E. H. Marhoefer, Jr., Co. v. State

25 Ill. Ct. Cl. 139, 1965 Ill. Ct. Cl. LEXIS 26
Court of Claims of Illinois·Decided May 28, 1965·No. No. 4914·Published

Opinion

Perlin, C.J.

This action was instituted by claimant, E. H. Marhoefer, Jr., Go., an Illinois corporation, for damages in the sum of $493,544.88 resulting from alleged unreasonable delays in completion of a construction contract, which was awarded to claimant by the State of Illinois. At hearing, claimant increased its ad damnum to $591,695.60.

At the conclusion of a lengthy hearing, during which the parties submitted a great number of exhibits, books and documents, the following stipulation was entered into by and between the attorneys for claimant and the Attorney General of Illinois representing respondent:

Stipulation of Fact

“It is hereby stipulated by and between the parties hereto, by their respective attorneys, after trial of the within cause before the Special Commissioner appointed to hear same, and upon presentation of all the evidence both oral and documentary, as follows:
“1. That the Court has jurisdiction of the parties to and the subject matter of this cause.
“2. That the complaint was brought under Chap. 37, Par. 439.8 of the Ill. Rev. Stats.
“3. That claimant is in the general contracting business, and has been so engaged for many years last past, and has offices at 2424 North 25th Avenue, Franklin Park, Illinois.
“4. That claimant is the sole owner of the claim herein alleged against the State of Illinois, and that no other person or corporation has any interest in said claim.
“5. That, on or about August 21, 1956, claimant as a general contractor submitted to the Department of Public Works and Buildings of the State of Illinois its proposal for the general work for the Illinois Psychiatric Institute State Hospital to be erected at 1601-1659 West Taylor Street, Chicago, Illinois.
“6. Prior to the submission of said proposal, the respondent required bidders to include in same certain allowances for hardware, which allowance was included in claimant’s proposal submitted August 21, 1956 to respondent.
“7. That claimant’s proposal was accepted, and a contract was entered into between claimant and respondent, dated September 18, 1956, pursuant to which contract claimant agreed to do the work described therein and in the plans and specifications and other contract documents for a total contract amount of $4,259,524.00 comprised as follows:
‘Scope of Wobk:
‘Proposal No. 1 for the General Work for the Illinois Psychiatric Institute State Hospital (Eleven Story Building), 1601-1659 West Taylor Street, Chicago, Illinois, as shown on the drawings, and as specified, the sum of. .$4,297,924.00
‘Proposal No. 9 for the General Work (Eleven Story Building) — in event that the electrically controlled locks for the Patients’ Rooms and Stairway Doors are not installed, thus changing the special shaped door frames for these doors to standard door frames, and changing the locks to standard locks, as shown on the drawings, and as specified, except that the electrically operated locks shall be provided for Door B to Stair W, Door B to Stair N, Door B to Stair S, and Door H2 from Corridor 500 W to Public Corridor 500, in all stories from the 5th to the 11th, inclusive, is accepted and authorized, deduct the sum of................................ 43,700.00
$4,254,224.00
‘Proposal No. 11 for the General Work — in event that the installation of ‘Detention Screens’ in lieu of ‘Protective Screens’ at all windows where the protective screens are indicated, as shown on the drawings, and as specified, is accepted and authorized, add the sum of.. 5,300.00
$4,259,524.00’
“8. That said contract originally provided a hardware allowance of $168,000.00, which said amount was modified by Addendum No. 2 in the amount of $38,000.00 from said hardware allowance by the elimination of certain locks and other hardware, all as is more particularly set out in Proposal No. 9, which contained a deductive hardware allowance of $38,000.00. That the final allowance for hardware provided for under the contract documents amounted to $168,000.00 less the $38,000.00 covering the change in locks and other hardware requirements bringing the net hardware allowance under the contract documents to $130,000.00. That said net hardware allowance of $130,000.00 was the true and correct amount of same, and is the amount used by respondent in computing the hardware allowance credits and debits with respect to claimant’s payments. That, claimant’s claim that it is entitled to $38,000.00 because of an error of the respondent in computing the correct amount of said allowances after giving consideration to the deductive Proposal No. 9 is not supported tire evidence, and, therefore, the Court finds in favor of respondent and against claimant with respect to said claim for $38,000.00 hardware allowance alleged credit.
“9. That claimant commenced construction of the building pursuant to the plans and specifications and other contract documents, and experienced certain small delays in pouring the first floor concrete slab, which said delays were caused by contractors of respondent, but that said delays were not unreasonable, and, therefore, claimant is not entitled to reimbursement from respondent for additional costs incurred by reason of these small delays.
“10. That respondent unreasonably delayed claimant in choosing a hardware supplier, and in approving the finished hardware schedules required by the metal door frame and metal door manufacturer in order to properly and promptly manufacture said door frames and doors. That because of this delay the metal door frames and doors could not be manufactured in time to meet the progress schedule of claimant, and that this in turn interfered with the sequence of claimant’s work on the interior masonry walls of the project, and in so doing decreased efficiency of performance of said work by claimant. That these delays were without fault on the part of claimant or its subcontractor, suppliers, employees or agents but solely the fault of respondent, and said delays were unreasonable in extent. That, as a result of said delays, claimant was obliged to incur additional costs for both direct and indirect labor, equipment rental expense, and overhead expenses in the total amount of $197,961.75, and is entitled to reimbursement from respondent for said amount.
“11. That during the course of the construction respondent changed the design of windows in the curtain wall of the building from center pivoted windows to double hung windows. That this change was not provided for in the plans and specifications or other contract documents on which claimant originally bid, and was not made a part of it until on or about April 26, 1957 after all the engineering and design of the curtain wall and its center pivoted windows, as originally required by the plans and specifications and other contract documents, had been completed.

Free access — add to your briefcase to read the full text and ask questions with AI

E. H. Marhoefer, Jr., Co. v. State, 25 Ill. Ct. Cl. 139, 1965 Ill. Ct. Cl. LEXIS 26 (Ill. Super. Ct. 1965).

25 Ill. Ct. Cl. 139 (E. H. Marhoefer, Jr., Co. v. State) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.