E. J. Albrecht Co. v. United States

63 F. Supp. 769, 105 Ct. Cl. 353, 1946 U.S. Ct. Cl. LEXIS 12
CourtUnited States Court of Claims
DecidedJanuary 7, 1946
DocketNo. 45579
StatusPublished
Cited by1 cases

This text of 63 F. Supp. 769 (E. J. Albrecht Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
E. J. Albrecht Co. v. United States, 63 F. Supp. 769, 105 Ct. Cl. 353, 1946 U.S. Ct. Cl. LEXIS 12 (cc 1946).

Opinion

JoNES, Judge,

delivered the opinion of the court:

This suit grows out of the construction by plaintiff of an outlet channel, the purpose of which was to bypass excess water around the Sardis Dam on the Little Tallahatchie River near Sardis, Mississippi. Plaintiff had no part in the construction of the dam itself, which was being built at the same time.

The contract called for various items of work of which excavation, fill and concrete were a major part. The outlet structure comprised in its essential details an intake which was to be provided with gates to control the flow of water; an approach channel leading from above the dam to the gates; a conduit leading from the gates through an existing ridge or hill; a large and deep pool with concrete bottom, walls and baffles termed a stilling basin, into which the conduit emptied, and an outlet channel which was to connect the stilling basin with the river bed below the dam.

The contract as to excavation, fill and backfill was on a unit price basis. Prior to the submission of its bid plaintiff had inspected the site and not only investigated the test bor-ings of the defendant but also made its own borings.

Notice to proceed on the work was received by the contractor May 11, 1938, and work was begun five days later. The original contract period expired on June 15, 1939, but extensions of time totaling 156 calendar days were allowed by the Government and the work was completed and ac[383]*383cept'ed on November 18,1939, within the time fixed for completion by the extensions granted. No liquidated damages are involved. '

Plaintiff’s claim for compensation is based upon increased costs for excavation, rolled fill and backfill. Plaintiff’s expenditures for these three items were $142,120 more than it received as payment therefor.

It alleges that delays and increased costs were caused by two items: (1) improper refusal of the Government to permit plaintiff to use dry borrow pit material in rolled fill operations and (2) delay in agreeing to pay for the increased cost of imported concrete aggregate, which .in turn postponed excavation in the stilling basin from the dry season to the rainy season.

The rolled fill controversy

The rolled fill was intended to produce a densely compacted and more or less impervious surface in various parts of the structure. As defined in the specifications, the process of making rolled fill was to spread the materials in layers of . about 6 inches, then harrow the same and subsequently roll it with a roller having a series of staggered knobs spread over its cylindrical surface. The specifications in considerable detail set forth such matters as the depth to which the teeth of the harrow should penetrate, the weight of the roller and the number of passes of the roller over the material. They also particularly emphasized the necessity of having the correct moisture content in the material so as to give the greatest possible compaction.

Material portions of the contract relating to the rolled fill are set out in Finding 8. The following excerpts therefrom have a direct bearing upon the present issue:

(4) Should the material as dumped, spread, or moistened be too wet to permit, in the opinion of the contracting officer, the securing of the desired compaction, the rolling shall be delayed until the material has dried to the required consistency. * * * The contracting officer may require at any time that any or all of the operations cease * * * when the moisture content of the excavated materials is excessive, such excavated materi[384]*384als shall bo stock-piled at approved locations adjacent to the work until their use is authorized. No additional payment for such stock-piling will be made nor will any additional payment be made for the hauling of this material to its final position in the dam.

The specifications also stated (2-07 (e)):

Borrow Areas. — It is anticipated that sufficient material suitable for required fills will be available from the excavations prescribed by these specifications. Additional material for fill, if required, shall be procured from borrow areas “C,” “C-l,” and “D,” located as shown on the drawings.

In May 1938 plaintiff started its excavation work in the approach channel area and in the conduit area. These materials would have been suitable for use as rolled fill but for the fact that they were too wet to be immediately used and they were therefore placed in stock piles. The material in the stock piles failed to dry properly in time for its use as rolled fill in the approach channel. It was necessary for plaintiff to either harrow the top of the stock piles or do additional harrowing after the material was put in place.

Plaintiff complained to the project engineer about the extra labor and cost involved in the drying of the material, and requested that in lieu of using the stock pile material it be permitted to excavate from borrow pits where the material was relatively dry. Plaintiff was told that it could use borrow pit material for rolled fill if desired, but that no payment could be authorized for excavating such material.

The real issue therefore is not that plaintiff was refused the use of borrow pit materials in lieu of the stock-piled material that was too wet at the time, but that the contracting officer, through his representative, the project engineer, did not feel at that time that the Government should incur the added expense of 25 cents per cubic yard for excavation from the borrow pits when it had already paid the same amount for the excavation of material which was suitable for rolled fill with the exception of its moisture content.

Plaintiff orally asked for written instructions on this issue but the project engineer advised him that he had no written instructions to give except what was in the contract. Plain[385]*385tiff cites this as a reason why no appeal was taken during the progress of the work, stating that plaintiff was under no obligation to appeal from a matter as to which the contracting officer had refused to give written instructions.

Paragraph 1-19 of the specifications relating to protests and appeals states in part:

* * * If the contractor considers any work required of him to be outside the requirements of the contract, or if he considers unfair any action or ruling of the inspectors or contracting officer, he shall ask for written instructions or decision from the contracting officer immediately. Any protest based upon such instructions or decision, or claim otherwise arising under the contract, including a request for extension of time under Article 9, shall be submitted to the contracting officer within the period specified in the contract. If the contractor is not satisfied with the ruling of the contracting officer he may, where so provided in the contract, make written appeal to the Chief of Engineers. * * *

To plaintiff’s position we can not agree. The above-quoted portion not only permits a protest based upon written instructions, but, in addition, on any claim otherwise arising under the contract. If plaintiff, having asked for them, had been refused written instructions this fact alone could have properly formed the basis of a protest and a subsequent appeal. If the project engineer, as the authorized representative of the contracting officer had refused to make a decision a different question would have been presented.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

New York Shipbuilding Corporation v. The United States
385 F.2d 427 (Court of Claims, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
63 F. Supp. 769, 105 Ct. Cl. 353, 1946 U.S. Ct. Cl. LEXIS 12, Counsel Stack Legal Research, https://law.counselstack.com/opinion/e-j-albrecht-co-v-united-states-cc-1946.