E & T Skyline Construction, LLC v. Talisman Casualty Insurance Company, LLC

District Court, S.D. New York·Decided November 6, 2023·No. 1:19-cv-08069·Unknown

Opinion

UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF NEW YORK

E & T SKYLINE CONSTRUCTION, LLC, 19-cv-8069 (JSR) Plaintiff, FINDINGS OF FACT AND -v- CONCLUSIONS OF LAW

TALISMAN CASUALTY INSURANCE

COMPANY, LLC,

Defendant.

JED S. RAKOFF, U.S.D.J.: This case concerns a construction dispute about the installation of custom windows, imported from Italy, at a luxury condominium building in Manhattan. Plaintiff E & T Skyline Construction, LLC (“E&T”), the general contractor responsible for the building’s construction, hired subcontractor NY Renaissance Corp. (“NYR”) to deliver and install the windows. To cover its losses in case NYR failed to perform, E&T obtained a performance bond of $1,850,000 from defendant Talisman Casualty Insurance Company, LLC (“Talisman”). As it turned out, E&T terminated NYR for default and came knocking to Talisman to pay the bond. Talisman refused, pointing to E&T’s own failure to fulfill each of its obligations under the bond agreement, which was a precondition for Talisman’s payment. E&T sued Talisman for breach of the bond agreement, and the Court held a four-day bench trial. The Court now holds that Talisman is not liable, and sets forth the following findings of fact and conclusions of law. I. Findings of Fact Based on the parties’ joint statement of facts, exhibits, deposition designations, and –- critically –- the trial testimony and the Court’s assessment of the witnesses’ demeanor and credibility, the Court makes the following factual findings: 1. E&T was the general contractor of a project (the “Project”) to construct a 40-story condominium building located at 30 East 31st Street in Manhattan. Tr. 6, 25.1 2. On November 17, 2016, E&T entered into a subcontract with NYR to deliver and install rectangular windows and custom triangle- shaped windows, along with related materials, at 30 East 31st Street. ECF No. 125 (“Joint Statement of Facts”), at 2; PX 1 (“Subcontract”).2 3. This dispute involves the custom windows, which NYR was to install on floors 33 through 40. Tr. 13. 4. On February 7, 2017, Talisman issued to E&T a performance bond of $1,850,000 for NYR’s work on the Project, with NYR as the

principal and Talisman as the surety. PX 4 (“Bond Agreement”). 5. The Bond Agreement provides that Talisman’s “obligation under this Bond” arises “[i]f there is no Owner Default.” Bond Agreement § 3. 6. The Bond Agreement defines “Owner Default” as “[f]ailure of the Owner . . . to pay the Contractor as required under the

1 Citations to “Tr.” refer to the trial transcript. 2 Citations to “PX” refer to plaintiff’s trial exhibits; citations to “DX” refer to defendant’s trial exhibits. Construction Contract or to perform and complete or comply with the other material terms of the Construction Contract.” Id. § 14.4. 7. Because the “Bond [was] issued for an agreement between a Contractor and subcontractor, the term Contractor” in the Bond Agreement “shall be deemed to be Subcontractor and the term Owner shall be deemed to be Contractor.” Id. § 15; Tr. 211. 8. The subcontract between E&T and NYR included a rider with additional terms and various schedules laying out the scope of work. Subcontract. 9. Although the subcontract initially listed a completion date

of January 17, 2018 for NYR’s work, it would not have been possible for NYR to complete its work by then because the building’s concrete superstructure –- the responsibility of a separate subcontractor with no involvement by NYR -- had not been fully erected. Tr. 175-77. 10. The building’s concrete superstructure was not complete until “May or June of 2018.” Tr. 177. 11. On March 8, 2019, E&T accepted a revised schedule that NYR proposed. Tr. 208, 368-69; DX 8 (“Revised Schedule”). 12. The revised schedule accepted by E&T, which listed June 2, 2019 as the end date for “finalizing the installation” of the custom windows, stated that the schedule was “subject to . . . the Owner

providing the upper floors of the site available for installation (free of current debris and protrusions into the window openings).” Revised Schedule at 1. 13. In NYR’s letter proposing the revised schedule, “NYR request[ed] that the Owner . . . compel[] its contractors to remove debris from the upper floors and otherwise make installation possible including by removing the protrusions currently in place.” Id. at 1- 2. 14. E&T understood the letter’s reference to “the Owner” to refer to E&T as the Project’s general contractor. Tr. 211. 15. On April 16, 2019, Nick Carranza of NYR sent an email to Kevin Tolbert of E&T, and others, stating, “[T]here is no way to install windows even if they were onsite today. There are openings

that still need framing which have nothing to do with our windows.” DX 9 at 1. 16. In another email sent on the same day, also from Nick Carranza to Kevin Tolbert and others, Carranza described “numerous obstructions throughout floors 33-39 preventing NYR from putting in windows.” Id. at 2. “Just to give one example,” the email stated, “the outriggers for the scaffolding on [the] 35th floor is [sic] preventing any installation of windows in this location and will continue to do so until the scaffolding is removed.” Id. 17. That email attached a “Custom Shape Window Onsite Conditions Report” that Carranza had prepared. Id. at 4. The report states that

its purpose is “to illustrate the onsite conditions of floors 33-39 where the custom shape windows are to be installed.” Id. The report contained pictures and written descriptions of impediments to installation of those windows on each of floors 33 to 39. Id. at 4- 13. 18. According to the report, windows could not be installed on the 39th floor because of “steel beams protruding from the window openings,” around which there was “no way to maneuver.” Id. at 4. 19. According to the report, windows could not be installed on the 38th floor because of “metal panels piled throughout the floor which need to be removed in order to start work.” Id. 20. According to the report, windows could not be installed on the 37th floor because, on the south elevation of the building, “there

[was] plywood blocking the openings and the hoist anchor/support [was] coming through the window opening.” Id. at 5. On the north elevation of the 37th floor, to which NYR did have access, NYR had “started to waterproof openings” for the windows. Id. 21. According to the report, windows could not be installed on the 36th floor because, on the north elevation, “there [were] piles of drywall and framing on the ground in front of the window openings,” and on the south elevation, “there [were] steel beams dispersed on the floor as well as plywood in front of the openings . . . preventing access to these windows.” Id. 22. According to the report, windows could not be installed on

the 35th floor because of “various suspended scaffolding outriggers protruding from the window openings.” Id. 23. According to the report, windows could not be installed on the 34th floor because of “steel beam supports as well as a shanty in front of the window openings.” Id. at 5-6. 24. According to the report, windows could not be installed on the south elevation of the 33rd floor because of “piles of metal framing lying on the floor in front of the window openings that need to be moved . . . prior to installation.” Id. at 6. NYR had begun waterproofing window openings on those parts of the floor that it could access. Id. 25. The photographs attached to the report corroborated the

Free access — add to your briefcase to read the full text and ask questions with AI

E & T Skyline Construction, LLC v. Talisman Casualty Insurance Company, LLC, (S.D.N.Y. 2023).

E & T Skyline Construction, LLC v. Talisman Casualty Insurance Company, LLC (E & T Skyline Construction, LLC v. Talisman Casualty Insurance Company, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.