E. H. Boerth Co. v. Lad Properties

82 F.R.D. 635, 1979 U.S. Dist. LEXIS 12353
CourtDistrict Court, D. Minnesota
DecidedMay 16, 1979
DocketNo. Civ. 4-74-164
StatusPublished
Cited by19 cases

This text of 82 F.R.D. 635 (E. H. Boerth Co. v. Lad Properties) is published on Counsel Stack Legal Research, covering District Court, D. Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
E. H. Boerth Co. v. Lad Properties, 82 F.R.D. 635, 1979 U.S. Dist. LEXIS 12353 (mnd 1979).

Opinion

MEMORANDUM AND ORDER

MacLAUGHLIN, District Judge.

This matter comes before the Court on defendant L. A. “Vern” Donnay’s motions for a judgment notwithstanding the verdict, for a new trial, to vacate the order for judgment and judgment entered thereon or, in the alternative, for a remittitur of the damages. Plaintiff E. H. Boerth Company, a securities underwriter, brought this action against defendants in 1974, alleging that defendants’ course of conduct amounted to breach of contract, common law fraud, and a violation of SEC Rule 10b-5 and the parallel Minnesota provision, Minn.St. § 80A.01. After a two-week trial, the jury found defendant L. A. Donnay liable under each of plaintiff’s four theories, and awarded $35,000 as damages under the breach of contract theory, $5,000 as damages for loss of professional reputation, $5,000 for the securities act violations and $5,000 under the common law fraud theory. In addition, pursuant to the finding of liability under the common law fraud count, the jury awarded $80,000 in punitive damages. On February 2, 1979, this Court entered an order for judgment in the total amount of $139,024.38. In this order for judgment, the Court found that plaintiff was entitled to recover damages in the amount of $35,000 for breach of contract, $5,000 for loss of professional reputation, $80,000 in punitive damages, and $19,024.38 for attorneys’ fees and costs awarded by the Court pursuant to Section 80A.01 of the Minnesota Statutes. In order to avoid a multiple or duplicative recovery, plaintiff was not allowed to recover the $5,000 sums awarded under an out-of-pocket measure of damages pursuant to the securities act and common law fraud findings of liability. Thus, the order for judgment awarded a total amount of $139,024.38.

This lawsuit arises out of the parties’ involvement in the underwriting of limited partnership units in a real estate project known as the Landings, which was to be located in Brooklyn Park, Minnesota. Defendant The Landings, a Minnesota limited partnership, was established to complete [639]*639construction of the Landings project and to obtain income from the townhouse units, six of which were previously constructed in 1968 on a 1.4-acre parcel known as the “Villas,” and 144 units which were to be constructed on an adjacent 20-acre parcel. Defendant LAD Properties, a Minnesota corporation, was hired by The Landings to manage the construction of the Landings project. Defendant L. A. “Vern” Donnay, a real estate developer, was at all relevant times the owner of all the common stock of LAD Properties, as well as the general partner of The Landings.

In an agency agreement dated August 6, 1973, between The Landings by its general partner L. A. Donnay, and plaintiff E. H. Boerth Company, plaintiff agreed to use its best efforts to procure purchasers for 69 limited partnership units for the Landings project. Edwin Boerth, the operator and owner of the E. H. Boerth Co., signed the agreement on behalf of the plaintiff. This agency agreement provided that unless commitments for the 69 units were obtained by plaintiff by December 31 of 1973, the offering would be terminated, and plaintiff would not receive any compensation for its underwriting efforts. However, in the event that plaintiff received commitments for the 69 limited partnership interests by the end of 1973, plaintiff would be entitled to 10 percent of the proceeds of the offering. As the 69 limited partnership interests were to be sold for $10,000 each, in the event they were all sold by December 31, 1973, plaintiff would have been entitled to $69,000 as compensation. In paragraph 4.a. of the agency agreement, The Landings, by its general partner L. A. Donnay, promised: In further consideration of the agreement of the Underwriter herein contained, the Partnership by its General Partner agrees as follows:

a. The Partnership will use its best efforts to cause the Registration Statement to receive clearance and will advise you promptly and, if requested by you, will confirm such advice in writing . . . (iv) of the happening of any event which in the judgment of the Partnership or the General Partner makes any material statement in the Registration Statement or the Prospectus untrue or which requires the making of any changes in the Registration Statement or the Prospectus in order to make the statements therein not misleading.

This agency agreement was subsequently amended in order to clarify that plaintiff could appoint selected broker-dealers to assist in effecting sales of the limited partnership units.

This litigation has had a long history of discovery and procedural disputes1 which need not at this time be fully explored. The facts adduced at trial should be briefly outlined, however, in order to provide a basis for an evaluation of defendant Don-nay’s motions. The gist of plaintiff’s action here was premised on material omissions which defendants failed to provide and certain misrepresentations made in connection with the development of The Landings, all of which contributed to Edwin Boerth’s continued participation in the doomed [640]*640project. These misrepresentations and omissions, to a substantial extent, concerned the financial affairs of the Landings project and the Donnay enterprises. One area of dispute concerned the refinancing of the mortgage on the 1.4-acre “Villas” parcel which contained six townhouse units. As the financing on the 1.4-acre parcel expired in October of 1973, it was necessary for the Donnay companies to obtain financing on the parcel from a new lender in order to insure the success of the Landings project. This refinancing was never obtained. Plaintiff claimed, and the jury could have found, that personnel of L. A. Don-nay’s companies, including L. A. Donnay himself, repeatedly assured Edwin Boerth that such refinancing was being, would be, or had been obtained by the defendants. Insofar as the construction on the 20-acre site was concerned, this construction was funded through a loan to LAD Properties, Inc., made by the First Wisconsin National Bank of Milwaukee. In a letter dated October 3,1973, this lender advised Dean Peterson of the Donnay enterprises that no further draws could be made on The Landings project as the lender’s inspectors estimated an over disbursement of approximately $400,000. The letter also indicated that over disbursements had occurred on numerous other Donnay projects, and that further draws would not be approved. Although L. A. Donnay was aware of this problem, he did not inform Edwin Boerth, or cause any of his employees to inform Mr. Boerth. Moreover, plaintiff’s evidence also made it abundantly clear that construction loan funds earmarked for The Landings were diverted to other projects as the financial resources of the Donnay empire crumbled. Mr. Donnay, despite intimate knowledge of the financial losses his companies had sustained, testified that he had no knowledge of such diversions and made no efforts to investigate whether or not funds intended for The Landings were utilized for other Donnay projects. Mr. Boerth was not notified of these diversions by L. A. Donnay or the personnel of his companies. Furthermore, Mr. Donnay admitted that he had knowledge that subcontractors on the Landings projects had walked off the job, possibly as early as July of 1973, although he refrained from acknowledging that during the relevant time period he had knowledge that the reason for their walking off was because they were not being paid. Mr. Boerth, again, was not informed of these occurrences by either Mr. Donnay or his subordinates.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Grain Land Coop
978 F. Supp. 1267 (D. Minnesota, 1997)
United Laboratories, Inc. v. Kuykendall
437 S.E.2d 374 (Supreme Court of North Carolina, 1993)
Brooks v. Doherty, Rumble & Butler
481 N.W.2d 120 (Court of Appeals of Minnesota, 1992)
Putnam Resources v. Pateman
757 F. Supp. 157 (D. Rhode Island, 1991)
Avirgan v. Hull
691 F. Supp. 1357 (S.D. Florida, 1988)
Pork Producers, Ltd. v. Bailey (In Re Bailey)
75 B.R. 314 (M.D. Tennessee, 1987)
Sieren v. American Family Financial Services of Wisconsin, Inc.
356 N.W.2d 408 (Court of Appeals of Minnesota, 1984)
Lionti v. Lloyd's Insurance Company
709 F.2d 237 (Third Circuit, 1983)
Lionti v. Lloyd's Insurance
709 F.2d 237 (Third Circuit, 1983)
Clayton Brokerage Co. of St. Louis v. Pilla
632 S.W.2d 300 (Missouri Court of Appeals, 1982)
Labor Relations Commission v. Fall River Educators Ass'n
416 N.E.2d 1340 (Massachusetts Supreme Judicial Court, 1981)
Creque v. Cintron
17 V.I. 69 (Supreme Court of The Virgin Islands, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
82 F.R.D. 635, 1979 U.S. Dist. LEXIS 12353, Counsel Stack Legal Research, https://law.counselstack.com/opinion/e-h-boerth-co-v-lad-properties-mnd-1979.