E & T Skyline Construction, LLC v. Talisman Casualty Insurance Company

CourtCourt of Appeals for the Second Circuit
DecidedJanuary 15, 2025
Docket24-369
StatusUnpublished

This text of E & T Skyline Construction, LLC v. Talisman Casualty Insurance Company (E & T Skyline Construction, LLC v. Talisman Casualty Insurance Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
E & T Skyline Construction, LLC v. Talisman Casualty Insurance Company, (2d Cir. 2025).

Opinion

24-369 E & T Skyline Construction, LLC v. Talisman Casualty Insurance Company, LLC

UNITED STATES COURT OF APPEALS FOR THE SECOND CIRCUIT

SUMMARY ORDER

RULINGS BY SUMMARY ORDER DO NOT HAVE PRECEDENTIAL EFFECT. CITATION TO A SUMMARY ORDER FILED ON OR AFTER JANUARY 1, 2007, IS PERMITTED AND IS GOVERNED BY FEDERAL RULE OF APPELLATE PROCEDURE 32.1 AND THIS COURT’S LOCAL RULE 32.1.1. WHEN CITING A SUMMARY ORDER IN A DOCUMENT FILED WITH THIS COURT, A PARTY MUST CITE EITHER THE FEDERAL APPENDIX OR AN ELECTRONIC DATABASE (WITH THE NOTATION “SUMMARY ORDER”). A PARTY CITING A SUMMARY ORDER MUST SERVE A COPY OF IT ON ANY PARTY NOT REPRESENTED BY COUNSEL.

At a stated term of the United States Court of Appeals for the Second Circuit, held at the Thurgood Marshall United States Courthouse, 40 Foley Square, in the City of New York, on the 15th day of January, two thousand twenty-five.

Present: DEBRA ANN LIVINGSTON, Chief Judge, JOHN M. WALKER, JR., SARAH A. L. MERRIAM, Circuit Judges. _____________________________________

E & T SKYLINE CONSTRUCTION, LLC,

Plaintiff-Appellant,

v. 24-369

TALISMAN CASUALTY INSURANCE COMPANY, LLC,

Defendant-Appellee. ____________________________________

For Plaintiff-Appellant: BRET L. MCCABE (Joseph P. Asselta, on the brief), Forchelli Deegan Terrana LLP, Uniondale, NY.

For Defendant-Appellee: MICHAEL F. KUZOW (Michael F. McGowan, on the brief), Westermann Sheehy Samaan & Gillespie, LLP, East Meadow, NY. Appeal from a judgment and order of the United States District Court for the

Southern District of New York (Rakoff, J.).

UPON DUE CONSIDERATION, IT IS HEREBY ORDERED, ADJUDGED,

AND DECREED that the judgment and order of the district court are AFFIRMED.

Plaintiff-Appellant E & T Skyline Construction, LLC (“E&T”), a general contractor

responsible for the construction of a luxury condominium in Manhattan, entered into a

subcontract (the “Subcontract”) with NY Renaissance Corp. (“NYR”). Under the

Subcontract, NYR was responsible for delivering and installing custom windows for the

condominium construction project. To cover its losses in case NYR failed to perform,

E&T obtained a performance bond of $1.85 million from Defendant-Appellee Talisman

Casualty Insurance Company, LLC (“Talisman”). E&T subsequently terminated NYR

for failing to perform and demanded Talisman pay the bond. Talisman refused on the

grounds that E&T had failed to fulfill its own obligations under the Subcontract, which

was a precondition of Talisman’s payment. E&T sued and, after a four-day bench trial,

judgment was entered in favor of Talisman on November 6, 2023. E&T appeals from

this judgment as well as the district court’s order denying E&T’s motion to alter or amend

the judgment under Rule 59(e) of the Federal Rules of Civil Procedure entered on January

11, 2024.

On appeal, E&T argues that the district court was wrong to conclude that the terms

of a March 8, 2019 revised schedule formed part of the Subcontract. E&T also contends

2 that the district court erred in concluding that it breached its agreement with NYR

regardless of whether the terms of the March 8 revised schedule were enforceable. We

assume the parties’ familiarity with the underlying facts and the record of prior

proceedings, to which we refer only as necessary to explain our decision to AFFIRM.

I. Forfeiture

On March 8, 2019, NYR sent a letter (the “March 8 Letter”) to E&T that proposed

a revised schedule for the delivery and installation of the custom windows. NYR

conditioned its ability to meet the revised schedule on, inter alia, E&T “providing the

upper floors of the site available for installation (free of current debris and protrusions

into the window openings)” and “compel[ling] its contractors to remove debris from the

upper floors and otherwise make installation possible including by removing the

protrusions currently in place.” Joint App’x 935-36. In its Findings of Fact and

Conclusions of Law, dated November 6, 2023, the district court concluded that there was

“no dispute that the terms of the March 8, 2019 revised schedule form part of the

subcontract.” Special App’x 16. E&T thereafter moved to alter or amend the judgment

pursuant to Rule 59(e), arguing for the first time that because the Subcontract required

modifications be made via a signed writing, the fact that the March 8 Letter was unsigned

meant its terms were not an enforceable part of the parties’ agreement. The district court

denied the motion, declining to consider E&T’s argument because it was one that E&T

“could have raised in its post-trial proposed findings of fact and conclusions of law but

3 did not.” Special App’x 32 (internal quotation marks and citation omitted). We agree

with the district court that E&T could have raised the issue of whether the March 8 Letter

was part of the Subcontract earlier and has therefore forfeited this argument.

We “[g]enerally . . . will not consider an argument on appeal that was raised for

the first time below in a motion for reconsideration.” Analytical Surveys, Inc. v. Tonga

Partners, L.P., 684 F.3d 36, 53 (2d Cir. 2012) (internal quotation marks and citation

omitted). Although we retain “broad discretion to consider issues not timely raised

below,” Off. Comm. of Unsecured Creditors of Color Tile, Inc. v. Coopers & Lybrand, LLP, 322

F.3d 147, 159 (2d Cir. 2003) (internal quotation marks omitted), “the circumstances

normally do not militate in favor of an exercise of discretion . . . where those arguments

were available to the parties below and they proffer no reason for their failure to [timely]

raise the arguments below,” Doe v. Trump Corp., 6 F.4th 400, 410 (2d Cir. 2021) (citation

and alterations omitted). We are more likely to exercise “this discretion where necessary

to avoid a manifest injustice or where the argument presents a question of law and there

is no need for additional fact-finding.” Allianz Ins. Co. v. Lerner, 416 F.3d 109, 114 (2d

Cir. 2005) (internal quotation marks and citation omitted).

E&T contends that it had no obligation to argue that the March 8 Letter was not

part of the Subcontract because Talisman never affirmatively characterized the letter’s

terms as part of the agreement. But it is hardly surprising that Talisman did not feel it

necessary to make that argument, because E&T repeatedly treated the March 8 Letter as

4 binding on the parties. For example, E&T sent two default notices that both alleged that

NYR was materially breaching the Subcontract for “failing to meet the deadline in NYR’s

recovery schedule dated March 8, 2019.” Joint App’x 1044, 1106. In arguing for

summary judgment, E&T acknowledged that the parties had “accepted” the March 8

Letter which thus “became a binding schedule under the Subcontract” and that NYR’s

“undisputed failure” to meet the revised schedule “is a proper ground for termination.”

Pl.’s Mem. of L. in Support of Mot. for Sum. J., E & T Skyline Constr., LLC v. Talisman Cas.

Ins. Co., LLC, No. 19CV08069(AT) (S.D.N.Y. April 1, 2021), ECF 98 at 14. At trial, E&T’s

president testified that E&T “accepted [the March 8 Letter] because it was the best

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. United States Gypsum Co.
333 U.S. 364 (Supreme Court, 1948)
Anderson v. City of Bessemer City
470 U.S. 564 (Supreme Court, 1985)
United States v. Susan M. Braunig
553 F.2d 777 (Second Circuit, 1977)
Allianz Insurance Company v. Regina Lerner
416 F.3d 109 (Second Circuit, 2005)
Analytical Surveys, Inc. v. Tonga Partners, L.P.
684 F.3d 36 (Second Circuit, 2012)
Sacerdote v. New York University
9 F.4th 95 (Second Circuit, 2021)
Siemens Energy, Inc. v. PDVSA
82 F.4th 144 (Second Circuit, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
E & T Skyline Construction, LLC v. Talisman Casualty Insurance Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/e-t-skyline-construction-llc-v-talisman-casualty-insurance-company-ca2-2025.