence by that time.

The closing to finalize permanent financing on the house occurred on February 28, 2014. Although the record is not clear as to exactly when or how the February 27, 2014 invoice was received by the Orrs, it is undisputed that it occurred within a day of the closing meeting between the Orrs and a title agent of the bank. Mr. Orr testified they received the invoice concurrently with the Promissory Note at the meeting on February 28, 2014, whereas Mitchell testified that the invoice would have been emailed to the title agent and forwarded to the Orrs.

Mr. Orr testified that neither he nor his wife had seen the February 27, 2014 invoice for $91,000 or the Promissory Note until the night of the closing. Mitchell was not present, but a title agent representing Eagle was present at the closing. According to Mr. Orr, due to issues with the initial construction loan appraisal and the later, lower -3- permanent financing appraisal, he and his wife would incur severe financial penalties in the sum of $45,000 per month if the Orrs did not satisfy the Construction Contract and obtain permanent financing by February 28, 2014, the night of the closing.

The Promissory Note’s pertinent sections are as follows:

FOR VALUE RECEIVED, the undersigned customer(s) makes promise to pay to the order of EAGLE, CDI, Inc. and/or Dan W. Mitchell . . . the principal sum of One Hundred Twenty-Two Thousand, Five Hundred Sixty Nine and 82/100 Dollars ($122,569.82) . . . from the date of this Promissory Note, until paid in full . . . .

Repayment Terms: This Promissory Note is payable in One installment payment of $122,569.82, which is due and payable 30 days from the date that this Promissory Note is signed by all the obligors, and the Note Holder.

The Promissory Note also included a 10% interest for the initial 30 days plus a fixed rate at 10% per annum for the time period that the debt was unpaid. It also included a 5% late fee. The Promissory Note makes no mention or reference to the Construction Contract or the $45,000 initial payment by the Orrs.

Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eddie C. Pratcher, Jr. v. Methodist Healthcare Memphis Hospitals
407 S.W.3d 727 (Tennessee Supreme Court, 2013)
Kafozi v. Windward Cove, LLC
184 S.W.3d 693 (Court of Appeals of Tennessee, 2005)
Lee Medical, Inc. v. Paula Beecher
312 S.W.3d 515 (Tennessee Supreme Court, 2010)
Southern Constructors, Inc. v. Loudon County Board of Education
58 S.W.3d 706 (Tennessee Supreme Court, 2001)
Quebecor Printing Corp. v. L & B Manufacturing Co.
209 S.W.3d 565 (Court of Appeals of Tennessee, 2006)
Doe v. HCA Health Services of Tennessee, Inc.
46 S.W.3d 191 (Tennessee Supreme Court, 2001)
Rogers v. First Tennessee Bank National Ass'n
738 S.W.2d 635 (Court of Appeals of Tennessee, 1987)
Planters Gin Co. v. Federal Compress & Warehouse Co.
78 S.W.3d 885 (Tennessee Supreme Court, 2002)
Campora v. Ford
124 S.W.3d 624 (Court of Appeals of Tennessee, 2003)
Bokor v. Holder
722 S.W.2d 676 (Court of Appeals of Tennessee, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
Eagle CDI, Inc. v. Michael J. Orr, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eagle-cdi-inc-v-michael-j-orr-tennctapp-2017.