E. Hathaway Construction, Inc. v. Eli

CourtCourt of Appeals of South Carolina
DecidedMay 4, 2004
Docket2004-UP-289
StatusUnpublished

This text of E. Hathaway Construction, Inc. v. Eli (E. Hathaway Construction, Inc. v. Eli) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
E. Hathaway Construction, Inc. v. Eli, (S.C. Ct. App. 2004).

Opinion

THIS OPINION HAS NO PRECEDENTIAL VALUE.  IT SHOULD NOT BE CITED OR RELIED ON AS PRECEDENT IN ANY PROCEEDING EXCEPT AS PROVIDED BY RULE 239(d)(2), SCACR.

THE STATE OF SOUTH CAROLINA
In The Court of Appeals


E. Hathaway Construction, Inc., Respondent,

v.

David Eli, a/k/a David Eliyahu, Four Seasons, Rebecca Shirley, David L. Shirley and the Shirley Family Limited Partnership, Defendants

Of Whom David Eli, a/k/a David Eliyahu, Four Seasons is the, Appellant.


Appeal From Horry County
 J. Stanton Cross, Jr., Master-In-Equity


Unpublished Opinion No. 2004-UP-289
Heard April 7, 2004 – Filed May 4, 2004


AFFIRMED IN PART, REVERSED IN PART, AND REMANDED


John M Leiter, of Myrtle Beach, for Appellant.

Norwood David DuRant, of Surfside Beach, for Respondent.

PER CURIAM:  E. Hathaway Construction, Inc. brought this action against David Eli, a/k/a David Eliyahu, Rebecca Shirley, David L. Shirley, and the Shirley Family Limited Partnership to foreclose on a mechanic’s lien and for breach of contract seeking to recover money owed for the construction of a building on land Eli leased from the Shirleys.  The Master-In-Equity awarded Hathaway a judgment on its breach of contract claim, determined the total debt on the mechanic’s lien, including a set-off in favor of Eli as a result of a leak, and ordered the foreclosure of the lien.  The master also awarded Hathaway attorney’s fees.  We affirm in part, reverse in part, and remand. 

FACTS

In March of 2000, Hathaway and Eli entered into a verbal contract for the construction of a building on land leased from the Shirleys.  The building was to be used by Eli for selling beach merchandise.  The parties agreed Eli was to pay cost plus fifteen percent. 

The original plan for the building called for the installation of a glass panel front to the building.  After construction began, Eli requested a change to the shape of the front of the building by adding more glass and an angled front.  Hathaway used a Kawneer prefabricated system for the front of the building. 

Eli made a portion of the payments required under the verbal contract.  However, he eventually stopped making payments and Hathaway ceased work on the building.  On August 31, 2000, Hathaway received a certificate of occupancy for the building, and no further work was completed on the building. 

Hathaway filed an Affidavit of Mechanic’s Lien against the real property and the “owners of the fee simple estate.”  The notice of mechanic’s lien made no mention of the leasehold interest.  On November 9, 2000, Hathaway filed the current action, seeking to foreclose on the mechanics lien and also seeking damages for breach of contract.  The Shirleys answered and cross-claimed against Eli for indemnification.  In his answer, Eli asserted he was entitled to a setoff for the leaking glass front.  He also counterclaimed for damages suffered by the construction deficiencies. 

The Master granted Eli a $20,000 set-off for Eli “to repair the roof that has a leak.”  He held Hathaway was entitled to a judgment of $243,705.24 and ordered foreclosure of the leasehold interest. 

Eli filed a motion for reconsideration.  In it he alleged the court erred in concluding Hathaway had a valid mechanic’s lien against the leasehold interest where the lien failed to mention the leasehold and only mentioned the fee simple interest.  Eli also alleged the court erred: 1) in enforcing the foreclosure against Eli’s wife because she was never made a party to the action; 2) in awarding penalties and interest to Hathaway based upon subcontractors not being paid; 3) in awarding prejudgment interest; 4) in awarding attorney’s fees under the contract; 5) in awarding one half of the accountant’s fee; 6) in determining the amount of the setoff to which Eli was entitled; and (7) in including certain sums in the total debt secured by the mechanic’s lien. 

The Master filed an Amended Final Order in which he reaffirmed his previous order, but changed some of the amounts.  He held the total debt secured by the mechanic’s lien was $201,752.69, which included $183,626.41 as the contract balance, prejudgment interest, attorney’s fees, court fees and the setoff in favor of Eli in the amount of $20,000.00.  The master also held Hathaway was entitled to a judgment in the amount of $239,128.59, which included the above total debt plus half of the accountant’s fee equaling $6,352.50 and penalties and interest charged by subcontractors equaling $31,023.40.  Although the attorney’s fees are included in the calculation of the mechanic’s lien, the order states the master awarded the attorney’s fees “under the terms of the contract.” 

STANDARD OF REVIEW

The foreclosure of a mechanic’s lien is an action at law.  T.W. Morton Builders, Inc. v. von Buedingen, 316 S.C. 388, 397, 450 S.E.2d 87, 92 (Ct. App. 1994).  An action for breach of contract seeking money damages is also an action at law.  Sterling Dev. Co. v. Collins, 309 S.C. 237, 240, 421 S.E.2d 402, 404 (1992).  In an action at law, tried without a jury, the master’s findings of fact will not be disturbed on appeal unless found to be without evidence which reasonably supports the Master’s findings.  Townes Assocs., Ltd. v. City of Greenville, 266 S.C. 81, 86, 221 S.E.2d 773, 775 (1976).

LAW/ANALYSIS

I.       Validity of the Foreclosure

Eli argues the Master erred in foreclosing on the leasehold interest pursuant to the mechanic’s lien because the mechanic’s lien did not mention the leasehold interest.  Additionally, he asserts the mechanic’s lien only referenced the owners of the fee simple interest, the Shirleys, and not the owners of the leasehold interest, which was foreclosed.  We find Eli failed to preserve this issue.

The mechanic’s lien statute requires the lien to include “a description of the property intended to be covered by the lien sufficiently accurate for identification, with the name of the owner of the property . . .” S.C. Code Ann. § 29-5-90 (Supp.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

South Carolina National Bank v. Cook
354 S.E.2d 562 (Supreme Court of South Carolina, 1987)
Pond Place Partners, Inc. v. Poole
567 S.E.2d 881 (Court of Appeals of South Carolina, 2002)
Patterson v. Reid
456 S.E.2d 436 (Court of Appeals of South Carolina, 1995)
Jackson v. Speed
486 S.E.2d 750 (Supreme Court of South Carolina, 1997)
Townes Associates, Ltd. v. City of Greenville
221 S.E.2d 773 (Supreme Court of South Carolina, 1976)
Sterling Development Co. v. Collins
421 S.E.2d 402 (Supreme Court of South Carolina, 1992)
T.W. Morton Builders Inc. v. Von Buedingen
450 S.E.2d 87 (Court of Appeals of South Carolina, 1994)
MI Co., Ltd. v. McLean
482 S.E.2d 597 (Court of Appeals of South Carolina, 1997)
Manning v. City of Columbia
377 S.E.2d 335 (Supreme Court of South Carolina, 1989)
Timothy C. Doughtie Advertising, Inc. v. Nelsen Steel & Wire Co.
324 S.E.2d 329 (Court of Appeals of South Carolina, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
E. Hathaway Construction, Inc. v. Eli, Counsel Stack Legal Research, https://law.counselstack.com/opinion/e-hathaway-construction-inc-v-eli-scctapp-2004.