E Electrical Contracting, Inc. v. Siemens Industry, Inc., Building Technologies Division

CourtDistrict Court, E.D. New York
DecidedJuly 13, 2021
Docket1:19-cv-00223
StatusUnknown

This text of E Electrical Contracting, Inc. v. Siemens Industry, Inc., Building Technologies Division (E Electrical Contracting, Inc. v. Siemens Industry, Inc., Building Technologies Division) is published on Counsel Stack Legal Research, covering District Court, E.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
E Electrical Contracting, Inc. v. Siemens Industry, Inc., Building Technologies Division, (E.D.N.Y. 2021).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF NEW YORK --------------------------------------------------------- x

E ELECTRICAL CONTRACTING, INC.,

Plaintiff, OPINION & ORDER

-against- 19-cv-223 (NG)(ST)

SIEMENS INDUSTRY, INC., BUILDING TECHNOLOGIES DIVISION, Defendant. --------------------------------------------------------- x SIEMENS INDUSTRY, INC., Third Party Plaintiff, -against- SKANSKA USA BUILDING INC., SKANSKA USA CIVIL DIVISION NORTHEAST INC., and WALSH CONSTRUCTION COMPANY II, LLC, individually and as Joint Venture of SKANSKA WALSH DESIGN BUILD JOINT VENTURE, and THE OHIO CASUALTY INSURANCE COMPANY, Third-Party Defendants. --------------------------------------------------------- x GERSHON, United States District Judge:

Third-party defendants Skanska USA Building Inc., Skanska USA Civil Northeast, Inc., Walsh Construction Company II, LLC, and Skanska Walsh Design Build Joint Venture (collectively “Skanska”) move, pursuant to Federal Rule of Civil Procedure 12(b)(6), to dismiss the Second Amended Third-Party Complaint (“SATPC”) filed by defendant/third-party plaintiff Siemens Industry, Inc., Building Technologies Division (“Siemens”). For the reasons that follow, the motion is granted in part and denied in part. I. Allegations of the Second Amended Third-Party Complaint The following facts are taken from the SATPC and are accepted as true for the purposes of this motion. This action arises out of a construction project commonly referred as the LaGuardia

Airport Central Terminal Building Replacement (the “Project”). Skanska, the general contractor for the Project, entered into an agreement with Siemens, a subcontractor, dated May 23, 2017 (the “Contract”).1 Siemens agreed to design and install a fire alarm system for the Site Wide Central Terminal Building, consisting of the Central Heat and Refrigerant Plant, Final Cooling Tower, Concourse B, Concourse A, Concourse B Pedestrian Bridge, Concourse A Pedestrian Bridge, West Parking Garage Connector, Headhouse, and Central Hall. Skanska established the schedule for Siemens’s work. According to the Contract, in the event that Skanska issues an acceleration directive to Siemens concerning the performance of the work and that directive is due “to the fault of [Skanska], [Siemens] shall be entitled to an equitable adjustment of the [Contract] Amount or an extension of time as reasonably determined by [Skanska].” SATPC at

¶¶ 16, 19. On August 2, 2017, Siemens entered into a subcontract (the “Subcontract”) with plaintiff E Electrical Contracting, Inc. (“EEC”) for the installation of certain fire alarm system work. Unlike the Contract, which is a Design-Bid-Build contract wherein Siemens was hired to design and install a site-wide Fire Alarm System, the Subcontract is a Bid-Build contract wherein EEC

1 There are two contracts at issue in this case—the contract between Skanska and Siemens and the contract between Siemens and plaintiff EEC. The parties occasionally refer to the contract between Skanska and Siemens as a “Subcontract” or the “Prime Subcontract.” However, it is referred to in the original complaint and in Siemens’s Third-Party Amended Complaint as the “Contract,” and is more clearly understood as the Contract in the context of this motion, in contrast to the subcontract that exists between Siemens and EEC. I will therefore refer to the contract between Skanska and Siemens as the Contract and the contract between Siemens and EEC as the Subcontract. was hired to build and install the work that Siemens designed. The Subcontract incorporates the entire Contract “as an integral part of the Subcontract.” Id. at ¶ 20. The reverse, however, is not true, as the Contract does not incorporate the Subcontract. Subject to due performance, the Contract is a lump sum agreement in the amount of $18,730,315, while the value of the

Subcontract is $14,435,000. An Amendment to the Subcontract provides that EEC’s invoices will be paid by Siemens only on a “pay-when-paid basis, within seven (7) days of [Siemens’s] receipt of payment from [Skanska] for [EEC’s] Work.” Id. at ¶ 25. Additionally, according to the SATPC, when Skanska directs changes to the project schedule that cause EEC to incur additional costs, EEC is entitled to compensation only to the extent that Skanska pays Siemens for those costs. According to the Contract, Siemens’s work on Concourse B was slated to begin on July 31, 2017 and to be completed by July 1, 2018. Both Siemens and EEC allege that work on Concourse B did not, in fact, begin until months after it was scheduled to start. The SATPC alleges that, because of delays by Skanska, the start of work on Concourse B and Headhouse was

delayed but without concomitant extensions of contractual deadlines, causing a compressed schedule. According to Siemens, it incurred additional costs as a result of these delays. Siemens therefore submitted a claim to Skanska for additional compensation on February 12, 2019. Skanska, however, refused to pay the claim or discharge any time-related damages. On March 27, 2019, Skanska directed Siemens to add a second shift of twenty workers by April 1, 2019 for the Headhouse project. Siemens communicated this directive to EEC on March 28, 2019, but EEC refused to provide the additional labor. Siemens then “placed EEC in default and partially terminated its scope of work.” Id. at ¶ 60. Siemens hired a second electrical subcontractor, B&G Electrical Contractors of N.Y., Inc. (“B&G”), to replace EEC, at a substantial cost to Siemens. II. Procedural History EEC filed an initial complaint against Siemens on January 11, 2019, alleging damages

arising from work on Concourse B and Headhouse. Its claims are based on the allegation that Siemens imposed its design obligations on EEC, even though EEC was hired not to design, but only to build and install the Fire Alarm System. On May 31, 2019, Siemens filed a third-party complaint against Skanska and the Ohio Casualty Insurance Company, the surety on the performance bond that EEC procured in accordance with its obligations under the Subcontract. Siemens thereafter sought a pre-motion conference for an anticipated motion to dismiss EEC’s initial complaint, while Skanska sought a pre-motion conference on its anticipated motion to dismiss Siemens’s third-party complaint. Following a conference on September 12, 2019, at which both proposed motions were discussed, Siemens filed its first amended third-party complaint on October 25, 2019, and EEC filed an amended complaint on November 15, 2019

(“Amended Complaint”). Siemens amended its third-party complaint a second time, filing the SATPC on December 6, 2019. EEC’s Amended Complaint seeks “a declaration of rights and responsibilities of the parties under the Subcontract, including, but not limited to, a declaration that (A) there has been a cardinal change to the Subcontract, (B) EEC is not required to perform any further work under the Subcontract, (C) that EEC’s refusal to perform such work is not a breach of the Subcontract and (D) EEC is entitled to recover . . . its costs and damages incurred in performing the work thus far required by Siemens to be performed as a consequence of Siemens’ cardinal changes.” Am. Compl. at ¶ 41. Additionally, EEC seeks damages for breach of contract, account stated, and quantum meruit. In the SATPC, Siemens brings claims against Skanska for breach of contract, contractual indemnity, declaratory judgment, common-law indemnification, equitable contribution, quantum

meruit, and account stated. Skanska now moves to dismiss the SATPC.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Connecticut Bar Ass'n v. United States
620 F.3d 81 (Second Circuit, 2010)
Patane v. Clark
508 F.3d 106 (Second Circuit, 2007)
ATSI Communications, Inc. v. Shaar Fund, Ltd.
493 F.3d 87 (Second Circuit, 2007)
Wolff v. Rare Medium, Inc.
171 F. Supp. 2d 354 (S.D. New York, 2001)
Strasbourger v. . Leerburger
134 N.E. 834 (New York Court of Appeals, 1922)
Chisholm-Ryder Co. v. Sommer & Sommer
70 A.D.2d 429 (Appellate Division of the Supreme Court of New York, 1979)
Harsco Corp. v. Segui
91 F.3d 337 (Second Circuit, 1996)
Chambers v. Time Warner, Inc.
282 F.3d 147 (Second Circuit, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
E Electrical Contracting, Inc. v. Siemens Industry, Inc., Building Technologies Division, Counsel Stack Legal Research, https://law.counselstack.com/opinion/e-electrical-contracting-inc-v-siemens-industry-inc-building-nyed-2021.