Eager v. Siwek Lumber & Millwork, Inc.

392 N.W.2d 691, 2 U.C.C. Rep. Serv. 2d (West) 1551, 1986 Minn. App. LEXIS 4724
CourtCourt of Appeals of Minnesota
DecidedSeptember 2, 1986
DocketC6-86-193, C3-86-796
StatusPublished
Cited by6 cases

This text of 392 N.W.2d 691 (Eager v. Siwek Lumber & Millwork, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eager v. Siwek Lumber & Millwork, Inc., 392 N.W.2d 691, 2 U.C.C. Rep. Serv. 2d (West) 1551, 1986 Minn. App. LEXIS 4724 (Mich. Ct. App. 1986).

Opinion

OPINION

FOLEY, Judge.

Following judgment for Thomas J. Eager in the amount of $25,760.67 for breach of warranties, Siwek Lumber & Millwork, Inc. moved for a new trial and/or amended findings. Eager counter-moved for attorney’s fees under the Consumer Fraud Act, Minn.Stat. § 325F.69 (1984), and for prejudgment and post-judgment interest. The trial court denied Siwek’s motions for a new trial and/or amended findings but granted Eager’s motions awarding attorney’s fees and interest on the judgment in its order of January 2, 1986. Siwek Lumber appeals from that order (C6-86-193) raising the issues addressed here.

Subsequently, the trial court entered an amended judgment according to its order *693 of January 2, as modified by its order of January 30, fixing the attorney’s fees. Si-wek Lumber brought a separate appeal from the amended judgment (C3-86-796) again challenging the award of attorney’s fees and now also challenging the award of pre-judgment interest. By order of this court, the two appeals have been consolidated. We affirm.

FACTS

After contracting to tear down and build a new garage for Anna Jermsta, Thomas J. Eager, a Minneapolis contractor, and Jermsta purchased a garage kit from Si-wek Lumber for $2,337.17. The purchase was made after Joseph Siwek, president of Siwek Lumber, expressly and impliedly warranted to Eager that the materials and supplies in the kit conformed to the Minneapolis Building Code.

Eager subsequently tore down Jermsta’s existing garage and had begun constructing the new garage from the kit when a Minneapolis building inspector halted construction because the materials did not conform to the building code. Eager immediately notified Joseph Siwek and sought replacement or supplement of the materials which did not meet the building code or a refund of his money for the entire kit. Siwek admitted that he refused this as well as Eager’s subsequent demands.

At trial, Siwek noted that he did send an invoice to the building inspector indicating that the framing lumber (two-by-fours) shipped from its supplier was of the required grade. Siwek admitted that this invoice did not state the grade of the unstamped two-by-sixes supplied in the kit for construction of rafters or the plywood. The building code required that these materials also have mill grade stamps. No cure was offered for other materials in the kit which were inadequate in quantity or quality to construct the garage according to the building code.

Eager was unable to continue construction of the garage because Siwek refused to replace or supplement the inadequate materials in the kit or to refund his money. Eager also testified that he lacked the funds to purchase replacement parts. Jermsta subsequently collected $2,086 on Eager’s construction bond for his default and the city revoked Eager’s contractor’s license, thus preventing him from engaging in further construction projects. Eager then commenced this suit.

Following trial, the court found that Eager had revoked his acceptance of the nonconforming goods within a reasonable time after discovery of the nonconformity. The court also found that Eager accepted the goods without knowledge that they failed to conform to local building codes and that his immediate notification of Siwek Lumber after learning of the nonconformance constituted a timely revocation of acceptance of the goods. The court further found that nonconformity of the kit to local building codes substantially impaired the value of the kit to Eager, that this impairment involved the basis of the bargain and that Eager did not discover the impairment because he had relied on Siwek’s assurances and warranties. In addition, the trial court found that this revocation occurred before any substantial change in the goods since Eager stopped construction immediately after the building inspector told him the materials did not conform with the city’s building code. The only change in goods was that Eager had begun to assemble the materials.

Eager was awarded total damages of $25,760.67 for Siwek’s breach of express and implied warranties, consisting of the following:

a) the price of the “kit”, $2,337.17;
b) lost profits in the amount of $450.00 for lost payment for the labor of removal of the pre-existing structure;
c) loss of a contractor’s bond which obligated the [respondent] to reimburse his carrier of the bond in the amount of $2,086.00;
d) lost profits in the amount of $887.50 for the anticipated profit from construction of the garage;
*694 e) lost profits and opportunities from the loss of the plaintiffs bond in the amount of $20,000.00.

Eager had also moved for attorney’s fees. This claim was rejected in the original judgment because the court found that no contract or statute permitted such recovery.

Siwek moved for a new trial or an order amending the findings and judgment. Eager counter-moved for pre-judgment and post-judgment interest and attorney’s fees under Minn.Stat. § 8.31, subd. 3a (1984), which authorizes the recovery of attorney’s fees for violations of the Consumer Fraud Act, Minn.Stat. § 325F.69 (1984). The court found that Siwek’s misrepresentation to Eager constituted a violation of this Act and that Siwek’s conduct was “egregious.” Therefore, attorney’s fees were awarded in a January 2, 1986 order denying Siwek’s motions. This order also awarded Eager pre-judgment and post-judgment interest and required Eager to submit an affidavit regarding reasonable attorney’s fees. Following submission of affidavits by both parties on reasonable attorney’s fees, the court awarded Egan $3,750 in attorney’s fees in its January 30 order.

Siwek Lumber appeals from the January 2, 1986 order and subsequently from the April 9, 1986 amended judgment which incorporated the orders of January 2 and 30.

ISSUES

1. What is reviewable here?

a. on appeal from an order denying a motion for a new trial?

b. on appeal from an amended judgment?

2. Did the trial court err in awarding consequential damages?

3. Did the trial court err in awarding attorney’s fees under Minn.Stat. §§ 8.31, subd. 3a and 325F.69 (1984)?

ANALYSIS

1. Appealability.

A. Order Denying New Trial. Although appellants assert four issues in their appeal from the January 2, 1986 court order denying them a new trial, their appeal must be limited to those issues specifically addressed to the trial court:

It is imperative that the request for [a] new trial and the Rule 59.01 basis therefor * * * be stated explicitly and with specificity.

Swartwoudt v. Swartwoudt, 349 N.W.2d 600, 602 (Minn.Ct.App.1984).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Holiday Recreational Industries, Inc. v. Manheim Services Corp.
599 N.W.2d 179 (Court of Appeals of Minnesota, 1999)
McNamara v. Nomeco Building Specialties, Inc.
26 F. Supp. 2d 1168 (D. Minnesota, 1998)
Church of the Nativity of Our Lord v. WatPro, Inc.
491 N.W.2d 1 (Supreme Court of Minnesota, 1992)
Church of Nativity of Our Lord v. Watpro, Inc.
474 N.W.2d 605 (Court of Appeals of Minnesota, 1991)
Park-Lake Car Wash, Inc. v. Springer
394 N.W.2d 505 (Court of Appeals of Minnesota, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
392 N.W.2d 691, 2 U.C.C. Rep. Serv. 2d (West) 1551, 1986 Minn. App. LEXIS 4724, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eager-v-siwek-lumber-millwork-inc-minnctapp-1986.