E. Keeler Co. v. Schott

1 Pa. Super. 458, 1896 Pa. Super. LEXIS 182
CourtSuperior Court of Pennsylvania
DecidedApril 13, 1896
DocketAppeal, No. 1
StatusPublished
Cited by5 cases

This text of 1 Pa. Super. 458 (E. Keeler Co. v. Schott) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
E. Keeler Co. v. Schott, 1 Pa. Super. 458, 1896 Pa. Super. LEXIS 182 (Pa. Ct. App. 1896).

Opinion

Opinion by

Rice, P. J.,

The plaintiffs’ cause of action, as set forth in their statement and bill of particulars, was the breach of a parol contract made on September 10, 1894, whereby the plaintiffs agreed to provide materials, and construct and put up in the defendant’s hotel a heating apparatus to consist of a furnace, steel boiler, steam pipes and fittings and radiators, for which the defendant agreed to pay $900. They allege that they at once entered upon the work, and that the hoiler was nearly completed and ready [462]*462for shipment, when the defendant discharged them from any further performance and declared “ the job off.” They claimed to recover the profits they would have made if they had been permitted to carry out the contract, and the cost of the labor and materials expended in the construction of the boiler. The defendant admits that there were negotiations between him and the plaintiffs on September 10, but denies that there was a contract. He alleges that it was then stated that nothing was to be considered a contract until reduced to writing and signed by both parties, and that the plaintiffs’ representative agreed to send catalogues showing the different styles of radiators, and a contract with specifications, which he should examine, and, if satisfactory, sign. The main question of fact, on the trial, was whether an oral contract was made on September 10, and upon this question there was a conflict of testimony. The trial resulted in a verdict and judgment in favor of the plaintiffs for an amount which indicates that both branches of their claim were allowed. We shall take up the assignments of error in their order.

1. The defendant’s letter of September 20 was offered for a specific purpose, namely: to show that the defendant recognized the existence of a contract between him and the plaintiffs. Taken in connection with the letter to which it was a reply it was very strong corroborative evidence of the plaintiffs’ allegation; and the defendant’s attempt' to explain away its language was extremely weak. The court would have been justified in commenting, with emphasis, upon the letter as evidence of the alleged contract. Nevertheless, the questions, whether the parties had entered into a contract, and what were its terms, were for the jury and were to be decided upon,a fair view of all the evidence,, and not the letter alone. In his general charge and in his answer to the plaintiffs’ first point, the learned judge submitted these questions to the jury. But the plaintiffs’ second point was so worded as to permit the jury to find that the plaintiffs, acting on the faith of the letter, prepared and made the boiler, and might, therefore, be entitled to recover its price, although there was no prior contract. If it does not mean that, it was purposeless. But the plaintiffs’ evidence was to the effect that the work was begun immediately after the conclusion of the negotiations on September 10, [463]*463and that the boiler was nearly completed when the defendant’s letters were received. The plaintiffs’ counsel, appreciating the force of this objection to the point, makes an ingenious and plausible argument to show that the number of men employed might have done the work between September 20, and September 25, when the order was countermanded. True, the work might have been done in that period, but we have looked through the record in vain for any affirmative evidence that it was done. The fact was susceptible of clear and unequivocal proof. It was peculiarly within the knowledge of 'the plaintiffs, and upon the theory which they asked the jury to consider the burden of proof was upon them. But if it were clear that the jury found that the plant was contracted for on September 10, it would be immaterial whether the boiler was constructed before or after the letter. Is it clear that the jury so found ? The substance of the point is, that if the plaintiffs acted on the letter then they would be entitled to recover, not only the price of the boiler, but damages for the defendant’s refusal to accept the plant “as contracted for.” How contracted for; on September 10, or by the letter? The point is ambiguous. The court had instructed the jury as to the obligations created by the contract of September 10. The point seems to present a second theory upon which the plaintiffs might possibly recover. The counsel may not have so intended, but the point seems to convey the impression that if the plaintiffs acted on the letter a liability on the part of the defendant would be created, which might not otherwise arise; in other words, that the letter acted on would, of itself, create a contract by which the defendant would be bound.

The same idea was conveyed in the general charge, when the learned judge says: “ the plaintiffs had a right to understand it according to the usual and ordinary meaning of the words used, and if they acted upon that meaning then it would bind Mr. Schott whether he used the words he wanted or intended to use or not.” But for what would it bind him ? Clearly, if not acted on, it would not, of itself, bind him to pay the price that had been discussed in the negotiations of September 10, if no contract was made then; and if, as the plaintiffs alleged, a contract was made then, the letter added nothing to its binding force. The letter alone did not make a contract for the breach [464]*464of which the plaintiffs could recover damages, and in the absence of affirmative evidence that the plaintiffs acted on the letter it was error to permit the jury to find that they did, and that a liability on the part of the defendant was thereby created. “It is the duty of a judge,” said Mr. Justice Williams, “to instruct the jury upon every question of law involved in a ease trying; but it is not his duty to answer points that raise questions in thesi merely, or that rest upon the assumption of a fact of which there is no such evidence as to justify the jury in finding it: ” Heffner v. Chambers, 121 Pa. 84. As we have said, the letter was very strong evidence of the existence of the contract alleged in the declaration. Under the testimony the attention of the jury should have been confined strictly to the issue thus raised. If, failing to prove the contract alleged in the pleadings, the plaintiffs were to be permitted to shift their ground and recover for work done, or upon the ground of work done, pursuant to the order contained in the letter, it was within their power, and incumbent on them to show that the work was done after the letter was received. Then they might reasonably ask a jury to find that it was done “ in consequence of what Schott wrote them,” but not otherwise. For these reasons we are of opinion that the affirmance of the plaintiffs’ second point was error, and we cannot say that it was harmless. The first assignment is sustained.

2. Where an offer is made to prove certain facts, some of which are admissible in evidence, while others are inadmissible, the offer is incompetent as a whole; and the court is not bound to separate the offer and admit the competent portion of it, although it may do so in its discretion: Smith v. Arsenal Bank, 104 Pa. 518. The offer embraced in the second assignment was not, as a whole, competent; therefore the court committed no error in rejecting it. Evidence of the cost of a steam plant similar to the one placed in defendant’s house was wholly irrelevant unless coupled with an offer to show that the plant was similar to the one alleged to have been contracted for. We suppose that it would be proper to show by any competent testimony what would be the actual cost of such a plant as that contracted for.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Helt v. Berman
38 A.2d 386 (Superior Court of Pennsylvania, 1944)
McKee, Tr. v. Ward
137 A. 599 (Supreme Court of Pennsylvania, 1927)
Frank Pure Food Co. v. Dodson
126 A. 243 (Supreme Court of Pennsylvania, 1924)
Hooper, Seving & Co. v. Bromley Bros. Carpet Co.
11 Pa. Super. 634 (Superior Court of Pennsylvania, 1899)
Funke v. Allen
74 N.W. 832 (Nebraska Supreme Court, 1898)

Cite This Page — Counsel Stack

Bluebook (online)
1 Pa. Super. 458, 1896 Pa. Super. LEXIS 182, Counsel Stack Legal Research, https://law.counselstack.com/opinion/e-keeler-co-v-schott-pasuperct-1896.